Marine Link
Thursday, March 28, 2024

South Stream’s offshore section Set for Construction

Maritime Activity Reports, Inc.

November 18, 2014

 

The Gazprom Management Committee addressed the progress with the South Stream

It was stressed that South Stream gas pipeline project was ready for constructing. This includes the most complicated part of the project – the first and the second strings of the offshore gas pipeline. FEED activities are completed for the offshore section. At present, the project contractor Saipem is engaged in detailed engineering of the submerged trunkline.

Almost 300 thousand tons of pipes have been supplied for the first offshore string. Pipeline sections for the deep-water part are currently being welded in the port of Burgas.

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week