Progress on Gudrun Platform Construction

Wednesday, August 03, 2011

The steel support structure for the Gudrun platform is now in place on the North Sea field, completing the first phase of the extensive installation work being carried out there.

”The entire operation has been carried out according to plan and in a secure manner,” reports Anders Opedal, senior vice president for projects in Statoil’s Technology, Projects and Drilling business area. “We’ve passed an important milestone for coming on stream at the right time and to budget. With the jacket solidly positioned on the seabed, we’ll be able to start drilling in the fourth quarter as planned.”

Installation of the steel structure began on July 24, and the job of attaching it to the seabed was completed on August 2, when the last of 12 60-meter piles was driven home.

Saipem 7000, the world’s second-largest crane vessel, has been used to carry out the installation work on Gudrun.

Weighing some 7,000 tons, the traditional jacket comprises two main structures of almost 2,300 tons each, tied together by six horizontal frames and various bracings.

“Gudrun is the first of a number of new installations in an area of the Norwegian North Sea which is both highly interesting and mature,” observes Ivar Aasheim, senior vice president for field development in the Development and Production Norway business area. “By exploiting existing infrastructure for processing and transport, we’re ensuring production from new fields. Gudrun will also make an important contribution to maintaining high production levels going forward.”

The next development milestone is the start of pre-drilling production wells on the field. These will be tied back to the platform for partial processing and oil and gas export. Final processing of Gudrun’s output will take place on Sleipner A, with the gas piped to the adjacent Sleipner T platform for carbon dioxide removal. In addition, electricity to operate the Gudrun installation once it comes on stream in two years’ time will be supplied from Sleipner A.

 

(Source: Statoil)

Maritime Reporter August 2013 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

ESS Lands Second Contract with Dolphin Drilling

ESS Support Services Worldwide, part of Compass Group, has won a new, three-year contract, worth £10.5 million, to provide hotel and catering services to Dolphin Drilling Ltd.

MNZ Opens New Office in Port Taranaki

Maritime New Zealand (MNZ) informs that for the first time in 5 years it has a permanent presence in New Plymouth on the opening of a new office at Port Taranaki

Fugro Achieves Innovation through Integration

When Aberdeen-based Diamond Offshore wanted to add new functionality to the existing helideck monitoring system on the Ocean Guardian drilling rig in the North Sea,

News

Citigroup Seeks British Court Backing on China Metals Claims

Citigroup Inc said on Friday it has started proceedings in commercial court in London to enforce its rights over $285 million of financing at two ports in China,

MARAD, ABS Sign MOA for NDRF Class and Survey

The U.S. Department of Transportation’s Maritime Administration (MARAD) announced it has signed a new Memorandum of Agreement (MOA) with the American Bureau of Shipping (ABS),

Salvage Crews Avert Disaster in the Galápagos

Mammoet Salvage helps avert environmental disaster in the Galápagos Islands Mammoet Salvage and its partner, CPT Remolcadores SA of Chile, recently responded

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Naval Architecture Pipelines Pod Propulsion Port Authority Ship Electronics Ship Repair Ship Simulators
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1327 sec (8 req/sec)