Warship Construction Delay Beneficial Says Australia's Defence

Press Release
Thursday, September 06, 2012

Australia is constructing three Air Warfare Destroyers (AWD) & Defence Ministry has been advised it best to allow more time between each keel-laying.

Minister for Defence Stephen Smith, Minister for Finance and Deregulation Senator Penny Wong and Minister for Defence Materiel Jason Clare attended the laying of the keel of the first Air Warfare Destroyer (AWD) in Adelaide and provided an update on the $8 billion project.

ASC in Adelaide is the principal shipbuilder in the project.  BAE Systems in Melbourne, Forgacs in Newcastle and Navantia in Spain are also building modular blocks which will be brought together by ASC at the South Australian Government’s Common User Facility in Adelaide where the ships are being assembled.

At the keel-laying ceremony of the first AWD Hobart, Minister Smith and Minister Clare announced a re-baselining of the AWD construction schedule, the AWD Alliance having conducted a detailed analysis of the construction schedule and advised Defence that the keel to keel interval should be extended to 18 months between each ship.

Defence Department decided that extending the AWD ship building program will help avoid a decline in naval shipbuilding skills before the commencement of Australia’s largest and most complex Naval project – the Future Submarine.

They also considered that the revised AWD project plan will reduce peak demand on project critical resources and facilities, and reduces project risk, but that the new schedule will not increase the cost of the project nor result in the loss of any jobs.

It was also concluded that the re-baselined construction schedule will help Navy reduce the challenge and risks associated with accepting into service two major capabilities (Landing Helicopter Dock Ships and the Air Warfare Destroyer) at around the same time.

The re-baselined schedule will mean the delivery dates for the ships will be for HMAS Hobart (AWD01) – March 2016; HMAS Brisbane (AWD02) – September 2017 and HMAS Sydney (AWD03) – March 2019.








 

Maritime Reporter August 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

MN 100: ContainerTug B.V.

The Company: ContainerTug B.V. is a specialized Dutch naval design engineering and construction company with a strong focus on developing workboats and the evaluation

Oman Drydock Company Expands Rapidly

Oman Drydock Company (ODC) is growing fast. In January, the yard hit an important milestone - its 300th drydocking. Harnessing the power of its new $1.8 billion, 1.

NASSCO Invests in Facilities, Equipment and People

General Dynamics NASSCO has invested several hundred million in capital projects as part of its efforts to increase efficiencies via  modular shipbuilding, including:

Navy

Iranian Ship, Crew Escape Captivity off Somali Coast

An Iranian fishing vessel and its crew have escaped after being held captive for five months by Somali fishermen, maritime piracy experts said on Friday, but it

Migrant Boat Sinks off Libya; 200 Feared Dead

A boat packed with mainly African migrants bound for Italy sank off the Libyan coast on Thursday and officials said up to 200 might have died. A security official in the western town of Zuwara,

Russian-Chinese Naval Drills End

The second phase of the Russian-Chinese Joint Sea-2015 naval maneuvers has officially ended outside the port of Vladivostok in Russia’s Far East, says spokesman

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Offshore Oil Pipelines Pod Propulsion Ship Electronics Ship Repair Ship Simulators Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.6760 sec (1 req/sec)