Aker Solutions Slow Out of the Blocks

Press Release
Monday, April 29, 2013

"The slow start to 2013 is truly disappointing," says Øyvind Eriksen, Executive Chairman of Aker Solutions ASA.

Aker Solutions decided to disclose preliminary information on its financial performance in the first three months of 2013 as the results so far considerably lag current consensus market estimates.

Aker Solutions expects to report revenue of NOK 11.1 billion and earnings before interest, tax, depreciation and amortisation (EBITDA) of NOK 868 million for the first quarter of 2013.

The earnings were impacted by increased costs at the Ekofisk Zulu platform project as work was accelerated to ensure the platform will be transported from the Egersund yard to the Ekofisk field in mid-June and start producing oil by October 2013. Extra work caused by quality issues related to cables delivered by a sub-supplier also increased the project's costs. Aker Solutions' Maintenance, Modifications and Operations (MMO) business area manages 60 percent of the project, while the company's Engineering business area manages 40 percent. The final project result will depend on bonus payments triggered by timely delivery, start-up of the platform and the final settlement with the customer.

Results were also weighed down by a loss of NOK 63 million at the Umbilicals business area. Aker Solutions in the first quarter wrote down the value of several Umbilicals projects following a thorough review of the entire portfolio. Several of the projects have, as previously reported, suffered from operational challenges in Norway. As a turnaround plan is about to be implemented, the Umbilicals business area is expected to generate a low, but positive EBITDA margin in the second quarter.
The earnings were also impacted by a loss of NOK 54 million at the Oilfield Services and Marine Assets (OMA) business area as the vessels Aker Wayfarer and Skandi Aker were idle in the first quarter. The OMA business area is expected to incur additional losses in the second quarter as Aker Wayfarer and Skandi Aker are set to remain idle until commencing operations in mid-June and mid-July, respectively. The Cat B project is, as previously communicated, in a system definition phase where Aker Solutions and the client are in a dialogue on how to proceed. The parties will spend the time required to find a solution and no news should be expected in the near future.

In addition, EBITDA margins for the business areas Drilling Technologies, Well Intervention Services and Mooring and Loading Systems were slightly lower in the first quarter than the average in recent quarters, mainly because of increased costs at some projects, some delayed contract awards and timing of progress.

Aker Solutions will present a full set of first-quarter earnings on May 8, 2013. The figures reported today are preliminary and have not been discussed or approved by the Aker Solutions Board of Directors.

"The slow start to 2013 is truly disappointing," says Øyvind Eriksen, Executive Chairman of Aker Solutions ASA. "As lost or postponed contract awards are part of the game, some of the quality issues are, simply speaking, unacceptable. We have worked hard to avoid such mistakes, but there is still a way to go. My hope is that the customers appreciate our efforts to deliver according to our commitments to safeguard their commercial interests and that we ultimately will be able to find amicable solutions to some of the additional costs."

 

Maritime Reporter March 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Newport News, ODU Partner for Bachelor's Degree Program

Huntington Ingalls Industries (HII) announced today that apprentices at Newport News Shipbuilding will now have the opportunity to earn a bachelor of science degree

Euronav Posts 62% Core Profit Increase

Belgian crude oil shipping group Euronav on Wednesday unveiled a 62 percent rise in first-quarter core profit as daily rates for its fleet rebounded from last year.

Modern Solutions Power Systems Conference

Thomas Alva Edison, who is considered to be one of the most prolific inventors in history, once said, “I find out what the world needs. Then I go ahead and try to invent it.

Offshore

Offshore Oil & Gas: Brazil’s Northern Frontier

In an effort to spread out oil and gas production to other parts of the country and increase overall oil production, Brazil has finally intensified hydrocarbon

Safety the Focus as Heavy Lifting Picks Up

Modern heavy lift capabilities are crucial for safe, efficient operations offshore Heavy lift operations offshore are an awe-inspiring feat, but an operation that

Azeri Shipyard, BP Sign Vessel Construction Contract

Azeri state energy company SOCAR's shipyard and British oil major BP have signed a $378 million deal to design and build a subsea construction vessel for the Shah Deniz II gas project,

Finance

Mitsui O.S.K. Ship Ready To Leave Chinese Port

Japanese shipping firm Mitsui O.S.K. Lines Ltd said on Thursday that its ship, the "Baosteel Emotion" 226,434 deadweight-tonne ore carrier, is ready to leave

Peel Ports Signs £100M Contract For Cranes For New Liverpool Terminal

Peel Ports Group has signed a multi-million pound deal with Shanghai-based Zhenhua Heavy Industries Co. (ZPMC) for 17 ‘mega cranes’ for its new £300m Liverpool2 container port.

Baker Hughes Announces Q2 Conference Call

Baker Hughes Incorporated (NYSE: BHI) announced today that it has scheduled a conference call on Thursday, July 17, 2014, to discuss results for the second quarter 2014, ending June 30, 2014.

Offshore Energy

Offshore Oil & Gas: Brazil’s Northern Frontier

In an effort to spread out oil and gas production to other parts of the country and increase overall oil production, Brazil has finally intensified hydrocarbon

C-MAR's Modern Approach to DP Training in Brazil

The modern offshore maritime industry heavily relies on different classes of DP vessels, from OSVs to Drillships and Tankers, almost all vessels serving the oil

UK Subsidises 8 Renewable Energy Contracts

The British government on Wednesday awarded investment contracts under a new subsidy regime to eight renewable energy projects, including five offshore wind farms and three biomass plants.

Underwater Engineering

STEM: SeaPerch Underwater Robotic Championships

University of Southern Mississippi Site for Fourth National SeaPerch Challenge – Underwater Robotic Championships Excitement continues to build for the Fourth Annual National SeaPerch Challenge,

McDermott Elect G.P. Luquette Board Chairman

Provider of integrated engineering, procurement, construction and installation (EPCI) services for upstream field developments worldwide, McDermott International, say that Gary P.

Ultra-deepwater Drillship 'Maersk Valiant' Delivered

Maersk Drilling advises that its second new drillship, 'Maersk Valiant', has been delivered from the Samsung Heavy Industries (SHI) shipyard in Geoje-Si, South-Korea.

 
 
Maritime Contracts Maritime Security Maritime Standards Navigation Offshore Oil Port Authority Salvage Ship Electronics Ship Repair Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1378 sec (7 req/sec)