Aker Solutions Slow Out of the Blocks

Press Release
Monday, April 29, 2013

"The slow start to 2013 is truly disappointing," says Øyvind Eriksen, Executive Chairman of Aker Solutions ASA.

Aker Solutions decided to disclose preliminary information on its financial performance in the first three months of 2013 as the results so far considerably lag current consensus market estimates.

Aker Solutions expects to report revenue of NOK 11.1 billion and earnings before interest, tax, depreciation and amortisation (EBITDA) of NOK 868 million for the first quarter of 2013.

The earnings were impacted by increased costs at the Ekofisk Zulu platform project as work was accelerated to ensure the platform will be transported from the Egersund yard to the Ekofisk field in mid-June and start producing oil by October 2013. Extra work caused by quality issues related to cables delivered by a sub-supplier also increased the project's costs. Aker Solutions' Maintenance, Modifications and Operations (MMO) business area manages 60 percent of the project, while the company's Engineering business area manages 40 percent. The final project result will depend on bonus payments triggered by timely delivery, start-up of the platform and the final settlement with the customer.

Results were also weighed down by a loss of NOK 63 million at the Umbilicals business area. Aker Solutions in the first quarter wrote down the value of several Umbilicals projects following a thorough review of the entire portfolio. Several of the projects have, as previously reported, suffered from operational challenges in Norway. As a turnaround plan is about to be implemented, the Umbilicals business area is expected to generate a low, but positive EBITDA margin in the second quarter.
The earnings were also impacted by a loss of NOK 54 million at the Oilfield Services and Marine Assets (OMA) business area as the vessels Aker Wayfarer and Skandi Aker were idle in the first quarter. The OMA business area is expected to incur additional losses in the second quarter as Aker Wayfarer and Skandi Aker are set to remain idle until commencing operations in mid-June and mid-July, respectively. The Cat B project is, as previously communicated, in a system definition phase where Aker Solutions and the client are in a dialogue on how to proceed. The parties will spend the time required to find a solution and no news should be expected in the near future.

In addition, EBITDA margins for the business areas Drilling Technologies, Well Intervention Services and Mooring and Loading Systems were slightly lower in the first quarter than the average in recent quarters, mainly because of increased costs at some projects, some delayed contract awards and timing of progress.

Aker Solutions will present a full set of first-quarter earnings on May 8, 2013. The figures reported today are preliminary and have not been discussed or approved by the Aker Solutions Board of Directors.

"The slow start to 2013 is truly disappointing," says Øyvind Eriksen, Executive Chairman of Aker Solutions ASA. "As lost or postponed contract awards are part of the game, some of the quality issues are, simply speaking, unacceptable. We have worked hard to avoid such mistakes, but there is still a way to go. My hope is that the customers appreciate our efforts to deliver according to our commitments to safeguard their commercial interests and that we ultimately will be able to find amicable solutions to some of the additional costs."

 

Maritime Reporter August 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Maersk Sells Ven Drilling Barges

Danish shipping conglomerate A.P. Moller-Maersk said on Tuesday its offshore oil and gas drilling unit has sold its Venezuelan barge activities. Maersk Drilling

Deadliest Weekend Ever in the Mediterranean: UNHCR

More than 700 people fleeing Africa and the Middle East may have drowned in shipwrecks in the Mediterranean over the last week, bringing the death toll this year to almost 3,

BAE Systems Awarded 'USS Hopper' Repair Contract

US Department of Defense informs BAE Systems Hawaii, Honolulu, Hawaii, is being awarded a not-to-exceed $22,905,907 undefinitized contract action to a previously

Finance

Maersk Sells Ven Drilling Barges

Danish shipping conglomerate A.P. Moller-Maersk said on Tuesday its offshore oil and gas drilling unit has sold its Venezuelan barge activities. Maersk Drilling

Trelleborg Report Optimistic for Port Investment

The latest 'Barometer Report' from Trelleborg's marine operations business sector, discusses the issues impacting ports and terminals around the globe, and reveals

Upcoming Winter Tanker Market Same as Last Year?

Will the 2014/15 winter tanker market be a repeat of the previous one? Poten & Partners consider the question in their latest 'Poten Tanker Opinion'. As the

Offshore Energy

Trelleborg Report Optimistic for Port Investment

The latest 'Barometer Report' from Trelleborg's marine operations business sector, discusses the issues impacting ports and terminals around the globe, and reveals

Technip Further Optimizes its Subsea Assets

Technip signed today an agreement to sell 100% of its North American diving assets to Ranger Offshore Inc.(1). Technip’s strategy focuses on high technology

Brazil to Hold Next Oil Rights Auction in 2015

Brazil will hold the 13th round of its oil rights auctions in the first half of next year, a senior mines and energy ministry official said on Monday. Marco Antonio Martins,

Underwater Engineering

Trelleborg Report Optimistic for Port Investment

The latest 'Barometer Report' from Trelleborg's marine operations business sector, discusses the issues impacting ports and terminals around the globe, and reveals

Oceaneering Exercise Charter Options on DP2 CSV

Oceanteam Shipping ASA says that Oceaneering International, Inc. has exercised both one year options on the CSV 'Bourbon Oceanteam 101' up to February 2017. The

InterMoor UK Completes 2,300 Accident-free Projects

InterMoor UK Operations, part of Acteon’s foundations and moorings business, says it has completed seven years and more than 2,300 projects without a single lost-time incident (LTI).

 
 
Maritime Standards Offshore Oil Pipelines Pod Propulsion Port Authority Salvage Ship Electronics Ship Repair Ship Simulators Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1638 sec (6 req/sec)