Lessons Learned Lead to Improvements in Follow-on LCS Ships

Edward Lundquist
Monday, December 05, 2011

The U.S. Navy and its shipbuilding partners have incorporated lessons learned from the first two Littoral Combat Ships (LCS) in the design and construction of the follow-on ships.

“I think the lead ships are pretty good,” says Rear Adm. Jim Murdoch, the Program Executive Officer for LCS (PEO LCS).  “I think LCS 3 and 4 will be better.”

LCS 1 is the USS Freedom, built at Marinette Marine in Wisconsin by a team led by Lockheed Martin, and commissioned in November of 2008.  The ship deployed to U.S. Naval Forces Southern Command as well as participated in the RIMPAC fleet exercises around Hawaii in 2010.  Freedom is currently in a scheduled maintenance period in San Diego.  Commissioned in 2010, USS independence (LCS 2) was built at Austal USA in Mobile, Ala., and recently called at Naval Station Newport in Rhode Island for the 20th International Seapower Symposium.  Independence is conducting tests at sea with both the Remote Minehunting Vehicle and MH-60S Seahawk helicopter using the AQS-20 sonar in simulated minefields.

Several ships of each design are under construction at the two builders’ shipyards.  Fort Worth (LCS 3) completed builder ‘s sea trials in Lake Michigan on Oct. 24., and is due to be commissioned next year.  Coronado (LCS 4) will launch next month at Mobile.

Milwaukee (LCS 5) is under construction at Marinette, and construction of Jackson (LCS 6) has begun in Mobile.

Murdoch said that criticism regarding the cost overruns of the first two ships was well founded.  But thanks to a robust competition, the follow on ships will cost much less.

“We have two great contracts in place to provide ships at a very affordable price, and maintain a stable design,” Murdoch says.

Focused Mission Combatant

The Littoral Combat Ship (LCS) is new kind of combatant designed to operate in the littoral—or coastal—waters of the world, to address the serious threats of mines, quiet diesel submarines and small, fast armed boats that can deny access to these waters.

LCS is the first ship built to address these focused missions of mine countermeasures (MCM), anti-submarine warfare (ASW), and surface warfare (SUW), and can be configured for those missions by changing modularized mission packages.  The ship itself has ample internal volume to carry mission packages to address one of the three focused missions, and these mission packages can be quickly changed to give the ship an entirely different combat capability depending on the specific threat being addressed.  These mission packages come in containerized modules which carry offboard vehicles and sensors.  Employment of off-board manned and unmanned vehicles at a distance from the ship allows the Navy to rapidly engage threats while the ship stays at stand-off ranges.

The Navy had planned to select just one of the two competing variants to be the Navy’s choice for LCS.  But in a surprise announcement last December, Lockheed Martin Corp. and Austal USA each received a fixed-price incentive contract for the design and construction of a 10 ship block-buy, for a total of 20 littoral combat ships from fiscal 2010 through fiscal 2015.  The average ship target-price across the entire dual-block buy for the Lockheed Martin LCS variant is $362 million; and the average ship target-price for the Austal USA LCS variant is $352 million, according to Navy officials.

Correcting deficiencies

The Marinette ship had some reserve buoyancy issues, structural cracks, corrosion problems in the vicinity of the water jet tunnels, and water was coming through the anchor hawse pipe in heavy seas.

To provide additional buoyancy on LCS 1, buoyancy tanks were attached on the stern on each side of the stern door.  In LCS 3, the hull was lengthened below the water line providing more buoyancy without the tanks, and space for an additional 10 percent fuel capacity.  With the extra length, the ship is actually faster.

LCS 1 has a “clean focsle,” Murdoch says.  The anchor windlass, used to raise and lower the anchor, usually found on the main deck of most combatants, is actually inside the ship on LCS 1.  But water came into the ship in heavy seas.  By having the opening on the deck, any water coming through the hawse flows overboard.  “The new design will allow the ship to go faster in high seas.”

"With that longer underwater hull, the ship is a little more efficient,” says Murdoch.  “Just operating on the diesel engine alone, she's about a knot faster.   We're probably one to two knots faster on the gas turbine (engines) alone than Freedom was."

The LCS 1 design will have a more robust shaft seal system and improvements to the stern door leading from the waterborne mission zone top the sea so as to reduce the impact of salt water corrosion, as well as larger bridge windows.

