Port Canaveral Harbor Expansion Begins

Posted by Michelle Howard
Friday, March 21, 2014
Photo: Port Canaveral

Dispute remains over who pays for maintenance costs for federal channel.

The $35 million harbor widening and deepening project at Port Canaveral to allow larger ships greater safety margins for sailing in and out of the port is scheduled to begin next month with completion in November 2014. The project to widen Port Canaveral’s 400-feet wide harbor by 100 feet and deepen the entrance by two feet to 46 feet cleared the final two U.S. Army Corps of Engineers permitting hurdles last week.

“The Canaveral Port Authority’s decision to utilize alternative federal processes that allow seaports to self-fund required studies and permits allowed us to arrive at this critical juncture 10 years earlier than taking the traditional route,” said Port Canaveral CEO John E. Walsh. “However, this is a bittersweet moment because the Army Corps of Engineers has deferred approval to fund maintenance dredging of the harbor via a Section 204f process after we complete the deepening and widening project. Once the still-pending WRDA bill is passed, the Army Corps will be required to fund dredging costs, but there is no guarantee the WRDA will pass or keep all provisions in place.”

“This deferred approval could cost the Canaveral Port Authority an unbudgeted $1.3 million per year for future maintenance of the harbor,” Walsh added. “Since this cost always has been the responsibility of the federal government, we are confident with meetings set in Washington next week, we can make legislative and administrative progress toward a resolution. Congressman Bill Posey has been a continued ally of Port Canaveral to get this project approval and is helping with the last Section 204f pieces, as well.”

The uplands work at the Canaveral Harbor entrance will begin next month followed by cutting the land and building a retaining wall during the next 6 months and conclude with dredging at the widening for the next three months. This portion of the project will be ready in November 2014 for the arrival of added large ships. Channel deepening of the remainder of the three-and-a-half mile length will continue through November 2015.

“The support the Port Authority received from Florida Governor Rick Scott and the $24.4 million in state funding for the Port’s channel project, as well as the backing of our federal congressional delegation, has been invaluable,” Port Authority Commission Chairman Tom Weinberg said. “They understand the importance of this project for the economic benefit of Brevard County and all of Central Florida.”
 

Maritime Reporter June 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Hornbeck Offshore Ride High on Q2 2014 Results

Hornbeck Offshore Services, Inc. has announced its financial results for the second quarter ended June 30, 2014.  Following are highlights for this period and excerpts

BAE Systems Awarded Two Navy Contract Modifications

The US Department of Defense informs it has awarded separate contracts to BAE Systems in Jacksonville and in Norfolk for ship repairs and modifications as follows: 1.

DW to Present at Upcoming Floating LNG 2014, Houston

Douglas-Westwood (DW) says that its manager in Houston, Andrew B. Meyers will be joining the speakers on the platform at the upcoming 27th-30th October 2014 'Floating

Ports

Pre-Mooring Safety Inspections at Trieste, Italy

The SIOT/TAL Terminal at Trieste has advised that the TAL Pre-Mooring Safety Inspection program will be modified from 1 September. The checks at road will affect:

MPHRP's Welfare Responder Training in Manila

Few people are as devoted to seafarers’ wellbeing as MPHRP’s partners, which include the members of the International Seafarers Welfare and Assistance Network

Growing American Shipping Bill Introduced by Garamendi

Congressman John Garamendi (D-CA-03), Ranking Member of the House Transportation and Infrastructure’s Coast Guard and Maritime Transportation Subcommittee, informs ot the introduction of  H.

Finance

Hornbeck Offshore Ride High on Q2 2014 Results

Hornbeck Offshore Services, Inc. has announced its financial results for the second quarter ended June 30, 2014.  Following are highlights for this period and excerpts

BAE Systems Awarded Two Navy Contract Modifications

The US Department of Defense informs it has awarded separate contracts to BAE Systems in Jacksonville and in Norfolk for ship repairs and modifications as follows: 1.

Exxon Mobil Corporation Declares 3Q Dividend

The Board of Directors of Exxon Mobil Corporation yesterday declared a cash dividend of 69 cents per share on the Common Stock, payable on September 10, 2014 to

News

Quality hat-trick for GAC Marine Logistics

Global ship spares logistics provider GAC Marine Logistics Inc. (GML) has secured ISO certifications in recognition of its Quality Management, Environmental

Hellfire Missile Firing a First for New Navy Helicopters

The Royal Australian Navy’s newest maritime combat helicopter, the MH-60R Seahawk ‘Romeo’, has successfully fired its first ‘Hellfire’ missile in the United States.

BMT Oceanica Wins Major Water Corporation Bid

Marine and coastal environment specialist, BMT Oceanica (BMT), a subsidiary of BMT Group Ltd, is delighted to announce that it has won the bid to provide Ocean

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Naval Architecture Navigation Offshore Oil Pipelines Pod Propulsion Ship Repair Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2181 sec (5 req/sec)