Project Finance Debt Facilities News

Greenfield Fund Takes Stake in German Wind Farm

The Marguerite Fund has acquired a 22.5% stake in the German greenfield Butendiek offshore wind farm. The Butendiek project is a 288 MW greenfield offshore wind farm located in the North-Sea in the German exclusive economic zone, 32 km west of the German Island of Sylt, and consisting of 80 Siemens 3.6 MW wind turbines. The start of the offshore construction works is scheduled for Spring 2014 and installation of the wind turbines is planned to take place between Autumn 2014 and Summer 2015. When commissioned the wind farm will produce 1,290 GWh p.a., enough to supply the equivalent of some 370,000 households with electricity each year. The cost of the project is estimated to be €1.3bn.