Warship Construction Delay Beneficial Says Australia's Defence

Press Release
Thursday, September 06, 2012

Australia is constructing three Air Warfare Destroyers (AWD) & Defence Ministry has been advised it best to allow more time between each keel-laying.

Minister for Defence Stephen Smith, Minister for Finance and Deregulation Senator Penny Wong and Minister for Defence Materiel Jason Clare attended the laying of the keel of the first Air Warfare Destroyer (AWD) in Adelaide and provided an update on the $8 billion project.

ASC in Adelaide is the principal shipbuilder in the project.  BAE Systems in Melbourne, Forgacs in Newcastle and Navantia in Spain are also building modular blocks which will be brought together by ASC at the South Australian Government’s Common User Facility in Adelaide where the ships are being assembled.

At the keel-laying ceremony of the first AWD Hobart, Minister Smith and Minister Clare announced a re-baselining of the AWD construction schedule, the AWD Alliance having conducted a detailed analysis of the construction schedule and advised Defence that the keel to keel interval should be extended to 18 months between each ship.

Defence Department decided that extending the AWD ship building program will help avoid a decline in naval shipbuilding skills before the commencement of Australia’s largest and most complex Naval project – the Future Submarine.

They also considered that the revised AWD project plan will reduce peak demand on project critical resources and facilities, and reduces project risk, but that the new schedule will not increase the cost of the project nor result in the loss of any jobs.

It was also concluded that the re-baselined construction schedule will help Navy reduce the challenge and risks associated with accepting into service two major capabilities (Landing Helicopter Dock Ships and the Air Warfare Destroyer) at around the same time.

The re-baselined schedule will mean the delivery dates for the ships will be for HMAS Hobart (AWD01) – March 2016; HMAS Brisbane (AWD02) – September 2017 and HMAS Sydney (AWD03) – March 2019.


Maritime Reporter October 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds


Seaspan Acquires Sixth 14000 TEU Boxship

Seaspan Corporation  announced today that it accepted delivery of a 14000 TEU containership, the YM Warmth. The new containership, which was constructed at Hyundai Heavy Industries Co.

Newport News Shipbuilding Converts to Natural Gas

Huntington Ingalls Industries (HII) announced today that its Newport News Shipbuilding division has converted its steam-generation plant from heavy fuel oil, also known as Bunker C,

French President Inaugurates CMA CGM’s New Mega Ship

The CMA CGM Bougainville, the largest containership sailing under French flag, was inaugurated Tuesday by French President François Hollande in Le Havre.   Other


China Completes lighthouses construction in disputed South China Sea

China has completed the construction of two lighthouses in the disputed South China Sea, the official Xinhua news agency reported, as tensions in the region mount over Beijing's maritime ambitions.

HMS Protector Deployed to Antarctic

Ice ship HMS Protector is heading for waters no Royal Navy vessel has visited in 80 years as she begins a marathon deployment to Antarctica. The Plymouth-based

US Must Exercise Freedom of Navigation in Asia-Pacific -Navy Commander

The commander of U.S. forces in the Pacific said on Friday the United States must carry out freedom of navigation patrols throughout the Asia Pacific, but declined

Maritime Security Maritime Standards Naval Architecture Offshore Oil Pod Propulsion Port Authority Salvage Ship Repair Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.0925 sec (11 req/sec)