Progress on Gudrun Platform Construction

Wednesday, August 03, 2011

The steel support structure for the Gudrun platform is now in place on the North Sea field, completing the first phase of the extensive installation work being carried out there.

”The entire operation has been carried out according to plan and in a secure manner,” reports Anders Opedal, senior vice president for projects in Statoil’s Technology, Projects and Drilling business area. “We’ve passed an important milestone for coming on stream at the right time and to budget. With the jacket solidly positioned on the seabed, we’ll be able to start drilling in the fourth quarter as planned.”

Installation of the steel structure began on July 24, and the job of attaching it to the seabed was completed on August 2, when the last of 12 60-meter piles was driven home.

Saipem 7000, the world’s second-largest crane vessel, has been used to carry out the installation work on Gudrun.

Weighing some 7,000 tons, the traditional jacket comprises two main structures of almost 2,300 tons each, tied together by six horizontal frames and various bracings.

“Gudrun is the first of a number of new installations in an area of the Norwegian North Sea which is both highly interesting and mature,” observes Ivar Aasheim, senior vice president for field development in the Development and Production Norway business area. “By exploiting existing infrastructure for processing and transport, we’re ensuring production from new fields. Gudrun will also make an important contribution to maintaining high production levels going forward.”

The next development milestone is the start of pre-drilling production wells on the field. These will be tied back to the platform for partial processing and oil and gas export. Final processing of Gudrun’s output will take place on Sleipner A, with the gas piped to the adjacent Sleipner T platform for carbon dioxide removal. In addition, electricity to operate the Gudrun installation once it comes on stream in two years’ time will be supplied from Sleipner A.

 

(Source: Statoil)

Maritime Reporter November 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

Oil at $60 per Barrel, Libya Fire Supports

Brent on track for biggest annual drop since 2008; stimulus measures from Japan, China lend some support. Brent crude oil rose to $60 per barrel on Monday, supported

ARC Towage Takes Delivery of 4 Damen Tugs

ARC Towage of Trinidad & Tobago has taken delivery of the last of a series of four Damen ASD 2810 Tugs. All four have been delivered in less than 18 months.

Otto Marine Sells AHTS for $100 mi

Otto Marine Limited sold an Anchor Handling Tug Supply Vessel to a renowned unrelated third party for US$100 million. DNV classed and Norwegian-designed, the VS491 21,

News

RS to Class Newbuild Arctic Tankers

Russian Maritime Register of Shipping (RS) has signed an agreement with South Korean yard Samsung Heavy Industries Co. LTD for design approval and survey under construction of a new series of 42,

Canal Delays Weigh on Panama Growth

Panama on Sunday lowered its 2014 growth expectation to 6.3 percent, down from a previous estimate of around 7 percent. Panama's economy grew 8.4 percent in

Egypt Nears Deal for Algerian LNG Imports

Egypt expects to agree a deal to import liquified natural gas from Algeria as early as this week, ministry sources said on Monday, as the country seeks to ease a chronic energy shortage.

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Pipelines Port Authority Salvage Ship Electronics Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2933 sec (3 req/sec)