ACP Issues RFP for Massive Dredging Project

Tuesday, September 11, 2007
In a move that will set in motion the next phase of its Expansion Program, the Panama Canal Authority (ACP) has released its request for proposal (RFP) for the Canal’s Pacific entrance dredging. Different from the dry excavation, this project will deepen and widen the Canal’s Pacific entrance channel to ensure that longer, wider ships can reach the new locks.

The document is available at: http://www.pancanal.com/eng/procsales/buy.html

The scope of work will include the dredging of approximately 9.1 million cubic meters (321 cubic ft.) and will widen the 8.9 mile-long navigation channels at least 218 meters, deepening them to a maximum level of -15.5 meters Mean Low Water Springs (MLWS). “The Pacific entrance dredging is integral to expansion and the construction of the new lane. The Pacific side’s geological characteristics make it more challenging than the Atlantic side. We will need a firm with the specialized equipment and experience to meet the demands of the project,” said ACP Project Administration Division Manager John Langman. “We’re proud that expansion is moving forward on schedule and we look forward to attracting qualified firms for this next stage.” Prior to the release of the Pacific entrance dredging RFP, on August 7 the Panamanian National Environmental Authority (ANAM) approved the environmental impact study (EIS) for the project.

With this approval, the ACP can now move forward with the process to select a firm. Bids for the Pacific entrance dredging are due January 28, 2008, and important dates in the process include a site visit September 19 and a discussion meeting September 20. The ACP will ultimately evaluate proposals that meet the project’s needs based on a combination of best value and individual consultations with bidding firms.

Expansion will build a new lane of traffic along the Panama Canal through the construction of a new set of locks, which will double capacity and allow more traffic and longer, wider ships.

Maritime Reporter September 2013 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

ClassNK's Noboru Ueda Attends KOTC Delivery Ceremony

Mr. Noboru Ueda, Chairman and President of ClassNK attended the delivery ceremony for the M/T Al Yarmouk, constructed at Daewoo Shipbuilding & Marine Engineering Co.

Ulrich Ganz of Bernhard Schulte Joins Tundra

Tundra Group is delighted to announce the addition of the former Senior Company Security Officer (CSO) of Bernhard Schulte Shipmanagement (BSM), Captain Ulrich Ganz,

NYK Opens New Planning Center in Kumamoto

On September 1, 2014, NYK and Kozo Keikaku Engineering Inc. established a stowage planning center for container shipping at the Kumamoto office of Kozo Keikaku Engineering Inc.

Dredging

DoD Award Dredging, Ship Maintenance, Charter Contracts

US Department of Defense informs of placement of contracts for Chesapeake Bay dredging, dry-docking of USS Pearl Harbor, and charter of surface escort vessels. Details as follows: 1.

Royal IHC Starts Building EasydredgeTM 2700

Royal IHC (IHC) is constructing the first vessel in its range of competitively priced standard trailing suction hopper dredgers (TSHD). It has started to build

Restoring the NY-NJ Harbor Estuary

Significant challenges often require a team effort. Restoring the New York-New Jersey Harbor Estuary is one of them. A group of professionals from the Army Corps of Engineers,

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Pod Propulsion Port Authority Ship Repair Ship Simulators Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1347 sec (7 req/sec)