Press Release
Thursday, September 06, 2012

Australia is constructing three Air Warfare Destroyers (AWD) & Defence Ministry has been advised it best to allow more time between each keel-laying.

Minister for Defence Stephen Smith, Minister for Finance and Deregulation Senator Penny Wong and Minister for Defence Materiel Jason Clare attended the laying of the keel of the first Air Warfare Destroyer (AWD) in Adelaide and provided an update on the $8 billion project.

ASC in Adelaide is the principal shipbuilder in the project.  BAE Systems in Melbourne, Forgacs in Newcastle and Navantia in Spain are also building modular blocks which will be brought together by ASC at the South Australian Government’s Common User Facility in Adelaide where the ships are being assembled.

At the keel-laying ceremony of the first AWD Hobart, Minister Smith and Minister Clare announced a re-baselining of the AWD construction schedule, the AWD Alliance having conducted a detailed analysis of the construction schedule and advised Defence that the keel to keel interval should be extended to 18 months between each ship.

Defence Department decided that extending the AWD ship building program will help avoid a decline in naval shipbuilding skills before the commencement of Australia’s largest and most complex Naval project – the Future Submarine.

They also considered that the revised AWD project plan will reduce peak demand on project critical resources and facilities, and reduces project risk, but that the new schedule will not increase the cost of the project nor result in the loss of any jobs.

It was also concluded that the re-baselined construction schedule will help Navy reduce the challenge and risks associated with accepting into service two major capabilities (Landing Helicopter Dock Ships and the Air Warfare Destroyer) at around the same time.

The re-baselined schedule will mean the delivery dates for the ships will be for HMAS Hobart (AWD01) – March 2016; HMAS Brisbane (AWD02) – September 2017 and HMAS Sydney (AWD03) – March 2019.








 

Maritime Reporter July 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

Pressure for Australia Sub Deal Grows

Australia to spend A$65 bln on ships and subs over 20 years; PM pledges A$40 bln for domestic shipbuilders. Australia will spend A$89 billion ($65 billion) on

Latest USCG Cutter At Boston Harbor

The Coast Guard’s latest 418-foot National Security Cutter James (WSML 754) entered Boston Harbor August 3, 2015. The James is the fifth of eight planned National

LNG Ferry Construction for Tallink Begins

The start of production of Tallink's new generation LNG powered fast ferry for the Tallinn-Helsinki route was celebrated on the 4th of August 2015 at Meyer Turku shipyard.

Navy

Pressure for Australia Sub Deal Grows

Australia to spend A$65 bln on ships and subs over 20 years; PM pledges A$40 bln for domestic shipbuilders. Australia will spend A$89 billion ($65 billion) on

Asian Nations Call for Stop to South China Sea Land Work

Calls grow for China to halt land reclamation. Southeast Asian countries on Tuesday backed a U.S. call to halt land reclamation in the South China Sea, underlining

Australian PM Promises 2500 Shipbuilding Jobs

Up to 2,500 shipbuilding jobs in Adelaide will be safe for "all time", the Prime Minister says, ahead of the expected announcement to build a new fleet of Navy ships worth $39 billion, reports ABC.

 
 
Maritime Contracts Maritime Security Maritime Standards Navigation Offshore Oil Pipelines Salvage Ship Electronics Shipbuilding / Vessel Construction Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1453 sec (7 req/sec)