Valemon Topsides Installed

By Michelle Howard
Monday, July 28, 2014
Two hours after the Valemon topsides weres lifted off the transport vessel, the structure landed on its feet. (Photo: André Osmundsen/Statoil)

On Monday, July 28, the topsides were lifted into place on the steel jacket on the Valemon field in the North Sea. Produced by Samsung Heavy Industries this is the first Statoil topsides built in South Korea.

The structure sailed from the yard on June 15 this year, and after a quick stop in Åmøyfjorden, Stavanger, last Saturday, it headed out to the field. The transportation to Norway took 40 days.

“This is a major milestone for the project, the most important milestone of course being start-up towards the end of the year,” said Bjørn Laastad, vice president for Valemon field development.

The lift of the 9,750-metric-ton topsides took two hours, and was performed slightly earlier than initially assumed.

Thanks to good weather in the North Sea this summer, the Saipem 7000 crane vessel was available for lifting once the topsides arrived in Norway. The weather was favorable also when the crane vessel and the topsides arrived on the field. “We had almost perfect lifting conditions,” Viktor Nilsen-Nygaard, head of Valemon transportation and installation, reports from the crane vessel.

After the topsides were lifted into place, the flare boom was installed. 

The more than two-year planning period has included very thorough safety evaluations for all phases of the lifting operation. From mid-June the West Elara rig pre-drilled production wells through the jacket on the field.

The rig’s derrick has been pulled in during the lifting operations. During the lift the distance between the topsides and rig was just five meters.

The well operations will resume in mid-October. According to plan three wells will be producing when the field comes on stream at the end of the year. The rig’s job, however, will be far from finished.  Drilling on the field is planned to continue until 2017.

In the months ahead commissioning work will take place on the field. Wells will be hooked up with production facilities on board, sea water pumps will be installed, and electricity, water and pipelines will be connected.

Valemon will be powered from Kvitebjørn, and the cable has already been laid on the seabed. So have the pipelines that will be transporting gas and condensate to Heimdal and Kvitebjørn, respectively.

“Some work remains before we are ready for start-up, but we are on track,” Laastad said.

In order to accommodate everyone involved in the commissioning and hook-up work Statoil has chartered a flotel. The project thus has bed capacity for some 400 people, which is the number expected to be offshore, at least in the most hectic period. But there is one thing that cannot be planned – and that’s the weather. 

“If we get much poor weather the flotel must be disconnected in periods. Poor weather also creates problems for the helicopter traffic, and may delay the commissioning work. So far, however, we have been lucky with the weather, and I hope this continues,” Laastad said.

Valemon will utilize existing installations and pipelines for gas and condensate export. The gas from Valemon will be transported through the existing pipeline from Huldra to Heimdal, which is a hub for transportation further to the gas markets in Europe.

The condensate will be piped to Kvitebjørn for stabilization, and transported from there to the Mongstad refinery near Bergen. 

This is a win-win situation which reduces the costs for the Valemon development, and gives Heimdal and Kvitebjørn new tasks. At Heimdal major upgrading has taken place which significantly extends the platform’s life.

  • The Valemon topsides landed on the jacket just before 13.00. (Photo: André Osmundsen/Statoil)

    The Valemon topsides landed on the jacket just before 13.00. (Photo: André Osmundsen/Statoil)

Maritime Reporter September 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds


Finland Scraps LNG Terminal Plan

Finnish gas utility Gasum has abandoned its plans to build the Finngulf liquefied natural gas  (LNG) import terminal in Finland with an offshore pipeline connection

MARAD Backs Emissions Reduction Projects

The U.S. Department of Transportation’s Maritime Administration (MARAD) announced it will provide more than $1 million to support the development of two new emission-reducing maritime solutions.

Rolls-Royce to Cut More Staff of Marine Unit

Britain's Rolls-Royce said it would cut an additional 400 staff from its marine business by the end of next year, its latest move to make the unit more efficient


PCCI to Provide Revised Crane Load Chart

PCCI, Inc. of Alexandria, Virginia, was awarded a contract by the Department of Transportation/U.S. Maritime Administration (MARAD) to provide a new, revised

Adani Ports, L&T Ink Pact for Kattupalli Port Operations

Adani Ports  has entered into a non-binding Memorandum of Understanding with L&T Shipbuilding Limited (L&T) for evaluating the operations of the port at Kattupalli,

Arctic Ice 'Too Thick' for Shipping Route

Sea ice in the Arctic is still too thick for Northwest Passage commercial shipping route in spite of warming temperatures. This is according to new research from York University.


Search for Ship Lost in Hurricane a Big Challenge

Deep seas may complicate efforts to find the sunken U.S. cargo ship lost off the Bahamas during Hurricane Joaquin, a federal safety investigator said, as a search

Weak Capesize Rates Depress Baltic Index

The Baltic Exchange's main sea freight index, which tracks rates for ships carrying dry bulk commodities, fell on Tuesday on weak demand for capesize vessels. The overall index,

U.S. Investigators Head to Florida to Probe Ship Lost in Hurricane

Federal safety investigators traveled to Florida on Tuesday to investigate the U.S. container ship lost at sea after being hit by powerful Hurricane Joaquin, leaving

Offshore Energy

MacGregor's Deck Machinery for Sentinel Marine ERRV

MacGregor, part of Cargotec, will supply deck machinery for a new 65m emergency rescue & response vessel (ERRV) for Sentinel Marine. The ship has been designed

Finland Scraps LNG Terminal Plan

Finnish gas utility Gasum has abandoned its plans to build the Finngulf liquefied natural gas  (LNG) import terminal in Finland with an offshore pipeline connection

Kruszewski Joins Braemar Engineering

Braemar Engineering, the specialist maritime engineering consultancy, today announced the appointment of Chis Kruszewski to the role of Senior Electrical Engineer in its Offshore,

Maritime Security Maritime Standards Naval Architecture Pipelines Salvage Ship Repair Ship Simulators Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1891 sec (5 req/sec)