Stolthaven Terminal News

Jurong Port - Jetty construction off Stolthaven Terminal

The working period for jetty construction work at Jurong Island, off Stolthaven Terminal, has been extended. The work is now continuing until 30 September 2014. According to the Maritime and Port Authority of Singapore Port Marine Notice No. A) 1 deg. 16.518'N / 103 deg. B) 1 deg. 16.413'N / 103 deg. C) 1 deg. 16.495'N / 103 deg. D) 1 deg. 16.578'N / 103 deg. Construction of the proposed Jetty 2 will be carried out by piling barges,crane barges and working barges with the support of tug boats. The tug boats will also serve as safety boats.Piling barges and crane barges will be held in position by four anchors. Piling work will be carried out using piling barge. This is followed by steel and concrete work. The last sequence will be the installation of fendering and mooring facilities.