Progress on Gudrun Platform Construction

Wednesday, August 03, 2011

The steel support structure for the Gudrun platform is now in place on the North Sea field, completing the first phase of the extensive installation work being carried out there.

”The entire operation has been carried out according to plan and in a secure manner,” reports Anders Opedal, senior vice president for projects in Statoil’s Technology, Projects and Drilling business area. “We’ve passed an important milestone for coming on stream at the right time and to budget. With the jacket solidly positioned on the seabed, we’ll be able to start drilling in the fourth quarter as planned.”

Installation of the steel structure began on July 24, and the job of attaching it to the seabed was completed on August 2, when the last of 12 60-meter piles was driven home.

Saipem 7000, the world’s second-largest crane vessel, has been used to carry out the installation work on Gudrun.

Weighing some 7,000 tons, the traditional jacket comprises two main structures of almost 2,300 tons each, tied together by six horizontal frames and various bracings.

“Gudrun is the first of a number of new installations in an area of the Norwegian North Sea which is both highly interesting and mature,” observes Ivar Aasheim, senior vice president for field development in the Development and Production Norway business area. “By exploiting existing infrastructure for processing and transport, we’re ensuring production from new fields. Gudrun will also make an important contribution to maintaining high production levels going forward.”

The next development milestone is the start of pre-drilling production wells on the field. These will be tied back to the platform for partial processing and oil and gas export. Final processing of Gudrun’s output will take place on Sleipner A, with the gas piped to the adjacent Sleipner T platform for carbon dioxide removal. In addition, electricity to operate the Gudrun installation once it comes on stream in two years’ time will be supplied from Sleipner A.

 

(Source: Statoil)

Maritime Reporter September 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

Autonomous Technology for Offshore Wind Farm

ASV Ltd in association with Planet Ocean Ltd, have received funding from the GROW:OffshoreWind initiative to investigate how the use of Autonomous Surface Vehicles

World’s 1st LNG Hybrid Barge Christened "Hummel"

The world’s first LNG hybrid barge of Becker Marine Systems was christened with the name "Hummel" on October 18, 2014, at Grasbrook Quay in HafenCity Hamburg.

KBR, Daewoo win Eni FLNG FEED

KBR Inc. announced today that the KD Consortium, consisting of KBR and Daewoo Shipbuilding & Marine Engineering Company, Ltd, has been awarded a front end engineering

News

Rolls-Royce to Design, Equip Stern Trawler for Ramoen

The Armon shipyard in Gijón, Spain has entered into a contract to build a new Stern Trawler for the Norwegian fishing company Ramoen. The vessel will be a Rolls-Royce design,

Frontline appoints Macleod as new CEO

Crude oil tanker firm Frontline, part of shipping tycoon John Fredriksen's business empire, appointed Robert Hvide Macleod as chief executive to replace Jens Martin Jensen, the firm said on Monday.

Autonomous Technology for Offshore Wind Farm

ASV Ltd in association with Planet Ocean Ltd, have received funding from the GROW:OffshoreWind initiative to investigate how the use of Autonomous Surface Vehicles

 
 
Maritime Careers / Shipboard Positions Naval Architecture Navigation Offshore Oil Port Authority Salvage Ship Electronics Ship Repair Ship Simulators Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2078 sec (5 req/sec)