Floating Production System Orders Outlook

By Jim McCaul, IMA
Wednesday, May 14, 2014
Projected Growth Global Natural Gas Demand (Quadrillion Btu)

An EPC contract for a production unit can easily exceed $1 billion – and $3 billion for an FPSO has recently been breached.  Overall, this is a $20 to $30 billion annual market.  But, as described below, the sector is hitting some headwinds that could impact future business opportunities.

Backlog of Planned Floater Projects
243 floating production projects are in various stages of planning as of beginning May. Of these, 57% involve an FPSO, 16% another type oil/gas production floater, 23% liquefaction or regasification floater and 5% storage/offloading floater.
Brazil, Africa and SE Asia are the major locations of floating production projects in the visible planning stage.  We are tracking 50 projects in Brazil, 49 in Africa and 46 projects in SEA – 60% of the visible planned floating production projects worldwide.
Around 25% of the projects are at an advanced stage of development.  They typically have either entered the FEED phase, pre-qualification of floater contractors has been initiated or bidding/negotiation is in progress.  Award of the production floater contract in these projects is likely within the next 2-3 years.  The remaining 75% of the planned projects are in an early stage of development.   Contract awards are more likely in the 3+ year time frame.
 
Future Business Drivers

The large number of projects at the ready-to-go stage is clearly a positive indicator for future floating production equipment orders.  However, timing of the decision to proceed to contracting will be influenced by future underlying market conditions. Fundamentals driving future orders in the floating production market remain generally positive.  World oil and gas demand continues to grow, crude pricing remains in the $100 to $110 range and deepwater drillers are operating at high utilization. But the sector is hitting competition from shale/tight oil and gas supply, energy companies have been cutting capital spending budgets and deepwater drillers are not quite as bullish as in recent past. 

Growing Demand for Oil and Gas

On the positive side, global oil demand has grown at an average rate of 1.4% annually over the past 20 years.  With the exception of two years during the global financial meltdown, oil demand has increased year over year during this period. Growth in oil demand is widely expected to continue over the foreseeable future.  The IEA, for example, sees world oil demand in 2035 growing to 101 mb/d, an increase of 11% over today.  Global natural gas demand is also growing.  Gas consumption doubled between 1980 and 2010 and has grown another 13% since.  Over the past decade global natural gas consumption declined in only one year – 2009 as a result of the financial crisis. 
The EIA sees world gas consumption growing at an annual rate of 1.7% through 2040.  ExxonMobil projects a 65% increase in natural gas demand by between 2010 and 2040.

Unconventional Oil & Gas Supply
But unconventional oil and gas resources are changing the supply landscape.  Use of horizontal drilling and hydraulic fracturing to exploit oil and gas resources locked in shale, siltstone and mudstone, as well as production of oil from oil sands, has opened huge new sources of energy supply. 
Nowhere is the development of unconventional oil resources more rapidly advancing than in North America.  Between 2011/2014 the production of oil in the US and Canada increased 39%, primarily the result of incremental production of shale/tight oil in the US and oil sands resources in Canada.   As a result, production of oil in the US and Canada now accounts for 27.6% of non-OPEC oil production – up from 22% in 2011.
Development of shale/tight oil resources outside the US has been much slower due to land rights issues, access to drill equipment, environmental opposition to fracking, etc.  But the shale/tight oil revolution will undoubtedly spread beyond the US.   Opportunities are too big to ignore.  The EIA estimates that shale/tight oil resources worldwide total 345 billion barrels – and account for 10 percent of global oil reserves. 
The equally spectacular revolution in shale/tight gas production is changing global gas supply and is threatening the dominance of major players in the LNG sector.   And like shale/tight oil, the shale/tight gas revolution is centered in North America.   
Production of shale/tight gas in the US is projected to grow 52% over the next decade.   According to the EIA, shale and tight gas is expected to provide 71% of US natural gas production in 2024, up from 61% today.   In 2024 the US is expected to be producing 22.5 TCF of natural gas from shale and tight rock formations – the equivalent of more than three times the current natural gas production of Qatar.  
A substantial, though yet unclear, portion of future U.S. gas production will be exported as LNG. BP expects that the U.S. “will become a net LNG exporter from 2016, reaching a total net LNG export volume of 11.2 Bcf/d by 2035.”  ExxonMobil sees North America shifting “from a net importer to a net exporter of natural gas by 2020 as production outpaces demand.”  
Like oil, development of shale/tight gas resources outside the US has been much slower due to land rights issues, limited drill equipment, environmental opposition to fracking, etc.  But the shale/tight gas revolution will undoubtedly spread beyond the US.   As with shale/tight oil, the opportunities are too big to ignore.  The EIA estimates that world shale gas resources total 7299 Tcf – 32% of world natural gas resources
Shale/tight oil and gas development ultimately competes with deepwater for investment resources.  These resources are finite – and energy companies will channel their investment resources to the opportunities offering the best financial return.  Given the advances taking place in the shale/tight rock sector, it is reasonable to conclude that the shale/tight rock revolution is eroding investment in deepwater projects.
Significantly, the competitive balance is shifting in favor of shale/tight rock.  The cost of drilling shale/tight wells is falling – and well productivity is increasing.  Meanwhile, technical challenges of ultra-deepwater development, local content barriers and an overheated industrial base are forcing deepwater costs higher.
The pace of activity in the deepwater drilling sector is one of the best predictors of future equipment demand in the floating production sector.  The higher the pace of activity in the drill sector, the better the outlook for future floating production project starts.  According to Rigzone, drillship utilization in April was 84.8%, semisubmersible rigs 85.7%.  This includes utilization of drillships/semis in the competitive inventory.  These figures are historically strong and there has been little change in utilization over the past year.  But the less-than-positive message that many drillers recently have been giving about anticipated market conditions in deepwater drilling suggests a softening in the drill market is taking place – which is not good news for near term deepwater projects starts
Global oil demand keeps growing, but growth in unconventional oil supply is pressuring future crude prices, energy companies are cutting back on capital expenditures, drillers are reporting market softening and shale/tight oil and gas opportunities are attracting investment resources that otherwise might be used for deepwater projects. Time will tell how these positive and negative drivers combine to impact future orders in the sector.   But it appears that a dampening impact is already being felt. Since the beginning of this year there have been orders for six production floaters – 4 FPSOs, an FLNG and a production barge.  This is roughly in line with the average ordering pace over the past ten years – but in terms of increment to inventory the ordering pace has declined.

