Targeted Oil Rim News

Ithaca Energy Operations Update Ahead of Shareholders Meet

Ithaca Energy Provided its operations update ahead of today’s Shareholders Meeting. The details are as follows. The third development well on the Stella field, well 30/06a-B1X (“B1”), has been successfully drilled to a total measured depth subsea of 16,185 feet. A 2,147 foot gross horizontal reservoir section was drilled in the Palaeocene Andrew sandstone reservoir, within the targeted oil rim. The well intersected high quality sands across a net reservoir interval of 2,034 feet, equating to 95% net pay. This compares to 1,312 feet and 2,514 feet in Stella wells A1 and A2, respectively. Operations are currently on-going to run the well completion assembly, following which a clean-up flow test will be performed.