The initial phase of construction for the Canaport LNG project begins this week at Irving Canaport. Clearing of the site was completed in May 2005. The initial construction phase involves site excavation and leveling, and is the precursor to full-scale construction.

Front end engineering design for the project is now complete, and Canaport LNG issued a request for proposals for engineering, procurement and construction (EPC) earlier this summer. Onshore construction is scheduled to begin in Spring 2006.

Irving Oil Limited and Repsol YPF, S.A. announced in June that they had formed a new partnership, Canaport LNG, which will construct, own and operate the LNG regassification terminal in Saint John. The Canaport LNG terminal will be operational in 2008, initially delivering 1 billion cubic feet per day of regassified LNG into the market.

Maritime Reporter March 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Ports

Petroecuador Tenders to Buy High Octane Naphtha

State-run Petroecuador has launched two tenders to buy a total of 22 cargoes, 240,000 barrels each, of high octane naphtha RON 87 and 93 for delivery starting on May 21-23,

DP World in Talks With Banks for $3b Loan

Dubai-owned port operator DP World is in talks with lenders to triple the size of an existing $1 billion loan, as well as extend the lifespan and reduce the interest rate,

Hong Kong Receive BMT Maritime Strategic Study

BMT Asia Pacific (BMT), a subsidiary of BMT Group Ltd, says it has completed a major strategic study - “Enhancing Hong Kong’s Position as an International Maritime Centre (IMC)”,

LNG

ABS Approves Design for GTTNA’s LNG Bunker Barge

GTT North America (GTTNA), the Houston-based subsidiary of French engineering and technology company Gaztransport & Technigaz SA (GTT), received approval in principle from ABS for the design of a 2,

ISS to Support Petrobras Expansion

Inchcape Shipping Services (ISS)  has had its port agency and tanker husbandry services contract significantly enlarged by Petrobras.   The Brazilian government-owned energy giant,

Keystone Backers Keep Their Faith In Embattled Pipeline Plan

Six years after applying to build the Keystone XL pipeline, Canada's frustrated oil industry appears steadfast in its support of the plan even though Washington

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Navigation Pipelines Pod Propulsion Ship Electronics Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1422 sec (7 req/sec)