LCS 1 has a 5-meter ridged hull inflatable boat (RHIB) as a lifeboat, mounted on the port side.  “We want a larger boat.  A design change is in the works.”

Design improvements will permit heavier loads to be carried on the LCS 1 stern ramp.  This way the 11-meter RHIB can remain on the ramp between evolutions instead of being stowed and unstowed each time, a time-consuming task.

“These are small ships with a lot of propulsion plant in them,” Murdoch says.

However, Murdoch says care is being taken not to make structural changes that increase weight.  “Either you want a ship that goes 40 knots or you don’t.”

Murdoch said LCS 2 construction required too many labor hours.  The Austal ships now feature a more modular and economic construction process.  Large blocks of the ship are built with all the installed piping and wiring, and are mostly complete and tested when fitted to the other parts of the ship.  In addition, the LCS 4 centerline waterjets are larger so as to take full advantage of the General Electric LM2500 gas turbines.

The Austal ship has also experienced corrosion problems.

Both designs need more cathodic protection, he says.  The Navy and the builders are installing both additional sacrificial anodes known as zincs and an impressed current system,

“An Impressed Current Cathodic Protection System (ICCP) will be installed in both the cone assemblies and the water jet tunnels on Austal variant ships to reduce the effects of galvanic corrosion,” says Naval Sea Systems Command spokesman Chris Johnson.  “The General Dynamics and Austal USA approach to prevent corrosion on LCS 2 was based on commercial practices and included a coating system on the exposed metal, electrical insulation of dissimilar metals and cathodic protection via sacrificial zinc anodes in the water jet tunnels.  This design proved to be less effective than intended due to multiple factors including improper electrical insulation during installation.  To provide more comprehensive protection, an ICCP system and additional sacrificial protection design is being finalized and will be implemented on LCS 2 during its Post Shakedown Availability (PSA); has already been installed on LCS 4; and will be included on LCS 6 and follow as a baseline change prior to the start of construction.”

With the changes, Murdoch says both production lines should now be quite stable.  The key to keeping costs down, he says, is avoiding changes.  “We don’t introduce any changes we don’t absolutely have to,” he says.

(As published in the November 2011 edition of Maritime Reporter & Engineering News - www.marinelink.com)

Maritime Reporter August 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

New e-Navigation Technologies from Transas

Transas Marine introduced new software solutions for voyage planning and fleet management at SMM 2014 as a step towards becoming the forerunner in the development of e-Navigation technologies.

iSURVEY Awarded Two-year Contract with Island Offshore

iSURVEY has been awarded a two-year contract with offshore vessel owner, Island Offshore Management, which will see iSURVEY AS provide positioning services to Island

SBM Offshore Announces Thunder Hawk Tiebacks

SBM Offshore is pleased to announce it has signed a Production Handling Agreement (PHA) with Noble Energy to produce the Big Bend and Dantzler fields to the

Shipbuilding

Hyundai Mipo Dockyard Delivers Fourth PSV

Hyundai Mipo Dockyard (HMD) delivered the fourth high value platform supply vessel (PSV) for BP Shipping at its main shipyard in Ulsan, South Korea. HMD won

First-of-type Walk-to-Work Crewboat Launched

Incat Crowther announced the launch and sea trials of Muslim Magomayev, a first-of-type 70m Catamaran Fast Crew Boat (FCB). Constructed by Incat Tasmania, Muslim

Scorpio Tankers Receive 7 More Newbuildings

Scorpio Tankers Inc. say it has recently taken delivery of seven newbuilding vessels as follows: STI Madison and STI Park, LR2 product tankers, were delivered

Navy

Bulgarian Naval Academy Installs VSTEP Simulators

The Nikola Vaptsarov Naval Academy in Varna purchased a 360° Class A Full Mission Bridge simulator and an Incident Management Simulator for training of its Naval and Merchant marine students.

Simmons Assumes Command of USS James E. Williams

Capt. Anthony L. Simmons relieved Cmdr. Curtis B. Calloway as commanding officer of the guided-missile destroyer USS James E. Williams (DDG 95) at sea on Sept.

LHA 6 'America' Maiden Voyage Completes at San Diego

The Navy informs that the soon to-be-commissioned amphibious assault ship 'USS America' (LHA 6) arrived at its homeport of San Diego after completing its two-month

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Naval Architecture Pipelines Port Authority Ship Repair Ship Simulators Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2966 sec (3 req/sec)