Sea Acceptance Tests (SAT) for final delivery of eighth Landing Craft Tank (LCT) vessel built by Anadolu Shipyard (ADK) completed satisfactorily.

The eighth vessel (TCG Ç-158) LCT will be ready to be delivered on August 29th 2012, having completed its Sea Acceptance Test.


ANADOLU Shiphard has already delivered the first seven vessels of the LCT project (TCG Ç-151; TCG Ç-152; TCG Ç-153; TCG Ç-154; TCG Ç-155; TCG Ç-156; TCG Ç-157) between March and July 2012.

The shipyard points out that LCT program will be completed on time as planned 37 months after the start of the project, adding that this is the first Turkish Navy project undertaken by a so-called a privately owned shipyard, to be completed on time.
 

Related News

Hungary Detains Captain of Cruise Ship Involved in Danube Collision ESL Shipping's First Plug-in Hybrid Vessel Electramar Christened Silver Ships Delivers First Four Coastal Fast Response Boats Part of Philippine Subic Bay Shipyard Leased Out for Offshore Wind No Shortage of Good Ideas to Address the Mariner Shortage