Gjøa Platform on Its Way Home

Monday, June 14, 2010
Photo courtesy Statoil

After a period of development lasting five years, the Gjøa field is approaching start-up. On Sunday 13 June the field tow commenced of one the most modern platforms built in Norway. It was quite a milestone when the Gjøa platform was towed out into the fjord off Aker Solutions Stord shipyard.

“It feels incredibly good to finally send the platform out to the field. Many millions of work-hours lie behind this milestone,” acknowledged Statoil’s vice president for the Gjøa field development, Kjetel Digre.

Out in the fjord four huge anchor-handling vessels tautened the cables and the journey out to the field in the northern part of the North Sea commenced.

For work on Gjøa has not been without unexpected obstacles. An unusually long and snow-laden winter created a number of challenges for the project. And when spring finally arrived the platform tow had to be postponed.

A systematic review revealed that some minor modifications had to be carried out to the platform hull, and Gjøa had to remain in dock for an extended period.

“We have tackled a number of unforeseen hitches on the Gjøa project. So far we have solved all the challenges without delaying the planned start-up in the fourth quarter of 2010. This says a lot about what our project people are made of and it also speaks volumes about the need for having access to a competent specialist network, both in Statoil and at our suppliers,” states Digre.

Even though 70% of the work on Gjøa was carried out by Norwegian suppliers, the field development consists of pieces from all over the world.

“The gigantic jig-saw puzzle of these last five years has been solved thanks to an impressive cooperation between an incredible number of people, in Statoil and at our suppliers,” acknowledges Digre.

The tow out to the field is expected to take one and a half days. Work will then start on connecting the platform to the subsea installations and the pipelines that have already been made ready. Final trials and completion work, which can only be carried out on the field, will ensue before test production of oil and gas can start. It is expected that the field will come into regular production in the fourth quarter of 2010.

Gjøa will be the first floating platform to be supplied with electricity from shore. This will reduce environmental emissions equivalent to those from 100,000 passenger cars.

The field was proven in 1989 and its reserves are reckoned to amount to 82 million barrels of oil and condensate and 40 billion cubic metres of gas.

Statoil is development operator for the field while GDF SUEZ E&P Norge will take over as operator when Gjøa comes on stream.

Maritime Reporter September 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds


Seadrill Hopes to See Market Turn in 2017

Offshore rig driller Seadrill is facing another two years in the doldrums but hopes the international rig market could turn around in 2017.   Rig rates have more

Eni Arctic Service Rig Extension Okayed

Italian oil company Eni has received permission from Norway's Petroleum Safety Authority to extend the use of a service rig on its troubled Arctic Goliat oil field offshore Norway until Nov.

Oil Spill Statfjord North Sea Field - Statoil

Loading of tankers suspended, unclear when it will resume. Oil spilled into the North Sea during the loading of a tanker at Norway's Statfjord field on Thursday, operator Statoil said.

Maritime Contracts Maritime Standards Naval Architecture Navigation Pipelines Pod Propulsion Salvage Ship Electronics Ship Simulators Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1901 sec (5 req/sec)