Warship Construction Delay Beneficial Says Australia's Defence

Press Release
Thursday, September 06, 2012

Australia is constructing three Air Warfare Destroyers (AWD) & Defence Ministry has been advised it best to allow more time between each keel-laying.

Minister for Defence Stephen Smith, Minister for Finance and Deregulation Senator Penny Wong and Minister for Defence Materiel Jason Clare attended the laying of the keel of the first Air Warfare Destroyer (AWD) in Adelaide and provided an update on the $8 billion project.

ASC in Adelaide is the principal shipbuilder in the project.  BAE Systems in Melbourne, Forgacs in Newcastle and Navantia in Spain are also building modular blocks which will be brought together by ASC at the South Australian Government’s Common User Facility in Adelaide where the ships are being assembled.

At the keel-laying ceremony of the first AWD Hobart, Minister Smith and Minister Clare announced a re-baselining of the AWD construction schedule, the AWD Alliance having conducted a detailed analysis of the construction schedule and advised Defence that the keel to keel interval should be extended to 18 months between each ship.

Defence Department decided that extending the AWD ship building program will help avoid a decline in naval shipbuilding skills before the commencement of Australia’s largest and most complex Naval project – the Future Submarine.

They also considered that the revised AWD project plan will reduce peak demand on project critical resources and facilities, and reduces project risk, but that the new schedule will not increase the cost of the project nor result in the loss of any jobs.

It was also concluded that the re-baselined construction schedule will help Navy reduce the challenge and risks associated with accepting into service two major capabilities (Landing Helicopter Dock Ships and the Air Warfare Destroyer) at around the same time.

The re-baselined schedule will mean the delivery dates for the ships will be for HMAS Hobart (AWD01) – March 2016; HMAS Brisbane (AWD02) – September 2017 and HMAS Sydney (AWD03) – March 2019.








 

Maritime Reporter September 2013 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

RIMPAC Exercise Puts LCS Through Paces

It was the middle of May, and the littoral combat ship Independence was operating out of San Diego, testing components of the mine warfare mission package. The mission is one that,

New Superyacht ROCKIT.IT Launched by Feadship

Feadship says it has launched the outstanding 60.35-metre motoryacht ROCK.IT. Created for an experienced owner who has chartered Feadships and appreciated the essence of the brand,

FTA Approves WSF Ferry Terminal Plans

In the latest Washington State Ferries Weekly Update, Capt. George A. Capacci, Interim Assistant Secretary WSDOT/Ferries Division briefs as follows: "FTA approves

Navy

RIMPAC Exercise Puts LCS Through Paces

It was the middle of May, and the littoral combat ship Independence was operating out of San Diego, testing components of the mine warfare mission package. The mission is one that,

DoD Award Dredging, Ship Maintenance, Charter Contracts

US Department of Defense informs of placement of contracts for Chesapeake Bay dredging, dry-docking of USS Pearl Harbor, and charter of surface escort vessels. Details as follows: 1.

General Dynamics Delivers North Dakota (SSN-784) to U.S. Navy

General Dynamics Electric Boat yestereday delivered the nuclear-powered attack submarine North Dakota (SSN-784) on time and more than $30 million below target cost.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Offshore Oil Pod Propulsion Port Authority Salvage Ship Simulators Shipbuilding / Vessel Construction Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1360 sec (7 req/sec)