Warship Construction Delay Beneficial Says Australia's Defence

Press Release
Thursday, September 06, 2012

Australia is constructing three Air Warfare Destroyers (AWD) & Defence Ministry has been advised it best to allow more time between each keel-laying.

Minister for Defence Stephen Smith, Minister for Finance and Deregulation Senator Penny Wong and Minister for Defence Materiel Jason Clare attended the laying of the keel of the first Air Warfare Destroyer (AWD) in Adelaide and provided an update on the $8 billion project.

ASC in Adelaide is the principal shipbuilder in the project.  BAE Systems in Melbourne, Forgacs in Newcastle and Navantia in Spain are also building modular blocks which will be brought together by ASC at the South Australian Government’s Common User Facility in Adelaide where the ships are being assembled.

At the keel-laying ceremony of the first AWD Hobart, Minister Smith and Minister Clare announced a re-baselining of the AWD construction schedule, the AWD Alliance having conducted a detailed analysis of the construction schedule and advised Defence that the keel to keel interval should be extended to 18 months between each ship.

Defence Department decided that extending the AWD ship building program will help avoid a decline in naval shipbuilding skills before the commencement of Australia’s largest and most complex Naval project – the Future Submarine.

They also considered that the revised AWD project plan will reduce peak demand on project critical resources and facilities, and reduces project risk, but that the new schedule will not increase the cost of the project nor result in the loss of any jobs.

It was also concluded that the re-baselined construction schedule will help Navy reduce the challenge and risks associated with accepting into service two major capabilities (Landing Helicopter Dock Ships and the Air Warfare Destroyer) at around the same time.

The re-baselined schedule will mean the delivery dates for the ships will be for HMAS Hobart (AWD01) – March 2016; HMAS Brisbane (AWD02) – September 2017 and HMAS Sydney (AWD03) – March 2019.








 

Maritime Reporter June 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

Yanmar Diesel Engines for Fast New Crew Tender

The expansion of the number of wind turbines out at sea near the northern Dutch coast was reason enough for Ubels Offshore to expand its fleet with a fifth ship last year.

The Hour of Power: Hybrid Marine Technology and Green Ports

In 2015 two significant developments are going to make many operators, owners and builders of professional vessels consider hybrid marine power. Firstly the new emissions laws in ports,

GTT Records Order for 2 LNG Tankers

GTT receives a new order from Hyundai Samho Heavy Industries for two LNGCs for Teekay   GTT, a designer of membrane containment systems for the maritime transportation

Navy

European Court Ups Standards for River Dredging

The European Court of Justice (ECJ) ruled on Wednesday that damage to water quality must be considered when authorities approve river dredging to expand ports,

UK Navy’s Ice Patrol Ship Gets a New Coating

U.K. Royal Navy Ice Patrol Ship HMS Protector is deployed on operations for 330 days a year, mostly in the Antarctic region, making it essential that her underwater

Crowley Takes Over Management of MSC Ships

Crowley strengthens relationship with U.S. Navy, completes turnover of Military Sealift Command T-AGOS/T-AGM fleet   Crowley Maritime Corp. announced its global

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Offshore Oil Pipelines Pod Propulsion Salvage Ship Electronics Ship Repair Ship Simulators Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1188 sec (8 req/sec)