GAC Mersey Installs UK Offshore Platform

Press Release
Thursday, July 19, 2012
Conwy Platform: Photo credit GAC

GAC Shipping UK completes the successful installation of the Conwy platform 40 miles off the port of Liverpool in good time

The successful installation was completed only two months after a tug carrying the rig's jacket and topside - each weighing in at over 700 MT - set off from Rotterdam.

GAC's Liverpool office was appointed by Dutch heavy civil engineering company HSM Offshore BV to provide an integrated package of support services to construct and hook-up the platform.

The journey from the Netherlands took two and a half weeks due to bad weather resulting in ships having to seek shelter in Plymouth and Falmouth. The rig's components were eventually discharged at Seaforth Docks for modifications before being towed to the rig site around SEAFOX 1 so that construction could start.

Stephen Deakin at GAC Liverpool says that in addition to handling the ship agency for all the craft involved, his team was also involved in the procurement of plant and materials and arranging the construction of a quayside mattress to help spread the weight of the loads.

He adds: "It took an enormous amount of planning and coordination between the various parties involved - the client, engineers, pilots, the Harbour Master, a plethora of maritime experts, the crews of all the different craft and everyone involved in getting the HSM team out to the rig location to construct the Conwy platform."

 

Maritime Reporter March 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

Two Navy Contracts for GD Bath Iron Works

Included in the latest listing of contracts awarded by the US Department of Defense, Navy, are two contracts with General Dynamics Bath Iron Works, Bath, Maine.

Newport News Shipbuilding's Apprentice School to partner Old Dominion University

The Signing of a memorandum of understanding between the Apprentice School and Old Dominion University (ODU) will take place tomorrow (23rd April) at 3101 Washington Ave.

Viking Welding Delivers Fire/Rescue Boats

Fire Departments in South Carolina and Minnesota have recently accepted delivery of Response FR-28 and FR-31J boats built of welded aluminum by Viking Welding & Fabrication in Kensington, N.

Offshore

BP Gulf Spill Trial Set For January

The high-stakes penalty phase of BP's trial over its role in the 2010 U.S. Gulf of Mexico oil spill will start next January, court officials said on Tuesday,

North Sea Maintenance Offsets Lack of Sales to Asia

North Sea Forties crude differentials were unchanged on Tuesday in light trade, supported by upcoming North Sea maintenance, but the forward curve weakened due

Saipem: A Fleet Grows in Brazil

As some pre-salt plays begin production, a wide range of subsea infrastructure is being built, with O&G transportation pipeline grids being one of the vital downstream systems.

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Naval Architecture Pipelines Pod Propulsion Port Authority Ship Repair Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1213 sec (8 req/sec)