TDW Helps Relieve Stress on Riser Offshore Malaysia

Posted by Eric Haun
Thursday, June 26, 2014
Photo courtesy of T.D. Williamson

Comprehensive pipeline services solution allows preventive measures to be carried out safely

T.D. Williamson (TDW) announced that it recently completed a comprehensive pipeline services program for a major offshore operator to assist with efforts to relieve increasing contact stress between a gas export riser and platform jacket offshore East Malaysia.

Due to changes in seabed conditions, the platform jacket had moved, producing stress on the gas export riser attached to the platform jacket. The stress was most acute at the contact point between the bracings - or riser clamps - that anchor the riser to the platform structure. Concerned that the amount of stress developing at the contact point could eventually damage the riser, the operator decided that the best solution was to cut out and remove a section of the jacket bracing. Removal of the brace would not affect the technical integrity of the structure.

To ensure that the bracing could be safely removed from the pipeline, the customer requested TDW to isolate the affected section of the subsea line by inserting and setting a remotely-operated SmartPlug isolation tool in the line approximately 100m from the platform. By doing so, only a short section of the pipeline had to be depressurized and isolated while the bracing was removed. The only alternative would have been to depressurize the entire pipeline, which would have been extremely time consuming and costly. Further complicating the situation was the fact that the line is tied in to another major pipeline that extends to a central riser complex. This line would have had to have been bled down as well, causing major disruption to overall production from the field.

Before the pipeline could be isolated, however, it became apparent that one of the topside motor-operated valves (MOVs) closest to the pig launcher would not open properly, so it would have to be replaced in order that the SmartPlug tool could reach the point of isolation. To rectify this, TDW performed a hot tap and STOPPLE plug isolation on the line at a point located on the riser above the shutdown valve (SDV), thereby providing double-block isolation so that the operator could safely replace the malfunctioning MOV. Once the MOV was replaced, TDW launched the SmartPlug tool to the set location in order to isolate the line connected to the jacket bracing, which required a section removed. The line was isolated for five ¬days, which allowed a diving contractor to safely remove the bracing without disrupting production. The SmartPlug tool was then unset and retrieved back to the launcher.

Unexpected situation demands full range of pipeline services
As a result of the unforeseen requirement to replace the MOV, the challenges faced by the customer grew significantly. TDW worked closely with the customer to make certain that, in spite of the MOV replacement, the bracing would be safely removed within the original timeframe. First, TDW manufactured a special custom fitting for the hot tap and STOPPLE plugging operation at its manufacturing plant in Tulsa, Oklahoma in a very short time. TDW then managed the entire operation, working closely with its teams in Norway, Belgium and Singapore, and collaborating with its network of trusted specialists to provide welding, and nitrogen and water pumping services. TDW performed all this in just four months.

“Our customer was faced with a unique and pressing challenge: to relieve the increasing stress on the riser by removing the subsea bracing, without disrupting production,” said Rolf Gunnar Lie, Business Development Manager – Asia Pacific for TDW. “The fact that a defective MOV prevented us from immediately isolating this line so that the bracing could be removed safely could have been a real setback, delaying this critical work for months. In addition to SmartPlug pressure isolation services, TDW has deep experience in hot tap and STOPPLE plugging services, so we were able to help solve this problem and move forward rapidly,” he added. TDW made it possible for the customer to extract the bracing, which alleviated the growing pressure on the riser, ensuring that it continues to operate safely.

TDW’s relationship with the operator dates back 12 years, supplying pipeline pressure isolation services to facilitate safe maintenance activities on export lines and pipeline tie-ins. This recent operation was executed as part of a framework agreement between the two companies, which was extended in 2012.

Construction works trigger increased demand for isolation services

With operators keen to protect live pipelines and maintain production while construction or repair works take place, TDW reports increased demand for its specialist pipeline isolation services, particularly in Asia Pacific. By isolating a designated section of a pipeline with its SmartPlug technology, customers avoid the trouble and expense of having to completely depressurize the entire line. In addition, the line can remain isolated for extended periods - months, if necessary - while work is carried out, or if work is delayed due to inclement weather or other extenuating circumstances.

tdwilliamson.com

 

  • Photo courtesy of T.D. Williamson

    Photo courtesy of T.D. Williamson

Maritime Reporter October 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Energy

US House to Hold Hearing on Oil Export Ban

A House of Representatives panel will hold a hearing on Dec. 11 to explore whether a decades-old law that prohibits the export of crude oil makes sense in an era of domestic energy abundance.

Energy’s Promising Future Threatened

Unrealistic Fears and Overstated Risks obscure the benefits of new seismic data. The United States stands poised on the edge of a bright energy future. After decades

Pile Testing for Wikinger Wind Farm Launched

In October 2014 the first phase of the pile testing campaign for the Wikinger offshore wind farm project was launched after the site’s geotechnical investigation on the Baltic Sea had been completed.

News

US House to Hold Hearing on Oil Export Ban

A House of Representatives panel will hold a hearing on Dec. 11 to explore whether a decades-old law that prohibits the export of crude oil makes sense in an era of domestic energy abundance.

Bollinger Delivers 11th FRC to the US Coast Guard

Bollinger Shipyards, Inc. has delivered the William Trump, the 11th Fast Response Cutter (FRC) to the United States Coast Guard.   The announcement was made by Bollinger Chief Operating Officer,

Australian Defence Minister Says Would Not Trust Submarine Firm to Build Canoe

Australia's defence minister has said he would not trust state-owned Australian Submarine Corp (ASC) "to build a canoe", fuelling expectations that most work in

Maritime Safety

Avoiding the Edges of the Sea

Mariners do best when they avoid the edges of the sea – the shoals, rocks, and other hard spots.  Coming into contact with the edges of the sea at other than a

The Legal Consequences of 46 CFR Subchapter “M”

As the holiday season and the end of another year quickly approaches, the towing industry patiently waits for the Coast Guard to finalize the long-awaited towing vessel inspection rule.

Fire Departments Choose Sea-Fire Systems

Metalcraft Marine's Firestorm high-speed, aluminum fireboat represents a new generation in vessel technology, especially when fitted with Sea-Fire H Series engineered fire suppression systems.

Offshore Energy

Pile Testing for Wikinger Wind Farm Launched

In October 2014 the first phase of the pile testing campaign for the Wikinger offshore wind farm project was launched after the site’s geotechnical investigation on the Baltic Sea had been completed.

Damen, Palfinger Upgrade North Sea Jack-Up Rig

With the support of Palfinger systems JUMP technology, Damen Shiprepair Vlissingen has completed an upgrade of a Keppel Fels ‘N’ Class drilling rig, one of the largest in the North Sea,

Vietnam Warship Visits Underscore Regional Tension

Vietnam on Tuesday showed off its two most powerful warships in the first-ever port call to the Philippines but an official said it was not trying to challenge

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Naval Architecture Navigation Offshore Oil Pod Propulsion Salvage Ship Electronics Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1748 sec (6 req/sec)