Specialised subsea construction jack-up vessel 'Seajacks Zaratan' continues installation at a rapid pace at the North Sea Meerwind Offshore Park. Seajack Zaratan collected the three 675t steel structures from the construction port of Cuxhaven on the evening of Thursday 11th April. After completing the 110km transit to the German Bight site in 7 hours, Zaratan was jacked up at the first location ready to commence operations on Friday lunchtime and had completed hammering of the third pile by midnight on Saturday, resulting in a net installation time of 35 hours.