Aker Solutions, IHI Partnership on LNG Terminal

August 25, 2009

The Aker Solutions and IHI partnership has received a signed Notice of Substantial Completion for Sempra LNG's Cameron LNG liquefied natural gas (LNG) receipt terminal near Lake Charles, La.
The Cameron LNG terminal project combined Aker Solutions' expertise in regasification engineering, construction management, commissioning and start-up with IHI's design and manufacturing knowledge of LNG storage and processing systems.
Cameron LNG's first commissioning cargo arrived June 21. A subsequent delivery was made on June 30. The terminal is capable of processing 1.5 billion standard cubic feet per day (Bscf/d) of natural gas.
Aker Industrial Constructors was responsible for construction management of many subcontracts as well as self-performing portions of direct hire construction work.
Aker Bowen, a division of Aker Plant Services Group, was responsible for leading the joint team of Aker Solutions and IHI in commissioning and start-up.
Aker Solutions US, Inc. and IHI Inc. were the contracting parties responsible for delivering the project.

Maritime Reporter Magazine Cover Oct 2016 - Marine Design Annual

Maritime Reporter and Engineering News’ first edition was published in New York City in 1883 and became our flagship publication in 1939. It is the world’s largest audited circulation magazine serving the global maritime industry, delivering more insightful editorial and news to more industry decision makers than any other source.

Maritime Reporter E-News subscription

Maritime Reporter E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

Subscribe for Maritime Reporter E-News