WSF Begins Temporary Slip Removal

November 21, 2005

Work will begin soon to remove the temporary slip at the Friday Harbor Ferry Terminal. The project was put out to bid on August 22, 2005 and the contract to remove the temporary slip and construct a tie-up slip was awarded to General Construction Company of Poulsbo. Work is tentatively scheduled to begin on November 28, 2005, and is expected to be complete by the end of February 2006. The slip was always meant to be temporary, as it was built with bare steel that will corrode rapidly in the marine environment. Permit conditions require that WSF remove the slip and that in-water work be completed by March 21, 2006.

Related News

White House Expected to Extend Jones Act Waiver Chris-Marine Introduces Engine Insights Digitalization Solution for Cylinder Condition Kongsberg Maritime Begins Trading on the Oslo Stock Exchange Iranian Swarms of Fast Boats Used to Seize Container Ships Add to Shipping Threats Three Ships Fired Upon in Strait of Hormuz, Crews Unharmed