Phil Wright News

Williams Commissions New Offshore Platform

A unit of Williams has announced that it has commissioned a new production handling platform in federal waters approximately 60 miles south of Mobile Bay, Ala. Gas production from approximately 35,000 acres of federal leases is dedicated to the platform. Construction of Williams' Canyon Station -- a fixed-leg platform in 300 feet of water in East Main Pass Block 261 -- was completed on schedule at the end of June. The jacket was installed in October 2001, followed by the deck and all of the topsides equipment in May 2002. Phil Wright, president and chief executive officer of Williams' energy services unit, said, "The deck is set, the generators are running and we're raring to go.