Maritrans: Missing Data = Flawed Study

Friday, February 21, 2003

Maritrans Operating Company L.P. said it believes the benefits of deepening the Delaware River to 45 ft. have been severely misstated by the U.S. Army Corps of Engineers (ACOE). The ACOE report, released in December 2002, concluded that the benefits to cost ratio of the deepening project was 1.18 to 1. The report states that the major benefit of this project is in the form of reduced lightering expenses for refineries along the Delaware River. Maritrans Operating Company L.P., which performs a very high percentage of all lightering for area refineries, reports that the ACOE understated the actual volume of lightering by approximately 25 percent and under-reported the number of hours spent lightering by approximately 35 percent. These are key statistics in the report's calculations, and Maritrans believe that the ACOE's errors result in a substantial overstatement of the benefits of the project.

Maritrans Operating Company L.P. said it provided the ACOE with historical facts about lightering operations in an effort to have the information included. While this information had previously been provided at the ACOE's request, it was not included in the final analysis of the deepening project's feasibility.

In June 2002 the U.S. General Accounting Office issued a report in which it reviewed the ACOE's initial economic justification to dredge the Delaware River to 45 ft. The ACOE agreed with the GAO findings and committed to perform a re-analysis of the economic justification for the project.

Maritime Reporter September 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Finance

Wärtsilä Expects 5% Sales Growth

Wärtsilä announced its third quarter results, reporting that it sees good development in order intake and profitability. According to Wärtsilä, third quarter

Yara Reports Strong 3Q Results

Yara International ASA delivered strong third-quarter results, with record fertilizer deliveries and continued margin benefit from lower European gas price. "Yara

Lerwick Port Awards £16.5 mi Expansion Contract

Lerwick Port Authority has awarded a construction contract for the latest expansion of the harbour’s facilities in a project costing a total of £16.5 million

Environmental

Interferry Applauds IMO Consideration of BWTS Exemption

Interferry has praised a decision made at last week’s meeting of the IMO Marine Environment Protection Committee (MEPC) that could exempt certain ferry operators

MEPC Makes Progress on Energy Efficiency, Emissions

The Marine Environment Protection Committee (MEPC) of the International Maritime Organization (IMO) met for its 67th session from October 13-17, 2014, at IMO Headquarters in London.

Bright Outlook for BWM Convention

The Danish Maritime Authority informed that the Ballast Water Management Convention is now one step closer to ratification following last week’s meeting of United

 
 
Maritime Careers / Shipboard Positions Maritime Standards Navigation Offshore Oil Pod Propulsion Ship Electronics Ship Repair Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1236 sec (8 req/sec)