Valemon Topsides Installed

By Michelle Howard
Monday, July 28, 2014
Two hours after the Valemon topsides weres lifted off the transport vessel, the structure landed on its feet. (Photo: André Osmundsen/Statoil)

On Monday, July 28, the topsides were lifted into place on the steel jacket on the Valemon field in the North Sea. Produced by Samsung Heavy Industries this is the first Statoil topsides built in South Korea.

The structure sailed from the yard on June 15 this year, and after a quick stop in Åmøyfjorden, Stavanger, last Saturday, it headed out to the field. The transportation to Norway took 40 days.

“This is a major milestone for the project, the most important milestone of course being start-up towards the end of the year,” said Bjørn Laastad, vice president for Valemon field development.

The lift of the 9,750-metric-ton topsides took two hours, and was performed slightly earlier than initially assumed.

Thanks to good weather in the North Sea this summer, the Saipem 7000 crane vessel was available for lifting once the topsides arrived in Norway. The weather was favorable also when the crane vessel and the topsides arrived on the field. “We had almost perfect lifting conditions,” Viktor Nilsen-Nygaard, head of Valemon transportation and installation, reports from the crane vessel.

After the topsides were lifted into place, the flare boom was installed. 

The more than two-year planning period has included very thorough safety evaluations for all phases of the lifting operation. From mid-June the West Elara rig pre-drilled production wells through the jacket on the field.

The rig’s derrick has been pulled in during the lifting operations. During the lift the distance between the topsides and rig was just five meters.

The well operations will resume in mid-October. According to plan three wells will be producing when the field comes on stream at the end of the year. The rig’s job, however, will be far from finished.  Drilling on the field is planned to continue until 2017.

In the months ahead commissioning work will take place on the field. Wells will be hooked up with production facilities on board, sea water pumps will be installed, and electricity, water and pipelines will be connected.

Valemon will be powered from Kvitebjørn, and the cable has already been laid on the seabed. So have the pipelines that will be transporting gas and condensate to Heimdal and Kvitebjørn, respectively.

“Some work remains before we are ready for start-up, but we are on track,” Laastad said.

In order to accommodate everyone involved in the commissioning and hook-up work Statoil has chartered a flotel. The project thus has bed capacity for some 400 people, which is the number expected to be offshore, at least in the most hectic period. But there is one thing that cannot be planned – and that’s the weather. 

“If we get much poor weather the flotel must be disconnected in periods. Poor weather also creates problems for the helicopter traffic, and may delay the commissioning work. So far, however, we have been lucky with the weather, and I hope this continues,” Laastad said.

Valemon will utilize existing installations and pipelines for gas and condensate export. The gas from Valemon will be transported through the existing pipeline from Huldra to Heimdal, which is a hub for transportation further to the gas markets in Europe.

The condensate will be piped to Kvitebjørn for stabilization, and transported from there to the Mongstad refinery near Bergen. 

This is a win-win situation which reduces the costs for the Valemon development, and gives Heimdal and Kvitebjørn new tasks. At Heimdal major upgrading has taken place which significantly extends the platform’s life.
 

  • The Valemon topsides landed on the jacket just before 13.00. (Photo: André Osmundsen/Statoil)

    The Valemon topsides landed on the jacket just before 13.00. (Photo: André Osmundsen/Statoil)

Maritime Reporter September 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Environmental

Hurricane Gonzalo Knocks out Bermuda Power

Power was knocked out to 80 percent of Bermuda's electricity grid due to Hurricane Gonzalo, the island's only power company, Bermuda Electric Light Co., said on Friday evening.

Can Oil & Gas Superpower Lead on Climate Change?

A day before President Barack Obama addressed the United Nations to declare the nation is "stepping up to the plate" to tackle climate change, nearly 400,000

World’s 1st LNG Hybrid Barge Christened "Hummel"

The world’s first LNG hybrid barge of Becker Marine Systems was christened with the name "Hummel" on October 18, 2014, at Grasbrook Quay in HafenCity Hamburg.

Energy

Saudi Oil Pipeline Set Alight

A "limited fire" broke out on a subsidiary oil pipeline in eastern Saudi Arabia on Saturday after assailants fired shots at a security patrol, the state news agency SPA said.

Maduro Says Venezuela's 2015 Budget to Put Oil at $60

Venezuela's 2015 budget will be based on a target oil price of $60 dollars per barrel, President Nicolas Maduro said on Friday night, but he repeated expectations that prices will recover.

Hurricane Gonzalo Knocks out Bermuda Power

Power was knocked out to 80 percent of Bermuda's electricity grid due to Hurricane Gonzalo, the island's only power company, Bermuda Electric Light Co., said on Friday evening.

News

Saudi Oil Pipeline Set Alight

A "limited fire" broke out on a subsidiary oil pipeline in eastern Saudi Arabia on Saturday after assailants fired shots at a security patrol, the state news agency SPA said.

Maduro Says Venezuela's 2015 Budget to Put Oil at $60

Venezuela's 2015 budget will be based on a target oil price of $60 dollars per barrel, President Nicolas Maduro said on Friday night, but he repeated expectations that prices will recover.

Long Beach Port Adds ‘Free Time’ for Cargo to Ease Congestion

The Port of Long Beach will add an extra three days to the time that overseas import containers can remain on the docks without charge, in order to grant some

Offshore Energy

KBR, Daewoo win Eni FLNG FEED

KBR Inc. announced today that the KD Consortium, consisting of KBR and Daewoo Shipbuilding & Marine Engineering Company, Ltd, has been awarded a front end engineering

A2SEA Signs for Dudgeon

Dudgeon Offshore Wind Limited has awarded the Charter for WTG transport and installation to A2SEA A/S. A2SEA shall provide the jack-up vessel Sea Installer

GeoSea acquires HOCHTIEF Offshore Assets

DEME’s marine engineering specialist GeoSea acquires offshore assets of HOCHTIEF, one of Germany’s leading international construction groups. HOCHTIEF is selling

 
 
Maritime Careers / Shipboard Positions Maritime Standards Navigation Pipelines Pod Propulsion Salvage Ship Repair Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1757 sec (6 req/sec)