Warship Construction Delay Beneficial Says Australia's Defence

Press Release
Thursday, September 06, 2012

Australia is constructing three Air Warfare Destroyers (AWD) & Defence Ministry has been advised it best to allow more time between each keel-laying.

Minister for Defence Stephen Smith, Minister for Finance and Deregulation Senator Penny Wong and Minister for Defence Materiel Jason Clare attended the laying of the keel of the first Air Warfare Destroyer (AWD) in Adelaide and provided an update on the $8 billion project.

ASC in Adelaide is the principal shipbuilder in the project.  BAE Systems in Melbourne, Forgacs in Newcastle and Navantia in Spain are also building modular blocks which will be brought together by ASC at the South Australian Government’s Common User Facility in Adelaide where the ships are being assembled.

At the keel-laying ceremony of the first AWD Hobart, Minister Smith and Minister Clare announced a re-baselining of the AWD construction schedule, the AWD Alliance having conducted a detailed analysis of the construction schedule and advised Defence that the keel to keel interval should be extended to 18 months between each ship.

Defence Department decided that extending the AWD ship building program will help avoid a decline in naval shipbuilding skills before the commencement of Australia’s largest and most complex Naval project – the Future Submarine.

They also considered that the revised AWD project plan will reduce peak demand on project critical resources and facilities, and reduces project risk, but that the new schedule will not increase the cost of the project nor result in the loss of any jobs.

It was also concluded that the re-baselined construction schedule will help Navy reduce the challenge and risks associated with accepting into service two major capabilities (Landing Helicopter Dock Ships and the Air Warfare Destroyer) at around the same time.

The re-baselined schedule will mean the delivery dates for the ships will be for HMAS Hobart (AWD01) – March 2016; HMAS Brisbane (AWD02) – September 2017 and HMAS Sydney (AWD03) – March 2019.








 

Maritime Reporter April 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

Vigor’s Tacoma Yard Delivers Breasting Barges to Foss

Vigor Industrial expands its newbuild capacity in Washington; Tacoma yard delivers three breasting barges   Fabrication teams at Vigor Industrial’s Tacoma, Wash.

New Milling Disc from IN.MOTION

IN.MOTION Technology Distribution, LLC, announced the launch of a new milling disc designed for fast, efficient beveling, weld preparation and weld repair. According to the manufacturer,

Newport News Shipbuilding Hosts Sen. Inhofe

Huntington Ingalls Industries (HII) today hosted Sen. James M. Inhofe, R-Okla., for a tour of the company's Newport News Shipbuilding division.   The senator,

Navy

Newport News Shipbuilding Hosts Sen. Inhofe

Huntington Ingalls Industries (HII) today hosted Sen. James M. Inhofe, R-Okla., for a tour of the company's Newport News Shipbuilding division.   The senator,

Naval Authorities Rely on OSE Separators from GEA

The trend of modernizing ships and fitting them with more efficient separator systems, which has been noticeable since 2014 particularly in Europe and North America,

Italian Navy Takes Back Fishing Boat Seized Near Libya

The Italian navy took back control on Friday of a Sicilian fishing boat that had been seized overnight by unknown assailants near the Libyan coast, the defence ministry said.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Navigation Pod Propulsion Port Authority Salvage Ship Electronics Ship Simulators Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1247 sec (8 req/sec)