Warship Construction Delay Beneficial Says Australia's Defence

Press Release
Thursday, September 06, 2012

Australia is constructing three Air Warfare Destroyers (AWD) & Defence Ministry has been advised it best to allow more time between each keel-laying.

Minister for Defence Stephen Smith, Minister for Finance and Deregulation Senator Penny Wong and Minister for Defence Materiel Jason Clare attended the laying of the keel of the first Air Warfare Destroyer (AWD) in Adelaide and provided an update on the $8 billion project.

ASC in Adelaide is the principal shipbuilder in the project.  BAE Systems in Melbourne, Forgacs in Newcastle and Navantia in Spain are also building modular blocks which will be brought together by ASC at the South Australian Government’s Common User Facility in Adelaide where the ships are being assembled.

At the keel-laying ceremony of the first AWD Hobart, Minister Smith and Minister Clare announced a re-baselining of the AWD construction schedule, the AWD Alliance having conducted a detailed analysis of the construction schedule and advised Defence that the keel to keel interval should be extended to 18 months between each ship.

Defence Department decided that extending the AWD ship building program will help avoid a decline in naval shipbuilding skills before the commencement of Australia’s largest and most complex Naval project – the Future Submarine.

They also considered that the revised AWD project plan will reduce peak demand on project critical resources and facilities, and reduces project risk, but that the new schedule will not increase the cost of the project nor result in the loss of any jobs.

It was also concluded that the re-baselined construction schedule will help Navy reduce the challenge and risks associated with accepting into service two major capabilities (Landing Helicopter Dock Ships and the Air Warfare Destroyer) at around the same time.

The re-baselined schedule will mean the delivery dates for the ships will be for HMAS Hobart (AWD01) – March 2016; HMAS Brisbane (AWD02) – September 2017 and HMAS Sydney (AWD03) – March 2019.








 

Maritime Reporter May 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

DNV GL’s Synergi to Manage Siem Offshore Newbuilding Projects

Siem Offshore has chosen DNV GL’s Synergi Project to manage nine newbuilding projects. Synergi Project software The software is used to optimize the collaboration

Bahri Inks Contracts with Hyundai to Build 5 VLCCs

The National Shipping Co. of Saudi Arabia (Bahri) signed contracts on Thursday with Hyundai Samho Heavy Industries (HSHI) to build five very large crude carriers (VLCCs),

USS George Washington Completes Carrier Qualifications

Carrier Air Wing (CVW) 5 and the Nimitz-class aircraft carrier USS George Washington (CVN 73) completed its carrier qualifications (CQ), May 23. CQ allows

Navy

Libyan War Plane Bombs another Tanker

A fighter jet operated by Libya's military force backed attacked an oil tanker that was about to anchor in the northern city of Sirte, reports local media.   Lt Gen.

US Navy Submarine to be Named USS New Jersey

The U.S. Navy's next Virginia-class attack submarine will bear the name USS New Jersey, says AP reports.   U.S. Secretary of the Navy Ray Mabus hosted a ship-naming

USS George Washington Completes Carrier Qualifications

Carrier Air Wing (CVW) 5 and the Nimitz-class aircraft carrier USS George Washington (CVN 73) completed its carrier qualifications (CQ), May 23. CQ allows

 
 
Maritime Contracts Naval Architecture Pipelines Port Authority Ship Electronics Ship Repair Ship Simulators Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2333 sec (4 req/sec)