Fire-stricken Icebreaker Overhauled

July 30, 2015

SENER concludes the Almirante Irizar icebreaker engineering works for re-outfit and overhaul

SENER reports it has completed the engineering works relating to the re-outfit and overhaul of the Almirante Irizar icebreaker following a fire accident in an Antarctic season.
The icebreaker vessel Almirante Irizar docked for repair (Photo: SENER)
Scheme of the ship areas damaged (Image: SENER)
The icebreaker vessel Almirante Irizar docked for repair (Photo: SENER)
Scheme of the ship areas damaged (Image: SENER)
In 2009, the Argentinean Navy and the Tandanor SACyF shipyard asked SENER Ingenieria y Sistemas – Argentina to deliver an engineering integral project for the repair and modernization of the Almirante Irizar icebreaker.
After a series of meetings between the Tandanor design team and SENER, a final agreement was reached for the technical scope of work to be included both for the basic and the detail designs, based in a previous concept project from STX Wärtsilä. Ensuing project work began October 20, 2009.
As a consequence from the incidences suffered by the ship, 75 percent of her lower structures from the hull, decks and superstructures aft from the accommodation area (frame #84) were severely or totally affected. Pipes, fittings and auxiliary equipment, ventilation ducts, cable trays, cables laid and distribution panels located aft from frame #84 were completely ruined or heavily damaged. All the main and auxiliary diesel generators were also lost, the same with the main and secondary distribution cabinets and the emergency generator with its console.
Meanwhile, the electric propulsion engines and the auxiliary propulsion equipment suffered minor damage caused by the smoke and high temperatures. The outer shell and wing tanks aft from frame #84, and the accommodation and superstructure fore from frame did not suffer any damage.
According to SENER, these extensive damages make for a project that is far more complex than building a new ship. The complete project was the conjunction of a general repair of parts not affected by the fire, some ordinary tasks typical from a dry-docking, some new parts and some refurbishment for out-of-date equipment and systems.
There are new structures that must be connected with the original ones, same as for the pipes and auxiliary structures. This procedure required of more than 1,500 hours of measuring onboard from field technicians, for a further development of a CAD 3D model.
From the ship owner’s requirement of having a DNV classified ship (DNV’s ClassNotation1A1 Specially Ice Strengthened, Naval Support, HELDK SHF, E0, DG-P, LFL), one of the most challenging aspects for SENER was to prepare her for the IMO and SC rules, due to the changes that the classification rules have suffered for ships this type since the time that the ship was built in 1978. Furthr complicating matters, Almirante Irizar is more than a simple icebreaker; she is also a general and refrigerated cargo, liquid cargo, passenger, scientific research, hospital and logistics support vessel, with a hull designed for Antarctic waters navigation and ice breaking.
Almirante Irizar has the capability to run under UMS condition (Unmanned Engine Room), and adds a modern flight deck and aJP1 jet refueling station for all kind of helicopter operations from the ship.
The main topics included in this overhaul are as follows:
And all the above were under the constraints from the economic parameters and the shipyard building and strategic limitations.
Results from the project:
This was achieved with the continuous work from three divisions focused in the marine design, located in Tres Cantos (Madrid), Valencia (Spain) and Buenos Aires (Argentina), with a total of 40 people for the project load peaks, 23 of them Argentinian, SENER said. The FORAN database was centralized in Tres Cantos, but two slave databases in Valencia and Buenos Aires gave local access to the designers in both sites. This procedure made a hit in the use of FORAN, being the first time that a project is developed remotely from three sites so distant.
In the Madrid division there were works for Naval Architecture, structure and FEM analysis. In the Valencia division there were outfitting design, HVAC, fire structure integrity calculations, lifesaving means and devices, electrical design and automation, and finally accommodation. In the Buenos Aires division, there were project management, planning, documentation control, cost control and the development of all the detail design for hull structure and outfitting, plus the technical assistance to the shipyard.
All this work was executed in conjunction with Tandanor, the designated shipyard for the construction. Hence, combining the efforts from SENER and Tandanor, the result is one of the most relevant tasks ever undertaken in the marine history of Argentina.
A special consideration is also reserved for the Argentina Navy personnel, both for the DGMN (Direccion General Material Naval) and for the Navy members assigned to the ship all along the repair work.
Norberto Fiorentino from SENER Argentina said, “The effort and dedication from all those involved in the project, either in the SENER team, the shipyard team and the ship owner team, which ended up with a clear success of the enterprise.”

Related News

Partners Explore Medium-voltage Direct Current Power Systems on Ships Orcas Sink Sailing Yacht in Strait of Gibraltar Salvors Set to Blast Collapsed Baltimore to Pieces Worker Dies in Accident at Peru's Chancay Megaport Project Building the Next-Gen Maritime Prepositioning Ship & Auxiliary Crane Ship