Panama Canal PAC-4 Work Begins

Tuesday, January 26, 2010

Work on the second largest contract of the Panama Canal Expansion Program has begun. The Panama Canal Authority (ACP) issued consortium FCC-ICA-Meco the Notice to Commence the fourth and final dry excavation (PAC-4) contract.

PAC-4 is the most complex expansion project after the design and build of the new set of locks. The dry excavation included in PAC-4 will create an access channel linking the new Pacific locks with the Canal's existing Gaillard Cut (the narrowest stretch of the Panama Canal).

The ACP awarded the PAC-4 contract to FCC-ICA-Meco, a Spanish, Mexican and Costa Rican joint venture, following the consortium's lowest bid submission of $267.8m and its compliance with the requirements established in the request for proposal specifications. The ACP issued the Notice after receiving FCC-ICA-Meco's performance and payment bonds and signing the contract.

The scope of work will include 26 million cubic meters of unclassified excavation, the installation of a backfilled cellular cofferdam water barrier and the construction of an earth-rock filled dam that will create part of the access channel's eastern bank. The work is scheduled to conclude during the third quarter of 2013.

Expansion will build a new lane of traffic along the Panama Canal through the construction of a new set of locks which will double capacity and allow more traffic and longer, wider ships.

Maritime Reporter September 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

News

Livorsi Launches New Throttle Lineup

Livorsi Marine introduced the all new Platinum Series throttles, which they say are designed to be more ergonomically comfortable to the operator while being lighter

Henderson, Hanes & Associates Opens Doors in Miami

Ocean Engineering/ Naval Architecture Firm Brings Innovation to the Mega Yacht Community The Miami-based ocean engineering and naval architecture firm of Henderson & Associates, Inc.

Austal Launches Trenton (JHSV 5)

Second Joint High Speed Vessel to be launched at Austal in 2014 On September 30, 2014, Austal USA successfully completed the launch process of Trenton (JHSV

 
 
Maritime Careers / Shipboard Positions Naval Architecture Navigation Pipelines Pod Propulsion Salvage Ship Electronics Ship Repair Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1078 sec (9 req/sec)