Judicial Decision on M/V Mokihana Rebuild

Friday, December 11, 2009

On December 4, 2009, a federal district court in Va. entered judgment in favor of the U.S. Coast Guard and Matson Navigation Company, Inc. in a long-running vessel foreign rebuild case.  Winston & Strawn LLP represented Matson.

The Shipbuilders Council of America, Inc. and Pasha Hawaii Transport Lines LLC sued the Coast Guard initially in November 2006 seeking to disqualify the M/V Mokihana from the U.S. coastwise trade because of work to be done to the vessel in China. That initial suit was dismissed in 2007, but then re-initiated on December 10, 2007 after the work on the M/V Mokihana was complete.  The M/V Mokihana, a container ship, had work done in China to prepare the vessel for the addition of a roll-on/roll-off garage added to the stern of the vessel in Alabama. 

U.S coastwise laws – commonly referred to as the Jones Act – generally restrict U.S. coastwise trade to U.S. constructed vessels.  In connection with that U.S. build requirement, otherwise eligible coastwise vessels permanently lose their ability to participate in the U.S. coastwise trade if they are “rebuilt” foreign. 

The Coast Guard determines whether foreign shipyard work is disqualifying pursuant to a regulation it issued in 1996.  That regulation provides that a vessel is considered rebuilt foreign “when a major component of the hull or superstructure not built in the United States” is added to the vessel or if “work performed on its hull or superstructure constitutes more than 10 percent of the vessel’s steelweight.”  Steel work in excess of 7.5 percent but less than 10 percent of the vessel’s steelweight can also be disqualifying unless the Coast Guard in its discretion approves the amount.

The regulations also provide a process for ship owners to approach the Coast Guard and obtain a preliminary rebuild determination in advance of the shipyard work being done in order to obtain some assurance that the work won’t be disqualifying.  Matson sought and obtained both a preliminary and a final rebuild determination from the Coast Guard to the effect that the work to be done to the M/V Mokihana would not result in the vessel being considered “rebuilt.” 

Shipbuilders and Pasha advanced a number of arguments claiming that the Coast Guard acted arbitrarily and contrary to law in issuing those determinations.  Among other things, Shipbuilders/Pasha argued that the claimed addition of a deck in China was the addition of a “major component,” that the Coast Guard incorrectly excluded certain outfitting items from the steel calculation (such as auto platforms) and should have counted both removed and added steel in that calculation.  Initially, Shipbuilders/Pasha also argued that the work done in Alabama should have been cumulated with the work done in China in determining whether a foreign “rebuild” had occurred.

The “major component” issue was decided against the Coast Guard in a related case involving two Seabulk tank vessels which had been “double hulled” in China.  However, the district court’s decision in Seabulk case was reversed by the U.S. Court of Appeals for the Fourth Circuit in favor of the Coast Guard on August 21, 2009.  On appeal, the Coast Guard’s view that a “major component” should be judged based on whether it is “separable” was validated.  On that basis, the Coast Guard found that the addition of an inner hull piece-by-piece was not the addition of a “major component.” 

On December 3, 2009, federal judge T.S. Ellis, III concurred and found that the addition of a deck piece-by-piece to the M/V Mokihana, none of which was “major,” did not constitute the addition of a “major component” within the meaning of the Jones Act.  Judge Ellis also rejected Shipbuilders/Pasha’s other arguments finding in each instance that the actions of the Coast Guard were reasonable and within its lawful discretion.  Finally, Judge Ellis concluded the Coast Guard was correct in focusing on the foreign portion of the work in assessing whether there was a foreign “rebuilding” under the law.

Maritime Reporter July 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Legal

Massive Haitian Refugee Rescues off Bahamas

Coast Guard crews and Royal Bahamian Defence Force (RBDF) rescued more than 400 Haitians illegally migrating in three separate at sea interdictions in the span of 11 days, informs the US Coast Guard.

Ballast Water Management: California Update

The California State Lands Commission (CSL) has promulgated a letter to clarify its interpretation of existing ballast water requirements under the California's

Chilean Court Rejects Appeal Against Crow River Project

Chile's Supreme Court on Thursday rejected an application for an environmental organization against Crow River hydroelectric project, which plans to build in the

Shipbuilding

Bureau Veritas to Class, Certify FPSOs for Saipem

Bureau Veritas has been awarded a contract by Saipem to provide classification and certification services for the two Kaombo FPSOs for service off Angola. The

German Shipyard FSG Re-organizes Top Management

Flensburger Schiffbau-Gesellschaft (FSG) says it will be headed by a new management team from January 1st 2015, details as follows: Current Chief Technology

Bid to Rescue Clyde Shipbuilder Ferguson

Jim McColl, one of Scotland's richest men, has tabled a bid to rescue collapsed Clyde shipbuilder Ferguson and aims to return the yard to its former glory by creating hundreds of jobs,

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Pipelines Pod Propulsion Port Authority Salvage Ship Simulators Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1375 sec (7 req/sec)