Offshore Float-over Installation Generates Renewed Interest

Posted by Irina Tabakina
Wednesday, June 18, 2014
Bigger and heavier decks are on the horizon, installed in more remote locations.

An offshore installation method that is more than three decades old is generating renewed interest from many operators who are challenged with designing heavy-lift crane installations. Float-over installation has become a cost-effective alternative to lift installation for offshore construction, as ever-increasing size and weight of decks constantly exceed the lifting capacity of floating cranes.
Exploration of oil and gas in more remote offshore fields is driving the increasing demand for larger offshore units along with float-over installations. In the coming four years, an estimated 660 offshore production platforms are expected to be constructed worldwide of which 180 weigh more than 12,000 tons.
Dockwise has a track record transporting and installing 15 topsides and with five in the backlog. The SHWE topside installation in 2012 was one of the world’s largest and heaviest topsides transported to date, weighting 30,000 tons (including the deck support frame–DSF) and transported for more than 4,000 nautical miles over a period of 23 days.

Float-over Strengths

Float-over installations have innate benefits due to the installation approach. One of the key strengths of the float-over is the lack of rendezvous risk, which is the schedule risk resulting from the need to have the crane and vessel in the field at the same time. In principle, float-over installations do not have a weight limitation as today’s heavy transport vessels (HTVs) are capable to transport and install mega sized topsides. In addition, integrated platform installation eliminates extensive offshore hook-up and commissioning resulting in limited overall offshore exposure.

Float-over Phases

There are several phases involved when installing a deck with a semisubmersible HTV. The first is the standby phase where the HTV is at a safe distance from the jacket but connected to the mooring system. Last minute arrangements such as preparing the vessel’s ballast system or the hydraulic jacks are under way.
The second is the docking phase where the vessel carefully enters the jacket slot, the distance between the jacket legs. Winches or tugs are used to pull the HTV carefully into position.
In the third phase, pre-mating, the vessel positions the deck directly above the jacket. Once positioned, the HTV ballasts to match the leg mating unit (LMU) with the receptors on top of the jacket legs. During this phase, it is critical that the vessel motions be limited to suit the chosen LMU geometry. No weight transfer yet occurs.
For a successful float-over operation, countless hours of preparation come down to the exact moment when the deck makes contact with the jacket. The fourth phase is the most critical point of the installation leaving no room for uncertainty in the functionality of the load transferring equipment.
In the mating phase, the deck is lowered onto the jacket by the vessel’s rapid ballasting system where large quantities of water enter the ballast tanks, which enable the HTV to submerge. During this phase, the deck’s weight is completely transferred from the vessel onto the jacket. Custom engineered elastomer is used in the design of the LMUs to dampen the friction during load transfer.
In the post-mating phase, the deck sits secure on top of the jacket and a gap is created between the deck support unit (DSU) and the HTV to ensure vessel motions will not cause contact between the two.
In the exit phase, the vessel departs from the jacket slot on its own propulsion or with assistance from tugs. These five phases may slightly differ depending on equipment and installation approach.

Float-over Requirements
There are three essential specifications required for an HTV to perform a float-over. The first is the HTV’s width being the right size. The vessel must be narrow enough to fit inside the jacket slot. Secondly, the vessel must be designed with an open stern and equipped with movable casings. The open stern enables the HTV to exit the jacket slot during the last phase of an installation. To ensure the deck is perfectly positioned onboard the vessel, casings, which facilitate balance and ballasting, can be moved to best accommodate the cargo. Lastly, HTVs must have sufficient strength and stability to carry and transport heavy decks.

(As published in the June 2014 edition of Maritime Reporter & Engineering News - http://magazines.marinelink.com/Magazines/MaritimeReporter)

Maritime Reporter June 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

News

New Binding Law of The Sea Agreement Advanced

WOC Sustainable Ocean Summit (Singapore, 9-11 November 2015) Will Enable Industry to Organize its Input to this Major New Ocean Treaty Development The U.N.

Oceans Can’t Take Any more: Researchers Fear Fundamental Change

Our oceans need an immediate and substantial reduction of anthropogenic greenhouse gas emissions. If that doesn’t happen, we could see far-reaching and largely

Teekay LNG Partners Declares Distribution

Teekay GP LLC, the general partner of Teekay LNG Partners L.P. has declared a cash distribution of $0.70 per unit for the quarter ended June 30, 2015. The cash distribution is payable on August 14,

Marine Equipment

New Binding Law of The Sea Agreement Advanced

WOC Sustainable Ocean Summit (Singapore, 9-11 November 2015) Will Enable Industry to Organize its Input to this Major New Ocean Treaty Development The U.N.

Technip Samsung JV Wins 2 FLNG Project Contracts

The Browse project covers the realization and installation of three FLNG units to develop the Brecknock, Calliance and Torosa fields in the Browse Basin, 425 kilometers North of Broome,

Fjords Processing Bags Johan Sverdrup Contracts

Fjords Processing, headquartered in Norway (Fornebu), has won three contracts for the deliveries of process systems for the Johan Sverdrup development in the North Sea.

Offshore Energy

Technip Samsung JV Wins 2 FLNG Project Contracts

The Browse project covers the realization and installation of three FLNG units to develop the Brecknock, Calliance and Torosa fields in the Browse Basin, 425 kilometers North of Broome,

Fjords Processing Bags Johan Sverdrup Contracts

Fjords Processing, headquartered in Norway (Fornebu), has won three contracts for the deliveries of process systems for the Johan Sverdrup development in the North Sea.

Ocean Safety, Richard Irvin Marine Safety Merger

Ocean Safety has today announced the merger with Richard Irvin Energy Solutions Marine Safety Division and their Aberdeen branch.   This merger follows the

 
 
Maritime Security Maritime Standards Naval Architecture Navigation Pipelines Pod Propulsion Salvage Ship Electronics Ship Simulators Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2354 sec (4 req/sec)