Norway's Oil Sector May Face More Project Cuts, Delays

Posted by Michelle Howard
Thursday, April 24, 2014
Credit: Harald Pettersen - Statoil

More oil and gas projects in Norway could be put on hold because of rising costs, adding to a growing list of developments that have been delayed or called off, Bente Nyland, the head of the Norwegian Petroleum Directorate said on Thursday.
 


Most vulnerable will be small fields, projects to increase the recovery from producing assets, and new finds further than 40 km from existing infrastructure, Nyland told Reuters.
 


Oil firms are cutting back on capital spending across the world as years of cost inflation has squeezed margins, cutting back their ability to pay dividends.
 


Norway, where the per unit cost has increased 10-fold in 10 years has already fallen victim to cuts. Statoil earlier this year sharply reduced its investment budget while Shell this month called off a multi-billion dollar project to increase recovery at its Ormen Lange gas field.
 


Statoil's $15.5 billion Johan Castberg find in the Arctic, put on hold last year because of high costs, is also hanging in the balance but Nyland said she expected Statoil to eventually go ahead with the development.



"Increased costs will of course reduce the profitability of ongoing projects and might put a project on hold. The value of the future project will also be reduced," Nyland said.
 


"Costs are high and we know that companies have announced stronger investment discipline."
 


"We are afraid that this will cut some of the 165 (planned) projects to improve recovery and it might also stop the development of some of the 88 discoveries ... probably some of them will never be realized if this cost growth continues."



Increased oil recovery tends to be a low margin business and relies heavily on drilling new wells, a problem as drilling costs have doubled over the past decade.



With oil prices seen falling over the next two years and drilling costs staying high, spending on getting more out from fields can easily be abandoned, Nyland said.
 


"When the cost is increasing, you stop two things: exploration and increased oil recovery projects."
 


Developments in the Barents Sea in Norway's Arctic could also be at risk because they tend to be much further from shore than fields in the North Sea and the area lacks infrastructure.

 

(By Balazs Koranyi; Editing by David Evans)

Maritime Reporter February 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Finance

Wärtsilä, CME Offer ‘Scrubber Finance’

Funding concept promotes installation of scrubber systems by offering financing to shipowners, with returns taken from fuel price spread   In a move intended

Statoil: Johan Castberg, Snorre 2040 Timelines Changed

The licensees in the Johan Castberg and Snorre 2040 licences have decided to spend more time on the projects. “Castberg and Snorre 2040 are two major and important projects in our portfolio,

Wärtsilä, Clean Marine Energy Offer "Scrubber Finance"

Wärtsilä and Clean Marine Energy (Europe) Ltd (CME) today announced the landmark signing of the shipping industry's first collaboration agreement that will provide

Energy

EU to Deliver Climate Pledge to UN

EU ministers agreed on Friday to send their formal promise on how much they will cut greenhouse gas emissions to the United Nations ahead of climate change talks starting in November.

New Floating Installation Concept for Offshore Wind

Conquest Offshore, together with deugro Denmark A/S, has developed an installation system for monopiles and transition pieces, supported by Temporary Works Design (TWD) and Barge Master.

Royal IHC Merges Four Units into IHC IQIP

Royal IHC (IHC) has integrated four of its business units – IHC Hydrohammer, IHC Handling Systems, IHC Sea Steel and IHC Fundex Equipment – into one new organization,

News

IACS Comments on MOL Comfort Report

The International Association of Classifications Societies (IACS) informs it will study the final report issued in Japan by the Committee on Large Container Ship Safety (CLCSS),

EU to Deliver Climate Pledge to UN

EU ministers agreed on Friday to send their formal promise on how much they will cut greenhouse gas emissions to the United Nations ahead of climate change talks starting in November.

NV Charts Relocates US Headquarters

NV Charts has moved its offices and warehousing facilities to centrally-located Deale, Maryland, U.S. In announcing the move, Hasko Scheidt, CEO, said, “As we’ve grown and need room for expansion,

Offshore Energy

New Floating Installation Concept for Offshore Wind

Conquest Offshore, together with deugro Denmark A/S, has developed an installation system for monopiles and transition pieces, supported by Temporary Works Design (TWD) and Barge Master.

Royal IHC Merges Four Units into IHC IQIP

Royal IHC (IHC) has integrated four of its business units – IHC Hydrohammer, IHC Handling Systems, IHC Sea Steel and IHC Fundex Equipment – into one new organization,

CTruk OWSV Enhanced with Volvo IPS

Since the launch of its first-of-class CTruk MPC22 late last year, the East Anglia-based workboat designer and builder informs it has incorporated performance feedback

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Naval Architecture Offshore Oil Pod Propulsion Salvage Ship Electronics Ship Simulators Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2096 sec (5 req/sec)