Contract, Removal of MSC Napoli Stern

Wednesday, January 07, 2009

major contract to remove the stern of the container vessel MSC Napoli has been awarded to the newly-established company Global Response Maritime B.V.,based in The Netherlands.

The contract, placed by the vessel owners, calls for the clearance of a stern section with an estimated weight of around 3,800 tonnes.

MSC Napoli became a casualty during a violent Channel storm in January 2007. The vessel was beached deliberately, in order to prevent her sinking in the English Channel. Subsequent operations, by other contractors, included recovery of bunkers, containers and the forepart of the ship.

The work scope under the new contract involves the total removal of the stern, including main engine, together with delivery of all scrap to the recovery facility of Scheepssloperij Nederland B.V. at Gravendeel, in The Netherlands.

The equipment required for removal of MSC Napoli's stern includes the crane barge "Anna" of subcontractor Hapo International Barges, two 140 m flat-top barges equipped with heavy mobile cranes and two tugs. The task also requires diving and drilling spreads and a series of 24 chain-pullers.

The project method involves drilling under the stern and the positioning of lifting chains. This part of the operation is subcontracted to DISA in Beerse, Belgium, using crane barge "Anna" as the main work platform. Chain pullers will be installed on the two lifting barges. These will be moored parallel to the stern section. The chains will then be connected up to the pullers and tensioned. The barges will be ballasted down, to compensate for the forces acting on the pullers and reduce movement in the swell.

With all preparations completed, the stern will be lifted clear of the seabed, freeing the starboard bilge keel from the trench in which the stern is embedded. At this point, the two barges will be in catamaran configuration, with the stern section suspended between them. Next they will be rotated bow into swell.

The barges' mooring systems will be reinforced with grout anchors. It will be possible to set down the stern, should this be necessary in hostile weather.

Scrapping will commence when the pullers bring the wreck to the surface. Sections with weights of around 100 tonnes will be cut and lifted onto the main decks of the barges, utilising the two cranes. This operation will continue until the weight is reduced to around 1,200 tonnes. A decision will then be taken as to whether to lift this as one unit with the assistance of a sheerlegs or continue cutting until it is within the capacity of the larger of the two cranes (rated at 500 tonnes). This crane will also recover the poop deck, rudder and propeller - which are already detached from the stern.

Monitoring the project on behalf of the Government, the Secretary of State's Representative for Maritime Salvage and Intervention, Hugh Shaw said "I am delighted that the Owners have placed another contract for the removal of the final section of the MSC NAPOLI. From the onset of the incident they have shown tremendous resolve and commitment to remove the bunkers, cargo and the wreck. This contract marks the final piece of the jigsaw and I look forward to a successful operation."

Maritime Reporter May 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Contracts

DMW Marine Takes the Lead in Military Cranes

DMW Marine Group, LLC. has completed a number of projects for the U.S. Navy and foreign Navies in recent years, claiming a place as a go-to supplier for Navy departments globally.

Shipping Freight Rates Drop Amidst Overcapacity

Shipping freight rates on the world's busiest route, from Asia to Northern Europe, fell by the largest percentage amount since 2008, reflecting wild volatility

Two ASC Kalmar Cranes for DP World Brisbane

Kalmar, part of Cargotec, has received an order from DP World Australia to deliver two new Kalmar automatic stacking cranes (ASCs) for its semi-automated terminal in Brisbane.

Salvage

Indonesia Sinks Boats from China

According to The China People's Daily, Indonesia has just sank a large Chinese vessel and 40 other foreign ships caught fishing in The South China Sea.    The

Norwegian Cruise Ship Ran Aground off Bermuda

The Norwegian Dawn cruise ship with more than 3,700 people on board ran aground in Bermuda after the vessel temporarily lost power.   Small boats, divers and

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Pipelines Pod Propulsion Port Authority Ship Electronics Ship Repair Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1430 sec (7 req/sec)