Marine Link
Thursday, April 18, 2024
SUBSCRIBE

Energinet News

16 Nov 2022

Offshore Wind: Fugro Wins Geotechnical Survey Gig in Denmark

Credit:badahos/AdobeStock

Dutch offshore survey services firm Fugro has secured a contract with the Danish grid operator Energinet for geotechnical site investigations for the North Sea I offshore wind development.The Danish government plans to expand offshore wind capacity by 4GW by 2030, and the geodata acquired by Fugro will be used to inform future bids in the area. "This award follows Fugro’s success working on the North Sea Energy Islands project for Energinet throughout 2022, a project that is the first of its kind…

18 Oct 2022

50-meter Section Missing from Damaged Nord Stream Pipeline

Nord Stream gas leak photographed by the Swedish Coast Guard on September 27

Damage to the Nord Stream gas pipeline from Russia to Europe was caused by powerful explosions, Danish police said on Tuesday, echoing earlier findings into leaks that erupted in the network under the Baltic Sea and that have been blamed on sabotage.In what a Swedish newspaper described as the first publicly released footage of damage to the system, film from a private drone appeared to show a gaping rupture in one pipe. Expressen reported a 50-meter section missing from one area of pipeline.Dwindling flows of gas from Russia…

10 Oct 2022

Baltic Sea Island Bornholm Suffers Temporary Power Outage

Credit: Maik Meid/AdobeStock

A Danish Baltic Sea island suffered a temporary power blackout on Monday as a local grid fault caused the transformer feeding electricity from Sweden to shut down, Energinet and E.ON said. Danish transmission system operator Energinet said the blackout had not been caused by damage to the subsea cable feeding the electricity from the transformer station, and power had returned to all consumers on Bornholm. "The fault which caused a power outage on Bornholm on Monday at (0549 GMT) was not directly related to the submarine cable between Bornholm and Sweden…

17 Dec 2019

Boskalis Wins Two Offshore Projects

Dutch engineering company Royal Boskalis Westminster  has been awarded two offshore contracts with a combined value of approximately EUR 85 million.For a new offshore windfarm in Taiwan, Boskalis will carry out the scour protection of the turbine foundations and in Denmark a four-kilometer-long gas pipeline will be installed in the seabed. The execution of both projects is scheduled to take place in 2020.In Taiwan, Boskalis was awarded a contract for the scour protection for the Yunlin offshore windfarm. The award was made by Yunneng Wind Power Co. Ltd. Boskalis will install rock on the seabed around the 71 monopile foundations serving as scour protection.In total 325,000 tons of rock sourced from local quarries in Taiwan will be installed using a fall-pipe vessel.

03 Sep 2019

COBRA Cable Readies for Action

The 700MW COBRAcable interconnector linking the Dutch and the Danish grid will be available for the electricity market as of delivery day, 7 September, Dutch high-voltage grid operator TenneT said."After three years of construction, including the laying of the submarine cables as well as the construction of two onshore converter stations, and a successful test phase earlier this year, COBRAcable will be available for the electricity market as of the delivery day of 7 September, which is exactly on schedule," it said.The first direct connection between the electricity markets of Denmark and the Netherlands was jointly realised and is operated by the two TSCNET shareholders Energinet…

28 Aug 2019

Siemens Wins Viking Link Gig

Germany's Siemens AG said  that it has won a deal to supply two converter stations for the first high-voltage direct current (HVDC) link between the UK and Denmark.Viking Link will enable the exchange of up to 1400MW of electricity to provide increased power-supply reliability and security to consumers in both countries, and will support the integration of renewable energy.The interconnector is being jointly developed by National Grid Ventures (Great Britain) and Energinet (Denmark) via National Grid Viking Link Ltd. and Energinet Eltransmission A/S. Viking Link is scheduled to begin commercial operation at the end of 2023.The two converter stations…

26 Aug 2019

NKT Confirms Viking Link Cable Order

Danish group NKT A/S said it has signed the final contract with Energinet and National Grid for the supply of a cable system for the 1,400-MW Viking Link inter-connector between Denmark and the UK.As per the contract, NKT is to supply a cable system of approx. 150 km of 525 kV MI high-voltage DC onshore power cables for Viking Link inter-connector project, connecting the Danish and British power transmission grids.NKT and the project owners have now signed the final contract documents for the project. With this step, the award of the Viking Link cable solution to NKT is confirmed.As previously announced the order represents a contract value for NKT of approx. EUR 90m (approx. DKK 670m), corresponding to approx. EUR 75m in standard metal prices (approx.

