The original contract signed on February 26, 2004 with Blackford Dolphin Pte Ltd (Owner), a subsidiary of Fred Olsen Energy ASA, for work to be carried on the Blackford Dolphin was $177m. The expected delivery date was in June 2007.
On July 20, 2007, an addendum was agreed upon, which took into account changes up to that point in time by the Owner. The contract value was increased to $239.5m with the delivery date revised to February 2008.
Since the addendum, there have been further revisions, including changes to the design of the rig, by the Owner. This has resulted in variation orders and a delay in the completion of the rig. While some variation orders were agreed upon and paid for by the Owner, outstanding and unresolved variation orders remain. The disputed amount is EUR 65.4 million. Both parties have yet to agree on an extended delivery date.
Pursuant to the terms of the addendum, Keppel Verolme has served a notice to advise the Owner that it expects to be paid for work that has been done. Under the contract terms, the company is confident that it would be paid in full for work completed before the vessel can be towed away.
Keppel Verolme is confident that it has a strong case in this dispute. In event the matter goes to arbitration, the resolution of the dispute shall be held at the Singapore Chamber of Maritime Arbitration. The contract is governed by laws.
Based on available facts, Keppel Corporation Limited (KCL), the parent company of Keppel Verolme, does not expect the matter to have material financial impact on KCL for the year 2008.

Completion of FLC - Aker Yards transaction scheduled for July
Aker Yards and the Russian company FLC expects to complete the transaction in which FLC buys 70 percent ownership in three yards in Ukraine and Germany in July 2008. The agreement was announced 25 March 2008. The one remaining item in the process before the transaction is concluded is to complete the process to obtain approval from the competition authorities. This process has taken somewhat longer than anticipated, but FLC and Aker Yards expects that it will be possible to get this final approval shortly.

Maritime Reporter April 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Contracts

Termination of Seadrill Unit's and Rosneft Deal Extended

North Atlantic Drilling (NADL), a subsidiary of Seadrill, will delay the closing of a deal with Russia's Rosneft by two years and has agreed to renegotiate the terms of the agreement,

Qatar to Contract 6,000 Rooms on Cruise Ships for 2022 World Cup

Reviving an idea to lodge some football fans and guests during the 2022 World Cup in “floating hotels,” the Qatar Tourism Authority (QTA) has announced plans to contract at least 6,

USN Names Littoral Combat Ship

Secretary of the Navy Ray Mabus announced today that the next Freedom-variant littoral combat ship (LCS) will be named USS St. Louis. The future USS St. Louis,

 
 
Maritime Security Naval Architecture Navigation Offshore Oil Pipelines Port Authority Ship Electronics Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1143 sec (9 req/sec)