Navy Construction Force’s Largest Project Progressing

Sixty-one Sailors from Naval Mobile Construction Battalion (NMCB) 74 are supporting the Navy’s ongoing $19 million construction project at Navy Auxiliary Landing Field (NALF), San Clemente Island. The “Fearless” Beavers of NMCB 74 are constructing a 21-mile-long tank trail from a beach landing site to the island’s Shore Bombardment Access area. The trail will allow Marines to train with amphibious assault vehicles for shore landing operations. The project, which started in June 2004, is scheduled to be completed by 2010 and calls for many activities including equipment maintenance, operation of rock crushing equipment and blasting evolutions. “The training that takes place here is vital to Pacific Fleet’s readiness.