Delayed Production Start at Njord after Gas Leak

Press Release
Tuesday, April 26, 2011
The Njord-platform. Archive photo: Statoil

Production on the Njord platform was shut down on April 24 as a result of operational problems with gaskets in a gas export compressor. Later the same day, during work to resume production, a gas leak was discovered in one of the risers.

All production on Njord was immediately shut down and will remain shut down until the cause of the leak has been determined.

Production at the Njord field has been shut down since April 1 as a safety measure, while inspection of risers is carried out after earlier discoveries of internal damage to a particular type of flexible pipe.

The first instances of damage were discovered during a planned inspection last autumn, and an inspection programme was initiated which is now being carried out. Riser inspection is also being carried out at the Visund field.

Risers are the pipes that convey oil and gas from the seabed to the installation, and consist of several layers of plastic and steel. Production at Njord and Visund is planned to be phased in again in due course as inspection of the risers confirms that they are in order, or after they have been repaired or replaced.

The Njord field resumed partial production on April 16, but was shut down again on April 24 when manual measurements during a work operation revealed a gas leak from one of the risers after an automatic shutdown. The well was contained when the leak occurred.

The riser in which the leak was discovered was quickly depressurised, and production and the other risers were shut down in a controlled manner.

The Norwegian Petroleum Safety Authority (PSA) has been informed of the incident.

Shutdown delays production from the field. The total field production for Njord is around 70,000 barrels of oil equivalents (oe).

Risers on all installations are subject to constant monitoring and routine inspections in accordance with applicable inspection programmes.

Source: Statoil

Maritime Reporter June 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

2545 Candidates Vie for 11 Positions in Maersk Drilling

2545, that is exactly how many applicants applied for the 11 MITAS engineer positions available in Maersk Drilling in 2014. The Maersk International Technology and Science Programme,

GDI Awards N-KOM US$110-M Contracts

Gulf Drilling International (GDI) Limited, a subsidiary of Gulf International Services (GIS), the largest oilfield service company in Qatar, has awarded two contracts

Statoil Awarded Licence Offshore Colombia

Statoil has been awarded interest in the COL4 licence offshore Colombia in the Caribbean Sea in the 2014 Colombia Licensing Round. Statoil will hold 33,33% in the licence.

 
 
Maritime Contracts Maritime Security Naval Architecture Offshore Oil Pipelines Port Authority Ship Electronics Ship Simulators Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1990 sec (5 req/sec)