24 Jul 2019

UK-Denmark Subsea Power Cable Gig Awarded

The Italian electric power transmission specialists Prysmian, German multinational conglomerate Siemens and Swedish cable manufacturer have secured contracts worth a total 1.1 billion euros ($1.2 billion) to build the world’s longest subsea power cable, the Viking Link between Britain and Denmark.National Grid and Energinet have recently announced that these cable and converter station suppliers are chosen for the UK’s first ever subsea electricity inter-connector to Denmark.The 1.4 GW high voltage direct current inter-connector, which will be the longest in the world when completed, will stretch 768 kilometers from Lincolnshire to Western Denmark.The project will consist of two parallel HVDC cables which will be manufactured and installed by Prysmian Powerlink S.r.l.

20 Jun 2019

DNV GL Wins Baltic Pipe Project

The international oil & gas advisory and classification society DNV GL has won a major contract to provide independent verification services for the Danish transmission system operator Energinet’s section of the Baltic Pipe project, offshore Denmark.The Baltic Pipe project aims to enable the transport of gas from Norway from a tie-in to the existing Europipe II in the Danish North Sea to the export facility in Zealand. The pipeline in the Baltic Sea towards Poland is not included in the contract. The Baltic Pipe project is planned to be fully operational by 1 October 2022.DNV GL’s contract scope includes independent verification and submarine pipeline certification to the DNV GL certification regime DNVGL-SE-0475.

05 Jun 2019

NKT Commissions Kriegers Flak

Power cable systems provider NKT has commissioned the 170kV HVAC cable system for the 400MW Kriegers Flak combined grid solution which is the world’s first offshore interconnector using the national grid connections of offshore wind farms to connect the power grids of Denmark and Germany.NKT has successfully commissioned the turn key project of the 170 kV HVAC cable system for the combined grid solution connecting the wind farms Kriegers Flak and Baltic 2 for the innovative project Kriegers Flak Combined Grid Solution.The unique project was completed according to schedule and on budget and allows the national grid operators Energinet…

14 Jan 2019

Viking Link Between UK and Denmark Gets Green Signal

Viking Link, an electricity link between Denmark and the UK has been given the green light by the government. The  a proposed 473-mile (761km) electricity cable between Bicker Fen, near Boston, and Revsing, in southern Jutland.The cable running from the Lincolnshire coast to Denmark, uniting UK offshore wind with the sector’s pioneering nation. The GBP1.8 billion (USD 2.31 bln) project hits UK landfall between Sandilands and Anderby Creek.It will include about 40 miles of underground cables before it reaches landfall, running between Bicker Fen near Boston - where Grimsby’s latest offshore wind farm Triton Knoll will also feed in to - and a substation in Southern Jutland, Denmark.National Grid and Energinet hold a 50/50 share of Viking Link.

09 May 2017

Energy Island: Europeans Mull North Sea Hub

Image: TenneT

A plan set in motion by three European transmission system operators (TSO) aims to develop mammoth offshore wind farm infrastructure in the North Sea supported by at least one manmade island. First unveiled in June 2016, plans for the North Sea Wind Power Hub project will now press ahead to develop a large offshore renewable European electricity system following the signing of a trilateral agreement by TenneT TSO B.V. (Netherlands), Energinet.dk (Denmark) and TenneT TSO GmbH (Germany) in Brussels on March 23, 2017.

07 Jan 2014

NKT Opens Submarine Cables Center in Rotterdam

Turntable NKT Cables Logistics Center (Photo NKT)

NKT Cables established its submarine cable Logistics Center at Rotterdam’s deepwater port in the Netherlands. The center with its present 9,000- and 4,600-metric-ton turntable capacity has been implemented within the NKT Cables production flow, in order to provide a substantial logistics capacity. With its unique cable splicing technology, NKT Cables can connect long single cable lengths together to form extra-long continuous submarine cables, enabling load-outs of up to 6,000 metric tons - and even more - in one campaign to any cable laying vessel, adapting optimally to each specific project.

31 Dec 2013

Rotterdam Subsea Cable Centre Set Up by NKT

Submarine Cable Turntable: Image courtesy of NKT Cables

NKT Cables has established a submarine cable Logistics Centre, with a 9.000 and 4,600 tonne turntable capacity at Rotterdam’s deep-water port in the Netherlands. The company informs that with its unique cable splicing technology, NKT Cables can connect long single cable lengths together to form extra-long continuous submarine cables, enabling load-outs of up to 6,000 tonnes - and even more - in one campaign to any cable laying vessel. Extra-long lengths up to more than 30 km of submarine cable have been produced and loaded in a single, continuous length from the new site in Rotterdam.

26 Apr 2013

Eleven Companies Connect for Power to Gas Platform

Schedule of the concept of P2G and its applications

Eleven companies in Europe joined forces in the newly established North Sea Power to Gas Platform to further develop the concept of Power-to-Gas (P2G): the conversion of renewable power into gas. P2G will play an increasingly important role in our future energy system, as it reduces temporal surpluses of renewable power by converting these surpluses into gases. As these gases can be used for different purposes such as transportation, domestic heating, as feedstock for the chemical industry and power generation, the potential value of P2G is considerable.