USS Michigan Completed Early

Monday, November 03, 2008

USS Michigan Completed Early

USS Michigan (SSGN 727) undocked in late October, five days early, at Puget Sound Naval Shipyard and Intermediate Maintenance Facility (PSNS & IMF).

Michigan was at PSNS & IMF for a planned five-month major maintenance period. While Michigan’s maintenance availability was scheduled in advance, the full extent of the necessary work isn’t always known until the ship is drydocked.

The Trident maintenance plan objectives include all the maintenance to be performed to allow the ship to operate safely and unrestricted during prescribed operating cycles, operating intervals, and for its prescribed service life.

Execution of the maintenance plan ensures that the ship operates safely and unrestricted while at sea and, maximizing their operational availability.

PSNS & IMF, a Naval Sea Systems Command (NAVSEA) field activity, is one of four public shipyards that play a major role in maintaining America’s fleet and providing wartime surge capability to keep the nation’s ships ready for combat. Customer service is important in every business. For NAVSEA, serving our customers in the Fleet is our top priority.

(Source: NAVSEA)

Maritime Reporter June 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Navy

BAE Systems Awarded Two Navy Contract Modifications

The US Department of Defense informs it has awarded separate contracts to BAE Systems in Jacksonville and in Norfolk for ship repairs and modifications as follows: 1.

USCG Cutter Waesche Home from RIMPAC Exercises

The Coast Guard Cutter Waesche has returned to port at Coast Guard Base Honolulu, after spending three weeks at sea participating in Rim of the Pacific (RIMPAC) 2014 exercises,

Today in U.S. Naval History: July 30

Today in U.S. Naval History - July 30 1918 - Units of First Marine Aviation Force arrive at Brest, France 1941 - Japanese aircraft bomb USS Tutuila (PR-4) at Chungking,

Vessels

Hornbeck Offshore Ride High on Q2 2014 Results

Hornbeck Offshore Services, Inc. has announced its financial results for the second quarter ended June 30, 2014.  Following are highlights for this period and excerpts

USCG Cutter Waesche Home from RIMPAC Exercises

The Coast Guard Cutter Waesche has returned to port at Coast Guard Base Honolulu, after spending three weeks at sea participating in Rim of the Pacific (RIMPAC) 2014 exercises,

Growing American Shipping Bill Introduced by Garamendi

Congressman John Garamendi (D-CA-03), Ranking Member of the House Transportation and Infrastructure’s Coast Guard and Maritime Transportation Subcommittee, informs ot the introduction of  H.

 
 
Maritime Careers / Shipboard Positions Maritime Security Offshore Oil Pipelines Port Authority Salvage Ship Electronics Ship Repair Ship Simulators Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1683 sec (6 req/sec)