The original contract signed on February 26, 2004 with Blackford Dolphin Pte Ltd (Owner), a subsidiary of Fred Olsen Energy ASA, for work to be carried on the Blackford Dolphin was $177m. The expected delivery date was in June 2007.
On July 20, 2007, an addendum was agreed upon, which took into account changes up to that point in time by the Owner. The contract value was increased to $239.5m with the delivery date revised to February 2008.
Since the addendum, there have been further revisions, including changes to the design of the rig, by the Owner. This has resulted in variation orders and a delay in the completion of the rig. While some variation orders were agreed upon and paid for by the Owner, outstanding and unresolved variation orders remain. The disputed amount is EUR 65.4 million. Both parties have yet to agree on an extended delivery date.
Pursuant to the terms of the addendum, Keppel Verolme has served a notice to advise the Owner that it expects to be paid for work that has been done. Under the contract terms, the company is confident that it would be paid in full for work completed before the vessel can be towed away.
Keppel Verolme is confident that it has a strong case in this dispute. In event the matter goes to arbitration, the resolution of the dispute shall be held at the Singapore Chamber of Maritime Arbitration. The contract is governed by laws.
Based on available facts, Keppel Corporation Limited (KCL), the parent company of Keppel Verolme, does not expect the matter to have material financial impact on KCL for the year 2008.

Completion of FLC - Aker Yards transaction scheduled for July
Aker Yards and the Russian company FLC expects to complete the transaction in which FLC buys 70 percent ownership in three yards in Ukraine and Germany in July 2008. The agreement was announced 25 March 2008. The one remaining item in the process before the transaction is concluded is to complete the process to obtain approval from the competition authorities. This process has taken somewhat longer than anticipated, but FLC and Aker Yards expects that it will be possible to get this final approval shortly.

Maritime Reporter July 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Contracts

Nautilus Awards Contract for Dewatering Plant Design

Nautilus Minerals Inc. has awarded a contract for the design of the Solwara 1 dewatering plant to be used on the company’s production support vessel to the Brisbane

CWind Supports Ballast Nedam at Butendiek OWF

CWind, a provider of integrated services to the wind industry, announced today that it is providing corrosion protection services to Ballast Nedam at Butendiek Offshore Wind Farm (OWF).

Sea Trucks Returns to the Gulf of Mexico

Offshore installation services provider Sea Trucks Group announced it has been awarded a charter contract for its accommodation construction vessel Jascon 31 to operate in the Gulf of Mexico,

 
 
Maritime Security Maritime Standards Naval Architecture Offshore Oil Pipelines Pod Propulsion Port Authority Ship Electronics Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1434 sec (7 req/sec)