Slow-Steaming Through a Legal & Insurance Minefield

MarineLink.com
Friday, December 13, 2013
Image courtesy of UK P&I Club

The UK P&I Club’s publication ‘Hellas Hilights - Issue 28’ recorded Rod Lingard's attendance at the green4Sea Forum and his address on 'The Legal and Insurance Aspects of Slow-Steaming, excerpted as follows:

What’s the problem?
On one side the owner has an obligation to follow the charterer’s slow-steaming instructions under the charterparty yet on the other the owner has the usually implied obligation under the Bill of Lading to proceed with due dispatch. Due dispatch means the most direct route at the fastest speed. There is legal authority that an unreasonable delay is a deviation. A deviation in this respect is a departure from the contractually agreed voyage that deprives the carrier of the defences and rights of limitation that are usually available under The Hague or Hague Visby Rules.

Implications for cover
As many Members will be aware a [voyage] deviation has implications for P&I cover. There are also other insurance implications. Slow- steaming brings issues of, increased inspection, extra maintenance and crew training. It is possible that there may be problems with an insurance claim where there is an engine breakdown and there has been a history of slow-steaming. Depending on the policy wording then the hull underwriters may look at issues of deliberate or negligent mismanagement.

Similarly, in General Average, maintenance and training will come under close scrutiny as cargo look to avoid contributing their proportion of General Average by trying to show that the carrier has failed to exercise due diligence to make the ship seaworthy before and at the commencement of the voyage.

There is little case law in connection with slow- steaming
For example, in  the PEARL C the owners chartered the ship on an amended NYPE form for 9-12 months. The charter-party contained a performance warranty that the ship was capable of steaming at about 13 knots in good weather conditions. It was common ground between the parties that the warranty only applied on delivery. The charterparty incorporated the Hague Rules and a London arbitration and English Law clause.

The charterers withheld hire alleging that there had been a breach of the utmost dispatch obligation under clause 8 and that the charterers could deduct lost time due to slow-steaming under the first part of clause 15.

The matter went to arbitration and the tribunal held that in respect of 3 out of 16 voyages there had been deliberate slow-steaming as that was the only reasonable explanation. The tribunal went on to find that there had been a breach of clause 8 and a net loss of time under clause 15.

The owners appealed arguing (1) that the tribunal had been in error by converting the performance warranty into a continuing warranty and (2) the Article IV Rule 2(a) Hague Rules Defence, “Error by the master in the navigation or management of the ship”, was available to them.

The matter went to the High Court and Popplewell J. held that there had been no error by the tribunal. The judge confirmed that it was appropriate to use the warranted speed as the benchmark against which to assess if the ship had proceeded with the utmost dispatch and in the case of a deliberate decision to slow-steam the error in the management of the ship defence was not available to the owners.

The full article is available at: http://www.ukpandi.com/knowledge/article/hellas-hilights-issue-28-129625/?dm_i=33T,21PCJ,CJJYUG,7DK6A,1






 

Maritime Today


The Maritime Industry's original and most viewed E-News Service

Maritime Reporter June 2016 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Contracts

Norsafe Secures Contract with VARD Group

Norsafe informs it has signed a new contract with VARD Group, and will supply lifeboats complete with davit systems to a series of 15 new vessels.    Topaz Energy

IOMAXIS Awarded $245 Mln Contract to Support NRL

Contract will allow IOMAXIS to provide research, development and technical support to initiatives at the Naval Research Lab   IOMAXIS, provider of technologies

Demand, Bunker Pricing Spurs Asia Dry Bulk-Capesize Rates

Owners asking $1 per tonne more on Australia-China rates; Panamax rates climb to two-month high, but remain under pressure. Freight rates for large capesize

Legal

Enclosed Space Safety Rule Enters into Force

A new regulation aimed at protecting seafarers who need to enter enclosed spaces, by requiring ships to carry portable atmosphere testing equipment on board, enters into force on July 1, 2016.

Beijing Slams South China Sea Court Proceedings

Permanent Court of Arbitration ruling set for July 12. An international court said it would deliver a hotly anticipated ruling in the Philippines' case against

SOLAS Container Mass Verification Rule Enter into force

A new regulation requiring the gross mass of a container to be verified before it is loaded onto a ship enters into force today (1 July 2016). It will assist in

Insurance

MAST, AMSA Partner for Risk Management Services

Maritime security company Maritime Asset Security Training (MAST) has announced their partnership with Astbury Marine Services & Associates (AMSA), a specialist

UK P&I and Britannia Clubs Call off Merger Talks

The boards of the UK P&I and Britannia Clubs since February 2016 have been in discussion regarding a potential merger between the two clubs.     While a number

Tanker Contamination Claims

One of the most common areas of bulk oil cargo claims is cargo contamination which occurs during the transfer of bulk liquid cargoes, says  Captain Paul D. Hall,

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Naval Architecture Offshore Oil Pod Propulsion Port Authority Ship Repair Ship Simulators Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1059 sec (9 req/sec)