Aker Solutions Slow Out of the Blocks

Press Release
Monday, April 29, 2013

"The slow start to 2013 is truly disappointing," says Øyvind Eriksen, Executive Chairman of Aker Solutions ASA.

Aker Solutions decided to disclose preliminary information on its financial performance in the first three months of 2013 as the results so far considerably lag current consensus market estimates.

Aker Solutions expects to report revenue of NOK 11.1 billion and earnings before interest, tax, depreciation and amortisation (EBITDA) of NOK 868 million for the first quarter of 2013.

The earnings were impacted by increased costs at the Ekofisk Zulu platform project as work was accelerated to ensure the platform will be transported from the Egersund yard to the Ekofisk field in mid-June and start producing oil by October 2013. Extra work caused by quality issues related to cables delivered by a sub-supplier also increased the project's costs. Aker Solutions' Maintenance, Modifications and Operations (MMO) business area manages 60 percent of the project, while the company's Engineering business area manages 40 percent. The final project result will depend on bonus payments triggered by timely delivery, start-up of the platform and the final settlement with the customer.

Results were also weighed down by a loss of NOK 63 million at the Umbilicals business area. Aker Solutions in the first quarter wrote down the value of several Umbilicals projects following a thorough review of the entire portfolio. Several of the projects have, as previously reported, suffered from operational challenges in Norway. As a turnaround plan is about to be implemented, the Umbilicals business area is expected to generate a low, but positive EBITDA margin in the second quarter.
The earnings were also impacted by a loss of NOK 54 million at the Oilfield Services and Marine Assets (OMA) business area as the vessels Aker Wayfarer and Skandi Aker were idle in the first quarter. The OMA business area is expected to incur additional losses in the second quarter as Aker Wayfarer and Skandi Aker are set to remain idle until commencing operations in mid-June and mid-July, respectively. The Cat B project is, as previously communicated, in a system definition phase where Aker Solutions and the client are in a dialogue on how to proceed. The parties will spend the time required to find a solution and no news should be expected in the near future.

In addition, EBITDA margins for the business areas Drilling Technologies, Well Intervention Services and Mooring and Loading Systems were slightly lower in the first quarter than the average in recent quarters, mainly because of increased costs at some projects, some delayed contract awards and timing of progress.

Aker Solutions will present a full set of first-quarter earnings on May 8, 2013. The figures reported today are preliminary and have not been discussed or approved by the Aker Solutions Board of Directors.

"The slow start to 2013 is truly disappointing," says Øyvind Eriksen, Executive Chairman of Aker Solutions ASA. "As lost or postponed contract awards are part of the game, some of the quality issues are, simply speaking, unacceptable. We have worked hard to avoid such mistakes, but there is still a way to go. My hope is that the customers appreciate our efforts to deliver according to our commitments to safeguard their commercial interests and that we ultimately will be able to find amicable solutions to some of the additional costs."

 

Maritime Reporter July 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Rosneft and NADL Sign Exchange of Assets Deal

Rosneft, Seadrill Limited and North Atlantic Drilling Limited (NADL) signed a Framework Agreement that envisages long-term cooperation in the sphere of oilfield development projects.

Norman Murray, Petrofac Chairman Quits

Petrofac, the international oil & gas facilities service provider, today announces that Norman Murray, who has been Chairman since May 2011, has resigned from

MN 100: AEP River Operations

16150 Main Circle Drive, Suite #400 St. Louis, MO 63017 Tel: (636) 530-2100  Email: info@aepriverops.com Website: www.aepriverops.com President: Keith Darling The

Offshore

Gazprom, Vietnam Boost Cooperation in Energy Sector

The Gazprom headquarters hosted a working meeting between Alexey Miller, Chairman of the Company's Management Committee and Fam Suan Shon, Ambassador Extraordinary

Rosneft and NADL Sign Exchange of Assets Deal

Rosneft, Seadrill Limited and North Atlantic Drilling Limited (NADL) signed a Framework Agreement that envisages long-term cooperation in the sphere of oilfield development projects.

EBDG Completes Repower of COLUMBIA

Elliott Bay Design Group (EBDG), a leading naval architecture and marine engineering firm with offices in Seattle, New Orleans and Ketchikan, Alaska today announced

Finance

Sinopec's Profit up at 32.5 billion yuan in 1H, 2014

Asia's largest refiner - China Petroleum & Chemical Corporation announced Friday night, according to international accounting standards, the first half net profit of 32.

Polynesian Shipping Sold to Neptune Pacific Line

The Board of Polynesian Shipping Line Limited, Apia informed   that the business and the Company’s associated investments have been sold to Neptune Pacific Line Limited.

Airbus May Sell Stake in Submarine Supplier

Airbus is considering a sale of its 49 percent stake in submarine supplier Atlas Elektronik as part of a reshuffle of its military business, German newspaper Die

Offshore Energy

Gazprom, Vietnam Boost Cooperation in Energy Sector

The Gazprom headquarters hosted a working meeting between Alexey Miller, Chairman of the Company's Management Committee and Fam Suan Shon, Ambassador Extraordinary

Rosneft and NADL Sign Exchange of Assets Deal

Rosneft, Seadrill Limited and North Atlantic Drilling Limited (NADL) signed a Framework Agreement that envisages long-term cooperation in the sphere of oilfield development projects.

Norman Murray, Petrofac Chairman Quits

Petrofac, the international oil & gas facilities service provider, today announces that Norman Murray, who has been Chairman since May 2011, has resigned from

Underwater Engineering

Kvaerner in Statoil Unmanned Platform Project

Kvaerner say that Statoil has awarded it a concept study related to a standardised, unmanned dry tree wellhead platform for the Oseberg Future Development project.

RN Diving Expert Chris Baldwin Joins IMCA

The International Marine Contractors Association (IMCA) Secretariat says that Chris Baldwin has joined its team as a Technical Adviser following a short secondment from the Royal Navy.

Permanent On-site Collision Damage Repair in Greece

In July Hydrex mobilized a team of diver/technicians to Syros, Greece, for a complex repair operation on a 118-meter, 8550 DWT chemical tanker. The vessel had suffered

 
 
Maritime Careers / Shipboard Positions Maritime Security Naval Architecture Navigation Offshore Oil Pipelines Ship Electronics Ship Simulators Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1753 sec (6 req/sec)