Warship Construction Delay Beneficial Says Australia's Defence

Press Release
Thursday, September 06, 2012

Australia is constructing three Air Warfare Destroyers (AWD) & Defence Ministry has been advised it best to allow more time between each keel-laying.

Minister for Defence Stephen Smith, Minister for Finance and Deregulation Senator Penny Wong and Minister for Defence Materiel Jason Clare attended the laying of the keel of the first Air Warfare Destroyer (AWD) in Adelaide and provided an update on the $8 billion project.

ASC in Adelaide is the principal shipbuilder in the project.  BAE Systems in Melbourne, Forgacs in Newcastle and Navantia in Spain are also building modular blocks which will be brought together by ASC at the South Australian Government’s Common User Facility in Adelaide where the ships are being assembled.

At the keel-laying ceremony of the first AWD Hobart, Minister Smith and Minister Clare announced a re-baselining of the AWD construction schedule, the AWD Alliance having conducted a detailed analysis of the construction schedule and advised Defence that the keel to keel interval should be extended to 18 months between each ship.

Defence Department decided that extending the AWD ship building program will help avoid a decline in naval shipbuilding skills before the commencement of Australia’s largest and most complex Naval project – the Future Submarine.

They also considered that the revised AWD project plan will reduce peak demand on project critical resources and facilities, and reduces project risk, but that the new schedule will not increase the cost of the project nor result in the loss of any jobs.

It was also concluded that the re-baselined construction schedule will help Navy reduce the challenge and risks associated with accepting into service two major capabilities (Landing Helicopter Dock Ships and the Air Warfare Destroyer) at around the same time.

The re-baselined schedule will mean the delivery dates for the ships will be for HMAS Hobart (AWD01) – March 2016; HMAS Brisbane (AWD02) – September 2017 and HMAS Sydney (AWD03) – March 2019.








 

Maritime Reporter March 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

Shipbuilding: Vigor Industrial Grows Stronger

Vigor Industrial has ballooned from a modest shipyard in Portland, Oregon, to the largest shipbuilder in the Pacific Northwest and Alaska. Vigor increasingly thinks big and builds big.

Q-Max Floating Dock Launched

On March 21, 2014, senior management from N-KOM and Nakilat attended the launching and naming ceremony of N-KOM’s Q-Max sized floating dock at Hyundai Samho Heavy Industries in South Korea.

US Sens. Kaine and Reed Visit Newport News Shipbuilding

Huntington Ingalls Industries (HII) hosted U.S. Sens. Tim Kaine (D-Va.) and Jack Reed (D-R.I.) Tuesday for a tour of the company's Newport News Shipbuilding division.

Navy

Today in U.S. Naval History: April 16

Today in U.S. Naval History: April 16 1863 - Union gunboats pass Confederate batteries at Vicksburg 1924 - Navy commences relief operations in Mississippi Valley floods,

Australian Navy Assists French Fishing Vessel

While patrolling in the Indian Ocean off the coast of Africa, Royal Australian Navy ship HMAS Darwin provided emergency medical assistance for a heart attack victim on a French fishing vessel.

Search Resumes in S. Korean Ferry Disaster

Poor weather conditions may hamper effort; Mystery surrounds capsize of ship; Nearly 280 people still missing, many of them teenagers South Korean coastguards

 
 
Maritime Contracts Maritime Security Maritime Standards Navigation Pipelines Salvage Ship Repair Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1098 sec (9 req/sec)