Allan Palmer News

Stolt Offshore Completes Platform Salvage

Stolt Offshore reported it has successfully completed the Eugene Island 275A platform salvage project for Total E&P USA, INC., in what is described as the first platform salvage using only mechanical cutting devices. The platform was located on OCS-G-0988, some 70 miles off the Louisiana coast in 180 ft. of water. "Because of environmental and safety objectives, Total E&P USA asked Stolt to conduct the salvage operation without an arc being struck under water, using remotely operated tools as much as possible," said Allan Palmer, Stolt's regional manager of regional projects and operations in Houston. Stolt Offshore located heavy duty cutting tools that could be modified or redesigned to be used remotely underwater. Iberia, La..