The Panama Canal Expansion is moving forward to achieve its goal of enhancing the waterway's capacity. To date, the Program registers a 60.4% progress.

"The Panama Canal Expansion will enhance the value of the Panama route," Panama Canal Administrator Jorge L. Quijano said. "We are focused on the Third Set of Locks project, which is one of the key projects of the Expansion Program."

The Expansion Program has achieved many important milestones. Both entrances of the Panama Canal are ready for bigger ships, since the deepening and widening of the Atlantic and Pacific access channels have been completed. The dredging of Gatun Lake is expected to be completed by the end of this year. The Pacific Access Channel has reached the design depth and the dam that will divide the new channel from Miraflores Lake is under construction.

The Third Set of Locks project registers a 50% progress. The new lock complexes in the Pacific and Atlantic sides will feature three chambers, three water-saving basins per chamber, a lateral filling and emptying system and rolling gates.

The first four new lock gates will be arriving in the country this upcoming August, signaling a very important milestone for the Third Set of Locks project. Each one of the 16 gates required will weight an average of 3,300 tons. Constructed in Italy by subcontractor Cimolai S.p.A, the giant new gates will be unloaded in the Atlantic side of the Canal and rolled off the ship to a specially-constructed reception dock. Unlike the current Canal, which uses miter gates, the expanded Canal will have steel rolling gates.

The Panama Canal is also preparing to face future operations. In June, the Panama Canal received three of the 14 new tugboats that will enhance the Canal's current fleet. The additional capacity will allow assisting Post-Panamax vessels that will be transiting the expanded Canal, which will not use locomotives like in the existing locks.

The Panama Canal Expansion involves the construction of a third lane of traffic, which will double Canal's capacity and have an important impact in world maritime trade.

pancanal.com
 

Maritime Reporter June 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Aberdeen Pupils Peek into Subsea Oil & Gas Technology

Pupils at an Aberdeen primary school were given a rare insight into the depths of the oil and gas industry’s subsea sector after getting to sit in the driving

AVEVA, DNV GL's Sesam Integration Cuts Cost

Integration of Aveva and DNV GL's Sesam Reduces Costs in Maritime and Offshore Engineering. Engineers designing ship hulls and offshore floaters can now save

FORAN for Pertamina's Future Ships

FORAN has been chosen by state-owned company PERTAMINA to review the design of their future oil product carrier ships, under construction in a shipyard with the FORAN System.

Ports

3D Printing in Rotterdam Port

Is 3D printing just a hype? Or is it really possible to print spare parts for ships that can actually withstand the requirements set for the often "rough" working

Caltex Replaces Australian Crew

The 36 Australian crew members of an Caltex tanker refusing to set sail after they were told their jobs would be gone after the next run. MR tanker Alexander Spirit (40,

Mombasa Port Workers End Strike

Mombasa, Kenya port workers end strike and returned to work on Friday after being warned they could lose their jobs, reports Reuters.   However the members of

News

Aberdeen Pupils Peek into Subsea Oil & Gas Technology

Pupils at an Aberdeen primary school were given a rare insight into the depths of the oil and gas industry’s subsea sector after getting to sit in the driving

AVEVA, DNV GL's Sesam Integration Cuts Cost

Integration of Aveva and DNV GL's Sesam Reduces Costs in Maritime and Offshore Engineering. Engineers designing ship hulls and offshore floaters can now save

FORAN for Pertamina's Future Ships

FORAN has been chosen by state-owned company PERTAMINA to review the design of their future oil product carrier ships, under construction in a shipyard with the FORAN System.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Offshore Oil Pipelines Pod Propulsion Salvage Ship Simulators Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2010 sec (5 req/sec)