Progress on Gudrun Platform Construction

Wednesday, August 03, 2011

The steel support structure for the Gudrun platform is now in place on the North Sea field, completing the first phase of the extensive installation work being carried out there.

”The entire operation has been carried out according to plan and in a secure manner,” reports Anders Opedal, senior vice president for projects in Statoil’s Technology, Projects and Drilling business area. “We’ve passed an important milestone for coming on stream at the right time and to budget. With the jacket solidly positioned on the seabed, we’ll be able to start drilling in the fourth quarter as planned.”

Installation of the steel structure began on July 24, and the job of attaching it to the seabed was completed on August 2, when the last of 12 60-meter piles was driven home.

Saipem 7000, the world’s second-largest crane vessel, has been used to carry out the installation work on Gudrun.

Weighing some 7,000 tons, the traditional jacket comprises two main structures of almost 2,300 tons each, tied together by six horizontal frames and various bracings.

“Gudrun is the first of a number of new installations in an area of the Norwegian North Sea which is both highly interesting and mature,” observes Ivar Aasheim, senior vice president for field development in the Development and Production Norway business area. “By exploiting existing infrastructure for processing and transport, we’re ensuring production from new fields. Gudrun will also make an important contribution to maintaining high production levels going forward.”

The next development milestone is the start of pre-drilling production wells on the field. These will be tied back to the platform for partial processing and oil and gas export. Final processing of Gudrun’s output will take place on Sleipner A, with the gas piped to the adjacent Sleipner T platform for carbon dioxide removal. In addition, electricity to operate the Gudrun installation once it comes on stream in two years’ time will be supplied from Sleipner A.

 

(Source: Statoil)

Maritime Reporter April 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

Falklands' Oil Drilling at Isobel Deep Suspended

Oil explorers drilling in the waters north of the Falkland Islands have suspended work on the second well of their 2015 current six-well drilling campaign after a technical problem.

Arctic Nations to Fight Climate Change Despite Russia Tensions

The eight Arctic Council nations pledged on Friday to do more to combat climate change that is shrinking the vast frigid region, with countries trying to put

OSV Technology: Notable Designs & Deliveries

Though the market for Offshore Support Vessels (OSVs) is soft, advances in technology, fit and finish in  the sector is unrivaled in any other maritime niche over the past five years.

News

5th Floating Accommodation for Lerwick

A further accommodation ship, Ocean Atlantic, is due at Lerwick on Monday 27 April 2015 and is on its way from Portland in Dorset. As with the other floating accommodation at the port,

Double Order for Super Gloria Reachstacker

Kalmar, part of Cargotec, has gained an order for two Super Gloria reachstackers from Tadarsa Logistics S.L. in Aviles, Spain. The largest reachstackers ever built,

Goliat FPSO in Norway

The Goliat FPSO was successfully floated off the heavy-lift vessel, Dockwise Vanguard, in the fjord outside Hammerfest, says Eni Norge    The Goliat platform has arrived in Hammerfest,

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Pipelines Pod Propulsion Port Authority Salvage Ship Repair Ship Simulators Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2177 sec (5 req/sec)