Aker Solutions Slow Out of the Blocks

Press Release
Monday, April 29, 2013

"The slow start to 2013 is truly disappointing," says Øyvind Eriksen, Executive Chairman of Aker Solutions ASA.

Aker Solutions decided to disclose preliminary information on its financial performance in the first three months of 2013 as the results so far considerably lag current consensus market estimates.

Aker Solutions expects to report revenue of NOK 11.1 billion and earnings before interest, tax, depreciation and amortisation (EBITDA) of NOK 868 million for the first quarter of 2013.

The earnings were impacted by increased costs at the Ekofisk Zulu platform project as work was accelerated to ensure the platform will be transported from the Egersund yard to the Ekofisk field in mid-June and start producing oil by October 2013. Extra work caused by quality issues related to cables delivered by a sub-supplier also increased the project's costs. Aker Solutions' Maintenance, Modifications and Operations (MMO) business area manages 60 percent of the project, while the company's Engineering business area manages 40 percent. The final project result will depend on bonus payments triggered by timely delivery, start-up of the platform and the final settlement with the customer.

Results were also weighed down by a loss of NOK 63 million at the Umbilicals business area. Aker Solutions in the first quarter wrote down the value of several Umbilicals projects following a thorough review of the entire portfolio. Several of the projects have, as previously reported, suffered from operational challenges in Norway. As a turnaround plan is about to be implemented, the Umbilicals business area is expected to generate a low, but positive EBITDA margin in the second quarter.
The earnings were also impacted by a loss of NOK 54 million at the Oilfield Services and Marine Assets (OMA) business area as the vessels Aker Wayfarer and Skandi Aker were idle in the first quarter. The OMA business area is expected to incur additional losses in the second quarter as Aker Wayfarer and Skandi Aker are set to remain idle until commencing operations in mid-June and mid-July, respectively. The Cat B project is, as previously communicated, in a system definition phase where Aker Solutions and the client are in a dialogue on how to proceed. The parties will spend the time required to find a solution and no news should be expected in the near future.

In addition, EBITDA margins for the business areas Drilling Technologies, Well Intervention Services and Mooring and Loading Systems were slightly lower in the first quarter than the average in recent quarters, mainly because of increased costs at some projects, some delayed contract awards and timing of progress.

Aker Solutions will present a full set of first-quarter earnings on May 8, 2013. The figures reported today are preliminary and have not been discussed or approved by the Aker Solutions Board of Directors.

"The slow start to 2013 is truly disappointing," says Øyvind Eriksen, Executive Chairman of Aker Solutions ASA. "As lost or postponed contract awards are part of the game, some of the quality issues are, simply speaking, unacceptable. We have worked hard to avoid such mistakes, but there is still a way to go. My hope is that the customers appreciate our efforts to deliver according to our commitments to safeguard their commercial interests and that we ultimately will be able to find amicable solutions to some of the additional costs."

 

Maritime Today


The Maritime Industry's original and most viewed E-News Service

Maritime Reporter July 2016 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Young Taken on PESA Advisory Board

Hoover Container Solutions’ chairman and CEO, Donald Young, has been nominated and elected to the Petroleum Equipment & Services Association (PESA) Advisory Board for a three-year term.

US Navy Tests Latest Aegis Weapon System

The U.S. Navy conducted a series of cooperative air defense test exercises with the Spanish navy that culminated in live missile firing events using the latest Aegis Weapon System baseline July 20-21.

Antwerp Port CEO Scoops Baron Title

After 25 years as CEO of Antwerp Port Authority, Eddy Bruyninckx has been raised to the nobility by H.M. the king of Belgium with the rank of baron. In Belgium

Offshore

MOL Signs Long-Term Charter with Uruguayan JV for FSRU

Japanese shipping company Mitsui O.S.K. Lines, has, through its wholly-owned subsidiary Lakler S.A., agreed to conclude a charter contract with Gas Sayago, for

Migrants Survivors Tell of Struggle at Sea

The bodies of 21 women and one man were brought ashore to Sicily on Friday as fellow migrants described scenes of panic and violence when water poured into their dinghy.

Three Keppel Dredgers for Jan De Nul

Keppel Offshore & Marine Ltd (Keppel O&M)'s wholly owned subsidiary Keppel Singmarine Pte Ltd (Keppel Singmarine) has secured contracts from Jan De Nul Group to

Finance

Canadian Authorities seek to contain oil spill moving down river

Authorities are building a new containment boom to fight an oil spill in a major western Canadian river, officials said on Saturday, after the spill breached a

Ecuador Pays $112 mln Award to Chevron

Ecuador has paid $112 million to energy company Chevron Corp over a four-decade-old contract dispute, even though it remains in disagreement, the head of the central bank has said.

NASSCO Bags USS Oak Hill Modification Award

General Dynamics NASSCO-Norfolk was awarded a $42 million cost-plus-award-fee modification to a previously awarded contract for the repair and alteration for the USS Oak Hill (LSD-51).

Offshore Energy

MOL Signs Long-Term Charter with Uruguayan JV for FSRU

Japanese shipping company Mitsui O.S.K. Lines, has, through its wholly-owned subsidiary Lakler S.A., agreed to conclude a charter contract with Gas Sayago, for

Ithaca’s FPF-1 platform to be moved to Stella field

Ithaca Energy Inc. reports that the "FPF-1" floating production facility has completed the required inclination test as planned and departed the Remontowa shipyard in Gdansk, Poland.

Boskalis Awarded Aberdeen Offshore Wind Farm Contract

Royal Boskalis Westminster N.V. (Boskalis) has been awarded the Offshore Balance of Plant contract by Vattenfall for the construction of Aberdeen Offshore Wind Farm,

Underwater Engineering

Pathogenic bacteria hitchhiking to North and Baltic Seas?

For the first time, AWI scientists have found evidence of living, potentially pathogenic vibrions on microplastic particles. With increasing water temperatures

Ithaca’s FPF-1 platform to be moved to Stella field

Ithaca Energy Inc. reports that the "FPF-1" floating production facility has completed the required inclination test as planned and departed the Remontowa shipyard in Gdansk, Poland.

Great Lakes Dredging Awards Announced

Great Lakes Dredge & Dock Corporation announced that it was recently awarded four contracts with an approximate value of $93 million. Great Lakes received two

 
 
Maritime Careers / Shipboard Positions Maritime Security Naval Architecture Navigation Pod Propulsion Port Authority Ship Electronics Ship Repair Ship Simulators Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1137 sec (9 req/sec)