Omega Morgan Eyes Aging Bridge Projects

MarineLink.com
Tuesday, October 01, 2013
Omega Morgan specially designed a truss beam for the installation of the collapsed Skagit River Bridge. Piles could not be driven under the Akrow Bridge (part of the Skagit Bridge) so the company’s 70-foot trussed beam was specially made to support the new 950-ton bridge. (Photo courtesy Omega Morgan.)

Omega Morgan, a 22-year-old specialized moving company, has its eyes on the aging bridges in the Pacific Northwest. After successfully employing the jack-and-slide method of efficiently moving bridge spans into place for two high-profile projects, the company sees more opportunities in Oregon and Washington.

In January, Omega Morgan moved Portland’s 1,100-foot-long, 3,400-ton Sellwood Bridge across the Willamette River in a single day, in one piece and on an angle, drawing national media and big crowds.

Then in Washington State on the night of Sept. 14, an OM crew of eight jacked up a 915-ton span, slid it upriver and set it onto original concrete piers with new pedestals installed to accommodate the concrete beams arrangement. They slid the bridge span into place in just hours—not days—to get up to 71,000 vehicles-per-day moving across the Skagit River.

That last project came about after the Skagit River Bridge collapsed May 23 when a tall truckload hit several overhead crossbeams. This accident put a spotlight on old and damaged bridges across the U.S.

For example, in 2012, the Washington Department of Transportation said 70 projects across the state would receive a portion of $130 million in federal funds to repair or replace aging bridges.

One report said of Oregon’s total 7,631 bridges, 438 are deficient and the average is 42 years. In Washington, the average bridge age is 43 and of the 7,806 total, 362 are deficient.

“Some of these bridges are beyond the point of repair and need to be replaced,” said Kathleen Davis, director of Highways & Local Programs with WSDOT. “Plenty of them, though, can be repaired, which will add many more years of operation to their lifespan.”

Omega Morgan is one of the few companies in the region that does both jacking and sliding of bridges, making it a turnkey operation without any downtime. It takes expertise, too, explains the company’s chief engineer Ralph Di Caprio. “We had less than two inches of clearance on each side of the SkagitBridge, which was 162 feet long and 60 feet wide. This was really a precise move,” he said.

The project, including Omega Morgan’s deft jack and slide move, gets traffic moving more quickly, makes commuters happy and has caused politicians to ask why other projects like this can’t be more efficient.

The result is that the state of Washington has organized forums to talk about cost-cutting in similar projects and caused the governor to cite the move as proof of the state’s can-do-attitude and professionalism of the department of transportation.

In an article in the Seattle Times, the question is being asked why other highway jobs seem to take years and hundreds of millions of dollars to complete.

Max J. Kuney of Spokane was general contractor for the project. Kuney hired Parsons Brinckerhoff in Seattle for Skagit bridge engineering and Omega Morgan to tackle the heavy lifting and skidding.

Meanwhile, Omega Morgan pointed south in between the Pacific Northwest jobs and managed to jack and slide two bridge overpasses in Utah. “This is something we like to do and we’d like to have more of these projects,” Di Caprio said.

omegamorgan.com

  • Northwest-based Omega Morgan won a bid to jack up 915-ton span and then slid it onto steel columns for the Skagit River Bridge in Washington State. This photo is of the bridges after the new span was jacked down into place. The jack-and-slide method meant traffic could get moving more quickly.  The Skagit Bridge made national news when a truckload hit several crossbeams, causing it to collapse and putting a spotlight on thousands of aging bridges across the nation. (Photo courtesy Omega Morgan.)

    Northwest-based Omega Morgan won a bid to jack up 915-ton span and then slid it onto steel columns for the Skagit River Bridge in Washington State. This photo is of the bridges after the new span was jacked down into place. The jack-and-slide method meant traffic could get moving more quickly. The Skagit Bridge made national news when a truckload hit several crossbeams, causing it to collapse and putting a spotlight on thousands of aging bridges across the nation. (Photo courtesy Omega Morgan.)

Maritime Reporter September 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Singapore’s MPA Discuss LNG Bunkering

The Maritime and Port Authority of Singapore (MPA), Antwerp Port Authority, Port of Rotterdam and Port of Zeebrugge participated in a Liquefied Natural Gas (LNG)

Key to Somalia's Recovery

Piracy, terrorism and criminal activities originating in Somalia can only be addressed by creating a climate of security, engagement and empowerment that will encourage home grown businesses,

Long Beach Port Honors OOCL Executive

Andrew Tung, CEO and Managing Director of Orient Overseas Container Line, was presented today with the prestigious “Port Pilot Award” by the Long Beach Board of Harbor Commissioners.

News

USCG Reopens Port Allen Post Hurricane Ana

The Coast Guard Captain of the Port reopened Port Allen in Kauai Monday morning after surveying crews deemed it  safe for transit. The maritime public is advised

TRIYARDS Buys into Aluminium Shipbuilding Expertise

TRIYARDS Holdings Limited, an offshore vessel fabrication and engineering solutions provider to the oil and gas (O&G) industry, has added new capabilities, products

Singapore’s MPA Discuss LNG Bunkering

The Maritime and Port Authority of Singapore (MPA), Antwerp Port Authority, Port of Rotterdam and Port of Zeebrugge participated in a Liquefied Natural Gas (LNG)

 
 
Maritime Contracts Maritime Standards Naval Architecture Offshore Oil Pipelines Pod Propulsion Ship Electronics Ship Repair Ship Simulators Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.4575 sec (2 req/sec)