Underwater Bow Thruster Reinstallation In Tacoma

Marinelink.com
Thursday, July 18, 2013

Three months after Hydrex diver/technicians removed the bow thruster of a 294-meter container vessel in Tacoma, a Hydrex team once again mobilized to this location to reinstall the overhauled unit underwater with the use of the Hydrex flexible mobdock.


The superintendent of the ship was very satisfied with the first part of the operation. The job was completed well within the available time frame thanks to good team work of the Hydrex divers, the ship staff and the floating crane operator.

 

For this reason the customer asked Hydrex to take care of the reinstallation as well, which was carried out last month.


Together with all the necessary equipment, the team mobilized from the Hydrex office in Clearwater, Florida to the vessel’s location. After they set up a monitoring station on a workboat, the team positioned the bow thruster onto a cradle.

 

This cradle was designed especially for thruster operations. It can be adjusted to the size of the unit. In this manner the thruster is prevented from tipping over, making it much easier to handle. The Hydrex divers could lower the unit into the water and maneuver it inside the thruster tunnel in one take. The team positioned the bow thruster and secured the unit.


The team then used the lightweight flexible mobdocks developed by Hydrex to close off the thruster tunnel on both sides. This allowed the diver/technicians to evacuate all the water from the tunnel and create a dry working environment around the bow thruster. The thruster propeller blades were then reinstalled one by one. The team completed the operation by reconnecting the thruster unit to the engine room.


Hydrex can assist shipowners with almost any problem they encounter with their vessel’s thruster. A wide range of repair or maintenance work can be carried out to all types of thrusters. An entire unit can be overhauled, propeller blades or seals can be replaced or repair work on a specific part of a thruster can be performed by Hydrex diver/technicians on site. All of these repairs can be carried out without the need to drydock the vessel.


Off-hire time causes a substantial loss of money. The teams therefore worked in shifts during both the removal en reinstallation of the bow thruster. This was done to perform the bow thruster operations within the shortest possible time frame, saving the owner the time and money which going to drydock would have entailed.
 

Maritime Reporter February 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Marine Propulsion

Rolls-Royce to Power Zhuhai Ferries

Rolls-Royce has been selected to supply waterjets and high speed MTU diesel engines to power two new aluminium catamaran fast ferries for Chinese ferry operator

Propulsion Systems Ordered for Qatar Coastguard Vessels

Rolls-Royce waterjets and MTU diesels to power 17 new patrol boats for the Qatar Coastguard   Rolls-Royce has secured a £15.8 million contract to supply Rolls-Royce

Gladding-Hearn Bags Hy-Line Cruises Catamaran Order

Hy-Line Cruises, a division of Hyannis Harbor Tours, Inc., Hyannis, Mass., has ordered a new 493-passenger, high-speed catamaran from Gladding-Hearn Shipbuilding, the Duclos Corporation.

Ship Repair & Conversion

Electronics Retrofit for Taiwanese Research Vessel

L-3 SAM Electronics has been awarded a contract to retrofit propulsion control and automation systems aboard the Taiwanese Navy’s Ta Kuan hydrographic and oceanographic research vessel.

Tall Ship in Wet Dock for Repairs

The largest brig to be built in the U.K. in a century sailed into in a Greenock dry dock yesterday for general maintenance and essential winter repairs.   The

Europe Should Resume Shipbuilding

In the EU journal Parliament, Portuguese Member of European Parliament João Ferreira has proposed a five-point plan to stimulate growth in the EU shipbuilding industry.

Container Ships

Maersk Line CEO: 11 New Ships Likely in Q2 2015

Maersk is considering ordering 11 container megaships in the second quarter of 2015, the Wall Street Journal reported today. "We need to grow with the market and increase our capacity by 425,

Port of LA Container Volumes Down 22.7% in January

Port of Los Angeles container volumes decreased by 22.7 percent in January compared to January 2014 volumes, the port announced today. The port's January 2015 cargo volumes totaled 529,

Containership Becomes Largest to Sail the Thames

The Munkebo Maersk became the largest ship to ever sail up the River Thames as it called at DP World London Gateway, the U.K.’s newest deep-sea port hub. The 399-meter-long,

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Naval Architecture Offshore Oil Pipelines Salvage Ship Electronics Ship Repair Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.3856 sec (3 req/sec)