Teesside Reclamation And Recycling Centre News

U.K. EA Authorizes Dismantling of U.S. Ships

The UK Environment Agency (EA) has issued a modification to the waste management license of Able UK such that the company may engage in the dismantling of U.S. ships at its Teesside Reclamation and Recycling Centre. Able UK submitted an application to the Agency on July 31, 2003 to modify the existing licence for its Teesside Reclamation and Recycling Centre (TERRC) site, to permit an increase in its handling capacity from 24,500 to more than 75,000 tonnes per year. In issuing the licence the Agency has restricted the annual amount handled to 200,000 tonnes. The Agency granted the modification after it had undertaken a thorough assessment reviewing all the potential environmental risks to the Tees Estuary and the surrounding sensitive habitat sites.