Offshore Float-over Installation Generates Renewed Interest

Posted by Irina Tabakina
Wednesday, June 18, 2014
Bigger and heavier decks are on the horizon, installed in more remote locations.

An offshore installation method that is more than three decades old is generating renewed interest from many operators who are challenged with designing heavy-lift crane installations. Float-over installation has become a cost-effective alternative to lift installation for offshore construction, as ever-increasing size and weight of decks constantly exceed the lifting capacity of floating cranes.
Exploration of oil and gas in more remote offshore fields is driving the increasing demand for larger offshore units along with float-over installations. In the coming four years, an estimated 660 offshore production platforms are expected to be constructed worldwide of which 180 weigh more than 12,000 tons.
Dockwise has a track record transporting and installing 15 topsides and with five in the backlog. The SHWE topside installation in 2012 was one of the world’s largest and heaviest topsides transported to date, weighting 30,000 tons (including the deck support frame–DSF) and transported for more than 4,000 nautical miles over a period of 23 days.

Float-over Strengths

Float-over installations have innate benefits due to the installation approach. One of the key strengths of the float-over is the lack of rendezvous risk, which is the schedule risk resulting from the need to have the crane and vessel in the field at the same time. In principle, float-over installations do not have a weight limitation as today’s heavy transport vessels (HTVs) are capable to transport and install mega sized topsides. In addition, integrated platform installation eliminates extensive offshore hook-up and commissioning resulting in limited overall offshore exposure.

Float-over Phases

There are several phases involved when installing a deck with a semisubmersible HTV. The first is the standby phase where the HTV is at a safe distance from the jacket but connected to the mooring system. Last minute arrangements such as preparing the vessel’s ballast system or the hydraulic jacks are under way.
The second is the docking phase where the vessel carefully enters the jacket slot, the distance between the jacket legs. Winches or tugs are used to pull the HTV carefully into position.
In the third phase, pre-mating, the vessel positions the deck directly above the jacket. Once positioned, the HTV ballasts to match the leg mating unit (LMU) with the receptors on top of the jacket legs. During this phase, it is critical that the vessel motions be limited to suit the chosen LMU geometry. No weight transfer yet occurs.
For a successful float-over operation, countless hours of preparation come down to the exact moment when the deck makes contact with the jacket. The fourth phase is the most critical point of the installation leaving no room for uncertainty in the functionality of the load transferring equipment.
In the mating phase, the deck is lowered onto the jacket by the vessel’s rapid ballasting system where large quantities of water enter the ballast tanks, which enable the HTV to submerge. During this phase, the deck’s weight is completely transferred from the vessel onto the jacket. Custom engineered elastomer is used in the design of the LMUs to dampen the friction during load transfer.
In the post-mating phase, the deck sits secure on top of the jacket and a gap is created between the deck support unit (DSU) and the HTV to ensure vessel motions will not cause contact between the two.
In the exit phase, the vessel departs from the jacket slot on its own propulsion or with assistance from tugs. These five phases may slightly differ depending on equipment and installation approach.

Float-over Requirements
There are three essential specifications required for an HTV to perform a float-over. The first is the HTV’s width being the right size. The vessel must be narrow enough to fit inside the jacket slot. Secondly, the vessel must be designed with an open stern and equipped with movable casings. The open stern enables the HTV to exit the jacket slot during the last phase of an installation. To ensure the deck is perfectly positioned onboard the vessel, casings, which facilitate balance and ballasting, can be moved to best accommodate the cargo. Lastly, HTVs must have sufficient strength and stability to carry and transport heavy decks.

(As published in the June 2014 edition of Maritime Reporter & Engineering News - http://magazines.marinelink.com/Magazines/MaritimeReporter)

Maritime Reporter August 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

LQT Delivers Accommodation Facility and Helideck in Gulf of Mexico

LQT Industries , a full-service provider of accommodation facilities, design-build construction services, and support services to the oil and gas industry, has

Upcoming Expo 'Offshore Marintec Russia'

ExpoForum Convention and Exhibition Centre in St. Petersburg, October 7-10  will host the International Specialised Offshore Exhibition and Conference 'Offshore

RWE Dea Awarded Two New Concessions in Egypt

In the International Bid Round 2013, RWE Dea has been awarded two new offshore concessions with operatorship by the Egyptian General Petroleum Corporation (EGPC).

News

Jet Edge Celebrates 30 Years in Waterjet Industry

Waterjet systems manufacturer Jet Edge, Inc. celebrated its 30th anniversary Sept. 3 with a special open house celebration. Jet Edge’s anniversary event included

TITAN Salvage Receives NAMEPA Award

The North American Marine Environment Protection Association (NAMEPA) announced earlier this month that Houston-based TITAN Salvage, a subsidiary of Crowley Maritime Corp.

Second Sailing Added to Cleveland-Europe Express

The Port of Cleveland and Amsterdam-based Spliethoff Group announced today their mutual intent to add a second monthly vessel to the Cleveland-Europe Express (CEE),

Marine Equipment

Maritime Reporter @ 75: The Daily Cartoon

Maritime Reporter & Engineering News was founded by John J. O'Malley (1905-1980) in 1939, and today ranks as the world's largest audited trade publication in the world serving the maritime industry,

Jet Edge Celebrates 30 Years in Waterjet Industry

Waterjet systems manufacturer Jet Edge, Inc. celebrated its 30th anniversary Sept. 3 with a special open house celebration. Jet Edge’s anniversary event included

3D Scanning Speeds Up Drag Boat Racing

NVision, Inc., a company in 3D laser scanning and reverse engineering for over 24 years, said it was able to help a motorsports boat designer optimize the design

Offshore Energy

LQT Delivers Accommodation Facility and Helideck in Gulf of Mexico

LQT Industries , a full-service provider of accommodation facilities, design-build construction services, and support services to the oil and gas industry, has

Ricardo to Support Kongsberg WFMS Development

Ricardo and Kongsberg have signed a framework agreement that will see Ricardo support the development of the Kongsberg Wind Farm Management System (WFMS) as well

Aiming to Make Less Fuel Go Further: Maersk Drilling

Maersk Drilling says it is engaged in an energy efficiency project for its newbuilds together with Maersk Maritime Technology. The project involves an Energy Management System (MSPS),

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Naval Architecture Offshore Oil Pipelines Port Authority Salvage Ship Electronics Ship Simulators Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1890 sec (5 req/sec)