Latest Transit Update: Upper Mississippi Pinnacle Rock

MarineLink.com
Sunday, February 09, 2014
Upper Mississippi rock removal: Image courtesy of Big River Coalition

The Big River Coalition inform that the following transits restrictions have been established to allow traffic to pass during rock removal work operations at locations C-100 and C-101 (Thebes, IL). 

The restrictions may be changed based upon conditions, including weather and experience with vessels passing while the rock removal operations are being conducted.  The original request for these locations called for full channel closures and these new transit restrictions resulted from passing a test tow through this reach of the Upper Mississippi River (UMR).
 
The Coast Guard revised the information for the Regulated Navigation Area from Mile 0.0 UMR to Mile 109.9 UMR in order to promote safe vessel transits around this project.  The transit restrictions are scheduled from 0630 hours to 1830 hours, Monday through Saturday, unless the contractor is not on scene.

The following is reproduced from the Broadcast Notice to Mariners:
"The Coast Guard has established a regulated navigation area from mile 0.0 to mile 109.9 umr for contracted subsurface rock removal operations. vessels with AIS must have AIS turned on and transmitting. Vessels transiting between miles 45 and 46 between 6:30 a.m. CST and 6:30 p.m. CST daily will be permitted to transit with the following restrictions:

DOWNBOUND VESSELS TRANSITING ARE RESTRICTED TO 9 TOTAL BARGES IN A 3X3
TOW CONFIGURATION OR A MAXIMUM TOW LENGTH OF 600 AND WIDTH OF 108 FEET.
UPBOUND VESSELS TRANSITTING ARE RESTRICTED TO 24 TOTAL BARGES IN A 4x6
TOW CONFIGURATION OR A MAXIMUM TOW LENGTH OF 1200 AND A WIDTH OF 140 FEET.
VESSELS MEETING THESE SIZE RESTRICTIONS MUST CONTACT THE VESSEL KEITH
JACOBSON ON VHF-FM CHANNEL 16 TO ARRANGE PASSAGE DURING WORK HOURS, AND
TRANSIT AT SLOWEST SAFE SPEED. IF YOUR TOW EXCEEDS THESE RESTRICTIONS IT
WILL NOT BE PERMITTED TO TRANSIT DURING WORK HOURS.
 
WHEN STOPPING TO AWAIT PASSAGE THROUGH THEBES, CONTACT THE SECTOR OHIO
VALLEY COMMAND CENTER AT 502-779-5424 OR 502-779-5449 TO BE PLACED IN
QUEUE. THE COAST GUARD WILL CONTACT VESSELS IN THE QUEUE TO FACILITATE
PASSAGE THROUGH THE THEBES AREA WHEN THE RIVER REOPENS TO ALL TRAFFIC.”
 
The Big River Coalition also inform that The Corps’ St. Louis District reports that the contractor has made only minimal progress this week due to an equipment breakdown and weather challenges.  The surveys indicate that about 15% of the material has been removed (or freed) at both C-100 and C-101.  The latest update indicates that overall 640 cubic yards (cy) of rock material of the 1,527 cy of the Phase 2 base contract or 42% has now been completed.  

Source: The Big River Alliance
 

 

Maritime Reporter March 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Golden Ocean and Knightsbridge Complete Merger

The merger between Knightsbridge Shipping Limited and Golden Ocean Group Limited was approved today at special meetings of both companies' shareholders.      The new company,

Panama Canal Sets Sight on Another Expansion

As it enters the final stretch of a massive expansion, the Panama Canal Authority is setting its sights on an even more ambitious project worth up to $17 billion

Long Beach, LA Collaborate to Improve Cargo Flow

Executives from the ports of Long Beach and Los Angeles held a kickoff meeting earlier this week to begin working together to focus on cargo conveyance strategies

Navigation

US Will Work to Ensure Bab-el-Mandeb Strait Remains Open

The U.S. military will work with Gulf and European partners to ensure the strategic Bab el-Mandeb Strait at the tip of the Red Sea remains open to commerce despite fighting and instability in Yemen,

BMT’s REMBRANDT-INLAND Simulation Tool

Brown Water Training and Collision Reconstruction Taken to a New Level When a new or expanded port is planned on an inland waterway, how do you assure the civil

Using AIS Data to Assess Collision Risks

Automatic Identification System (AIS) data is now being used to determine the collision risk for offshore installations. MARIN helps oil companies with risk assessments

Dredging

Sen. Paul Proposes New Harbor Dredging Criteria

Sen. Rand Paul (R-KY) reintroduced the Harbor Equity Act on Monday, his office announced. This legislation modifies the existing criteria used by the U.S. Army

Fugro Clarifies: Being an Independent Service Provider

Fugro has taken notice of the press release from Boskalis of Friday evening, 20 March 2015, that it has increased its holding in Fugro N.V. to 25.1%. The further stake building by Boskalis,

Sri Lanka Okays Construction on Stalled Chinese Port Project

Sri Lankan government has approved the construction of a breakwater for a Chinese funded Colombo port city project which had been suspended by the government earlier this month.

News

Greek Ferry Runs Aground in the Aegean

A Greek ferry ran aground on the Aegean island of Kassos overnight, the AP is reporting.      None of the 227 passengers and 55 crew were injured and a tug

Golden Ocean and Knightsbridge Complete Merger

The merger between Knightsbridge Shipping Limited and Golden Ocean Group Limited was approved today at special meetings of both companies' shareholders.      The new company,

SAL Heavy Lift Performs Offshore Windfarm Work

MV Lone proves as project platform for Wikinger wind farm   SAL Heavy Lift informs it has completed the second phase of the Wikinger Pile Testing Campaign with DP II Class vessel MV Lone.

Maritime Safety

Greek Ferry Runs Aground in the Aegean

A Greek ferry ran aground on the Aegean island of Kassos overnight, the AP is reporting.      None of the 227 passengers and 55 crew were injured and a tug

US Will Work to Ensure Bab-el-Mandeb Strait Remains Open

The U.S. military will work with Gulf and European partners to ensure the strategic Bab el-Mandeb Strait at the tip of the Red Sea remains open to commerce despite fighting and instability in Yemen,

BMT’s REMBRANDT-INLAND Simulation Tool

Brown Water Training and Collision Reconstruction Taken to a New Level When a new or expanded port is planned on an inland waterway, how do you assure the civil

Underwater Engineering

Submerged Politics in Aussie's $39 bln Submarine Plan

Australian government plans to spend 50 billion Australian dollars (US$39.39 billion) on powerful new submarines, has become a political football at home, reports Reuters.

Moskito to Recover Oil from Sunken Wrecks

A tool for removing oil in submerged vessels was developed in Norway by Miko Marine. Moskito is designed to address the pollution threat that exists with the

Bibby Offshore Secures Contract with MGTC

Bibby Offshore announced today that its Asian Division, Bibby Offshore Singapore (‘BOS’), has secured a contract with the Moattama Gas Transportation Company (“MGTC”).

 
 
Maritime Contracts Navigation Offshore Oil Pipelines Pod Propulsion Port Authority Ship Electronics Ship Repair Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2359 sec (4 req/sec)