NNSY Finishes the USS Alaska

The fleet ballistic missile submarine USS Alaska (SSBN 732) finished its 27.5 month availability at Norfolk Naval Shipyard (NNSY) on schedule and under cost March 8, marking the first East Coast overhaul of a SSBN. "We gained technical knowledge from having worked two guided-missile submarine conversions here at Norfolk and from knowledge sharing with Puget Sound Naval Shipyard on West Coast engineering refueling overhauls and we applied that knowledge to our advantage," said Pete Marfio, project superintendent. Since March 30, 2006, NNSY has been part of the Occupational Safety and Health (OSH) Administration's Voluntary Protection Program (VPP) and earned "star site" status.