 

The Author
IMA provides market analysis and strategic planning advice in the marine and offshore sectors. Over 40 years we have performed more than 350 business consulting assignments for 170+ clients in 40+ countries. We have assisted numerous shipbuilders, ship repair yards and manufacturers in forming a a plan of action to penetrate the offshore market.  Assignments included advice on acquiring an FPSO contractor, forming an alliance to bid for large FPSO contracts, satisfying local content requirements, etc.
Tel: 1 202 333 8501
e: imaassoc@msn.com
www.imastudies.com

(As published in the May2014 edition of Maritime Reporter & Engineering News - http://magazines.marinelink.com/Magazines/MaritimeReporter)

  • By Jim McCaul, IMA

    By Jim McCaul, IMA

  • Annual Growth in Global Oil Demand Over Past Two Decades  (% change year over year)

    Annual Growth in Global Oil Demand Over Past Two Decades (% change year over year)

  • Projected U.S. Natural Gas Production  From Shale and Tight Rock Formations  (Trillions of cubic feet/year)

    Projected U.S. Natural Gas Production From Shale and Tight Rock Formations (Trillions of cubic feet/year)

  • By Jim McCaul, IMA
  • Annual Growth in Global Oil Demand Over Past Two Decades  (% change year over year)
  • Projected U.S. Natural Gas Production  From Shale and Tight Rock Formations  (Trillions of cubic feet/year)
Maritime Reporter March 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

China Unveils Action Plan on Maritime Silk Road

China has unveiled the principles, framework, and cooperation priorities and mechanisms in its Maritime Silk Road initiative in a bid to enhance regional connectivity

JV Wins $2bln Freeport LNG Contract in US

A joint venture (JV) between CB&I, Chiyoda International and Zachry Industrial has won a contract worth over $2bn from FLNG Liquefaction 3 for a liquefied natural

Feds Delay LNG’s Port Ambrose Application

The US Coast Guard and the US Maritime Administration (MARAD) have temporarily suspended their review of the proposed Port Ambrose deep-water LNG import terminal.

Finance

Scandlines Ferry Back in Service by End June

The damaged Scandlines ferry M/V Prinsesse Benedikte is being repaired at the Polish shipyard Remontowa and is expected to be ready before the end of June 2015.

Greece Will Sell Piraeus Port Stake in Weeks

The Greek government will sell its majority stake in the port of Piraeus within weeks, the country's deputy prime minister told China's official Xinhua news agency,

India May Add Japanese Soryu-Class Submarines to its Fleet

India is reportedly considering a project to incorporate six Japanese Soryu-class diesel-electric submarines into its fleet, says The Japan Times.   The Defense

Energy

USA Urged Not to Delay Arctic Drilling

The U.S. should immediately begin a push to exploit its enormous trove of oil in the Arctic waters off of Alaska, or risk a renewed reliance on imported oil in the future, reports AP.

Feds Delay LNG’s Port Ambrose Application

The US Coast Guard and the US Maritime Administration (MARAD) have temporarily suspended their review of the proposed Port Ambrose deep-water LNG import terminal.

Austal Graduates 48 4-Yr Apprentices

Austal USA combined two classes to graduate a total of 48 members of Austal’s cutting-edge four-year apprenticeship program yesterday at a formal ceremony held at the Arthur R.

News

Gulf Bridge Express Service to End

The Gulf Bridge Express Service will shortly be terminated with the last roundtrip voyage being MV Saint Nikolaos voyage 00008S, ETA New Orleans on April 22, 2015.

Obangame Express 2015 Concludes in the Gulf of Guinea

Maritime forces from Gulf of Guinea nations, Europe, South America, and the United States and several regional and international organizations concluded the multinational maritime exercise,

Scandlines Ferry Back in Service by End June

The damaged Scandlines ferry M/V Prinsesse Benedikte is being repaired at the Polish shipyard Remontowa and is expected to be ready before the end of June 2015.

Offshore Energy

Nations Convene for Arctic Maritime Discussion

Citing an increasing need to ensure safety, security and stewardship of Arctic waters, member countries of the Arctic Council gathered at U.S. Coast Guard Headquarters

Advanced Drillships a Burden for Owners as Business Slows

Not so long ago, advanced drillships costing more than half a billion dollars each and capable of operating in ever-deeper waters practically guaranteed big profits for oil-rig operators.

Russia May Allow More Firms to Offshore Oil

Russia may allow more oil companies to access its offshore projects, Energy Minister Alexander Novak said on Friday.   "In general, the access can be extended," Novak told reporters in Moscow.

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Offshore Oil Pipelines Salvage Ship Electronics Ship Simulators Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2754 sec (4 req/sec)