Fred. Olsen Rig Upgrade Delayed; Costs Eyed

Joseph Keefe
Tuesday, April 22, 2014
Fed. Olson image: Blackford Dolphin

Rig to cost $195 mln to upgrade vs earlier $125 mln; upgrade to be completed in June vs earlier view April. Firm's down 5.6 percent.

Norwegian rig firm Fred. Olsen Energy said on Tuesday that an upgrade on one of its most important rigs would be more expensive and would take longer than earlier thought, sending its shares sharply lower.

The Blackford Dolphin rig would cost $195 million to undergo "additional structural upgrades", which would be completed in June. In February the firm said the upgrade, part of a class renewal survey, would cost $125 million and would be completed in April.

The rig is one of the firm's two rigs that can drill in deep waters of up to 7,000 feet (2,130 metres), currently in high demand from oil and gas firms.

Fred. Olsen Energy shares were among the worst performers on the Oslo Bourse, down 6.7 percent at 0719 GMT against a benchmark index up 0.49 percent.

Separately, the firm said another of its rigs, the Borgny Dolphin, will suspend its operations off Brazil, where it was under contract from oil firm Petrobras.

The contract will cease from May. Fred. Olsen Energy did not say why the contract was stopped.


Reporting by Gwladys Fouche

 

Maritime Reporter June 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Ship Repair & Conversion

Shipping Gloomiest Since 2009

The shipping industry is the most pessimistic in six years about its prospects as a fleet surplus persists, according to a survey by law firm Norton Rose Fulbright, says a report in Reuters.

South Korea Tops in Shipbuild Orders

South Korean shipbuilders, led by industry leader Hyundai Heavy Industries Co., have secured the largest amount of new orders in the first six months of the year to retain the top slot,

MSC Geneva Gets Fatter

A revolutionary new option to scrapping for younger panamax containerships deemed too small for a tradelane involves widening the vessel rather than adding length.

Offshore

Research Vessel Concept a first for Voith

The new fisheries research vessel of the Shanghai Ocean University will be a first for Voith in several respects.   It is the first fisheries research vessel

Ocean Safety’s New Liferaft Facility Opens

Ocean Safety, a specialist in the worldwide supply, distribution, service and hire of marine safety equipment, has opened a new liferaft hire division.   Ocean

ISS Inks Service Pact with Technip

Inchcape Shipping Services (ISS) and Techniphave signed a contract to provide marine agency services and logistics for the Rashid C project in the Middle East. Currently

Finance

Buoys in Disputed Waters Roil South China Sea Dispute

Buoys stretched "as far as eye could see" - Philippine sailor. The Philippine navy recently found a large steel marker bearing Chinese inscriptions and hundreds

Navis N4 TOS Open in Liverpool Terminal

Peel Ports, owners and operators of the Port of Liverpool, has achieved a major milestone in its multi-million investment program to transform the port into Europe’s

AkzoNobel’s Carbon Credits Methodology Wins Award

AkzoNobel’s landmark carbon credits methodology for the shipping industry has won the Best Offsetting Project award in the 2015 Voluntary Carbon Market Rankings.

Energy

Buoys in Disputed Waters Roil South China Sea Dispute

Buoys stretched "as far as eye could see" - Philippine sailor. The Philippine navy recently found a large steel marker bearing Chinese inscriptions and hundreds

White House: Iran Talks Deadline Could Slip

The White House said Tuesday's deadline for negotiators in Vienna to come to a final, firm agreement on Iran's nuclear program could slip. When asked if President

Port of New Orleans Goes Green

Green Marine, a North American environmental certification program for the marine, port and terminal industry, officially recognized the Port of New Orleans recently as a certified Green Port.

Offshore Energy

ISS Inks Service Pact with Technip

Inchcape Shipping Services (ISS) and Techniphave signed a contract to provide marine agency services and logistics for the Rashid C project in the Middle East. Currently

Indonesia Expects Total to Decide on Mahakam within days

French oil firm Total  will decide how much interest it will retain from 2018 in Indonesia's offshore Mahakam oil and gas block over the next two days, the

First Subsea Wet Gas Compressor Installed

After several years of technology development, construction and testing the first subsea wet gas compressor in the world is now installed at the Gullfaks C platform in the North Sea.

 
 
Maritime Careers / Shipboard Positions Maritime Security Naval Architecture Navigation Offshore Oil Port Authority Salvage Ship Electronics Ship Repair Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1358 sec (7 req/sec)