Gjøa Platform on Its Way Home

Monday, June 14, 2010
Photo courtesy Statoil

After a period of development lasting five years, the Gjøa field is approaching start-up. On Sunday 13 June the field tow commenced of one the most modern platforms built in Norway. It was quite a milestone when the Gjøa platform was towed out into the fjord off Aker Solutions Stord shipyard.

“It feels incredibly good to finally send the platform out to the field. Many millions of work-hours lie behind this milestone,” acknowledged Statoil’s vice president for the Gjøa field development, Kjetel Digre.

Out in the fjord four huge anchor-handling vessels tautened the cables and the journey out to the field in the northern part of the North Sea commenced.

For work on Gjøa has not been without unexpected obstacles. An unusually long and snow-laden winter created a number of challenges for the project. And when spring finally arrived the platform tow had to be postponed.

A systematic review revealed that some minor modifications had to be carried out to the platform hull, and Gjøa had to remain in dock for an extended period.

“We have tackled a number of unforeseen hitches on the Gjøa project. So far we have solved all the challenges without delaying the planned start-up in the fourth quarter of 2010. This says a lot about what our project people are made of and it also speaks volumes about the need for having access to a competent specialist network, both in Statoil and at our suppliers,” states Digre.

Even though 70% of the work on Gjøa was carried out by Norwegian suppliers, the field development consists of pieces from all over the world.

“The gigantic jig-saw puzzle of these last five years has been solved thanks to an impressive cooperation between an incredible number of people, in Statoil and at our suppliers,” acknowledges Digre.

The tow out to the field is expected to take one and a half days. Work will then start on connecting the platform to the subsea installations and the pipelines that have already been made ready. Final trials and completion work, which can only be carried out on the field, will ensue before test production of oil and gas can start. It is expected that the field will come into regular production in the fourth quarter of 2010.

Gjøa will be the first floating platform to be supplied with electricity from shore. This will reduce environmental emissions equivalent to those from 100,000 passenger cars.

The field was proven in 1989 and its reserves are reckoned to amount to 82 million barrels of oil and condensate and 40 billion cubic metres of gas.

Statoil is development operator for the field while GDF SUEZ E&P Norge will take over as operator when Gjøa comes on stream.

Maritime Reporter March 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

U.S. DoI Upholds 2008 Shell Arctic Lease

The U.S. Interior Department on Tuesday upheld a 2008 lease sale in the Chukchi Sea off Alaska, moving Royal Dutch Shell a step closer to returning to oil and gas

Japan, U.S. Look to Expand Naval Cooperation

Japanese Prime Minister Shinzo Abe's push to allow Tokyo to come to the aid of an ally under attack will pave the way for closer cooperation between U.S. and Japanese forces across Asia, a top U.

BP Terminates GoM Rig Contracts

BP terminated contracts for two deepwater oil drilling rigs in the Gulf of Mexico as the British oil company slashes its exploration budget due to fallen oil prices.

 
 
Maritime Contracts Maritime Standards Navigation Offshore Oil Pipelines Pod Propulsion Salvage Ship Repair Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.0939 sec (11 req/sec)