Warship Construction Delay Beneficial Says Australia's Defence

Press Release
Thursday, September 06, 2012

Australia is constructing three Air Warfare Destroyers (AWD) & Defence Ministry has been advised it best to allow more time between each keel-laying.

Minister for Defence Stephen Smith, Minister for Finance and Deregulation Senator Penny Wong and Minister for Defence Materiel Jason Clare attended the laying of the keel of the first Air Warfare Destroyer (AWD) in Adelaide and provided an update on the $8 billion project.

ASC in Adelaide is the principal shipbuilder in the project.  BAE Systems in Melbourne, Forgacs in Newcastle and Navantia in Spain are also building modular blocks which will be brought together by ASC at the South Australian Government’s Common User Facility in Adelaide where the ships are being assembled.

At the keel-laying ceremony of the first AWD Hobart, Minister Smith and Minister Clare announced a re-baselining of the AWD construction schedule, the AWD Alliance having conducted a detailed analysis of the construction schedule and advised Defence that the keel to keel interval should be extended to 18 months between each ship.

Defence Department decided that extending the AWD ship building program will help avoid a decline in naval shipbuilding skills before the commencement of Australia’s largest and most complex Naval project – the Future Submarine.

They also considered that the revised AWD project plan will reduce peak demand on project critical resources and facilities, and reduces project risk, but that the new schedule will not increase the cost of the project nor result in the loss of any jobs.

It was also concluded that the re-baselined construction schedule will help Navy reduce the challenge and risks associated with accepting into service two major capabilities (Landing Helicopter Dock Ships and the Air Warfare Destroyer) at around the same time.

The re-baselined schedule will mean the delivery dates for the ships will be for HMAS Hobart (AWD01) – March 2016; HMAS Brisbane (AWD02) – September 2017 and HMAS Sydney (AWD03) – March 2019.








 


Shipbuilding

Austal Dives into Loss

Australia’s largest shipbuilder Austal posted a full year loss of $84.28 million because a program to build war ships for the US Navy took longer than expected.

Keppel to Deliver First North Sea FPSO

Keppel Offshore & Marine (Keppel O&M)'s wholly-owned subsidiary Keppel Shipyard Ltd (Keppel Shipyard) is on track to deliver a Floating Production Storage and Offloading

STX to Slash Jobs, Sell Yard

To stat above water by restructuring, South Korean Shipbuilder STX Offshore & Shipbuilding Co. plans to lay off about a third of its workforce and sell a yard in France, says a report in WSJ.

Navy

Michelle Obama Sponsors Attack Submarine

General Dynamics Electric Boat has delivered to the U.S. Navy an attack submarine that is sponsored by first lady Michelle Obama and will be named for her home state, reports AP.

Indian Warships Visit Port Victoria

In a demonstration of India’s commitment to its ties with Seychelles and maritime security in the Indian Ocean Region, Indian Naval Ships Kolkata, Trikand and

White House: Iranian Ships' Actions in Gulf Increase Risk of Miscalculation

Actions by Iranian vessels in several encounters with U.S. warships in the Gulf this week are cause for concern and increase risks of miscalculation, the White House said on Friday.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Navigation Offshore Oil Pipelines Port Authority Ship Electronics Ship Simulators Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.0921 sec (11 req/sec)