Warship Construction Delay Beneficial Says Australia's Defence

Press Release
Thursday, September 06, 2012

Australia is constructing three Air Warfare Destroyers (AWD) & Defence Ministry has been advised it best to allow more time between each keel-laying.

Minister for Defence Stephen Smith, Minister for Finance and Deregulation Senator Penny Wong and Minister for Defence Materiel Jason Clare attended the laying of the keel of the first Air Warfare Destroyer (AWD) in Adelaide and provided an update on the $8 billion project.

ASC in Adelaide is the principal shipbuilder in the project.  BAE Systems in Melbourne, Forgacs in Newcastle and Navantia in Spain are also building modular blocks which will be brought together by ASC at the South Australian Government’s Common User Facility in Adelaide where the ships are being assembled.

At the keel-laying ceremony of the first AWD Hobart, Minister Smith and Minister Clare announced a re-baselining of the AWD construction schedule, the AWD Alliance having conducted a detailed analysis of the construction schedule and advised Defence that the keel to keel interval should be extended to 18 months between each ship.

Defence Department decided that extending the AWD ship building program will help avoid a decline in naval shipbuilding skills before the commencement of Australia’s largest and most complex Naval project – the Future Submarine.

They also considered that the revised AWD project plan will reduce peak demand on project critical resources and facilities, and reduces project risk, but that the new schedule will not increase the cost of the project nor result in the loss of any jobs.

It was also concluded that the re-baselined construction schedule will help Navy reduce the challenge and risks associated with accepting into service two major capabilities (Landing Helicopter Dock Ships and the Air Warfare Destroyer) at around the same time.

The re-baselined schedule will mean the delivery dates for the ships will be for HMAS Hobart (AWD01) – March 2016; HMAS Brisbane (AWD02) – September 2017 and HMAS Sydney (AWD03) – March 2019.








 

Maritime Reporter March 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

First Supramax Vessel for Japan-Italy Venture

'DACC Tirreno' was delivered at the Oshima shipyard in Japan yesterday, the first of four Supramax bulk carriers for the dACC Maritime Limited fleet, the joint

Austal Graduates 48 4-Yr Apprentices

Austal USA combined two classes to graduate a total of 48 members of Austal’s cutting-edge four-year apprenticeship program yesterday at a formal ceremony held at the Arthur R.

BAE Systems to Expand San Diego Shipyard

BAE Systems announced it will invest approximately $100 million to expand drydocking capabilities at its San Diego shipyard.   The investment, which will include

Navy

Is China Building a Naval Base in Africa?

Recently, The Namibian reported the existence of a "confidential letter from Namibia's ambassador to China, Ringo Abed, to Namibia's foreign minister stating that

BAE Systems to Expand San Diego Shipyard

BAE Systems announced it will invest approximately $100 million to expand drydocking capabilities at its San Diego shipyard.   The investment, which will include

Indonesia Partners with China on Maritime

Indonesian President Joko “Jokowi” Widodo and Chinese President Xi Jinping pledged increased maritime cooperation during the formers visit to China.   The joint

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Naval Architecture Navigation Pod Propulsion Salvage Ship Electronics Ship Repair Ship Simulators Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1210 sec (8 req/sec)