Where is Floating Production Headed?

By Jim McCaul, IMA
Monday, January 20, 2014
Jim McCaul, IMA

The number of floating production units grew 5% in 2013. Here we examine the global market and future opportunities.

Currently, there are 319 oil/gas floating production units are now in service, on order or available for reuse on another field.  FPSOs account for 65% of the existing systems, 75% of systems on order. Another 24 floating LNG processing systems are in service or on order.  Liquefaction floaters account for 13%, regasification floaters 87%.  No liquefaction floaters are yet in service – all three are on order.
In addition, 100 floating storage units are in service, on order or available.

Growing Number of Floating Production Units
The number of floating production systems has grown at a strong pace over the past decade.  Aside from a tapering off in 2009/10, year to year growth has been in the range of 5-12% during this period. 
Ten years ago 203 oil/gas production floaters and no LNG processing units were in service or on order.  Five years ago there were 269 oil/gas units and 6 LNG processing units.  By the beginning of 2013 there were 306 oil/gas production floaters and 20 LNG processing floaters.  Now there are 319 and 24 units respectively.
Overall, the number of units grew 5% during the past year, 69% over the past decade.

 
Redeployment Prospects for Available FPSOs
Eighteen FPSOs have stopped producing and are available for redeployment.  The latest to join the inventory of idle FPSOs are Kuito and BrasiI, VLCC-size units owned by SBM.  The lease on each concluded at end 2013.  They are to be decommissioned. 
Some of the 18 available FPSOs are actively for sale.  Some are being retained for use on another field controlled by the current owner.  All require modification and upgrade to be reused.  Depending on the new field, the cost to modify the processing plant, mooring system and refurbish the unit can easily exceed $100 million. 
Ten of the available units are single hull, five are double hull and three have double sides or double bottom.  Single hull unit are less marketable than double hull units.
Details for available FPSOs can be found at www.imastudies.com.
Many of these available FPSOs (particularly single hull units) will not find another field.  This is behind the decision of SBM in December to write down the book value of the FPSO Falcon.  Explaining its decision to take a special charge of $55 million on Falcon (marketed since 2009) and Alba (a tanker acquired in 2009 as a conversion hull), SBM said the “estimated recoverable amount under current market conditions is considerably lower than the carrying value.”
To place the issue in perspective, 24 FPSOs have been redeployed over the past ten years – accounting for ~20% of the FPSO contracts during this time period.  Assuming this redeployment pace continues, more than 7 years will be needed to clear the inventory of FPSOs now looking for a field contract.  And this assumes a project match can be found for all units (which will not happen) and no further units come off field over the next several years (which will happen). 
Bottom line is there are far too many available FPSOs for the market to absorb. This situation should cause lenders to look very carefully at residual values in FPSO financings.  Anything more than scrap value may be optimistic, even for FPSOs built on new or young hulls.
 

Orders in 2013
Orders for 22 production floaters with a total contract value of ~$17 billion were placed in 2013.  The orders include 11 FPSOs, two TLPs, one Spar, one Barge, six FSRUs and one MOPU.  A 12th FPSO (Rosebank) was ordered but the contract was suspended pending review.
Details for orders in 2013 are available at www.imastudies.com.
The market seemed to hit resistance in 2013.  FPSO orders in particular were relatively weak.  Over the past ten years an average of 13.6 FPSOs have been ordered annually.  Only 11 FPSO contracts were placed in 2013. 
Resistance seems to be in the supply chain
Construction costs have been increasing, local content targets have been creating bottlenecks and access to financing has been constrained.  Oil company investment resources also have been shifting to shale oil and gas project development. 
We see supply chain resistance and competition for investment resources from shale oil/gas projects continuing over the near term.  Our new five year forecast of production floater orders reflects this – and our forecast of orders between 2014 and 2018 is down significantly as a result.

Backlog of Planned Floater Projects
234 floating production projects are in various stages of planning as of beginning January.  Of these, around 55% involve an FPSO, 15% another type oil/gas production floater, 25% liquefaction or regasification floater and 5% storage/offloading floater. 
This large backlog of projects in the planning cycle is further indication that project investment opportunity is not the cause of the recent lethargic order pace. 
There are plenty of floater projects at or near the final investment decision stage.  The decision to move to the contracting stage has been slowed by supply chain resistance and better uses of investment resources.

Where Planned Projects are Located

Brazil and Africa are the major locations of floating production projects in the visible planning stage.  We are tracking 50 projects in each region – 43% of the visible planned floating production projects worldwide.
Brazil clearly leads in terms of production floater requirements – as several Brazilian projects will require multiple production units.  Libra could require 12 production units, Jupiter six units, Lula two-plus units. 
When these large projects are taken into account, Brazil represents almost 30% of visible floating production system orders in the planning stage.
 


The Author
IMA provides market analysis and strategic planning advice in the marine and offshore sectors. Over 40 years we have performed more than 350 business consulting assignments for 170+ clients in 40+ countries. We have assisted numerous shipbuilders, ship repair yards and manufacturers in forming a a plan of action to penetrate the offshore market.  Our assignments have included advice on acquiring an FPSO contractor, forming an alliance to bid for large FPSO contracts, satisfying local content requirements and targeting unmet requirements through technology development.
Tel: 1 202 333 8501
e: imaassoc@msn.com
www.imastudies.com

(As published in the January 2014 edition of Maritime Reporter & Engineering News - www.marinelink.com)

Maritime Reporter October 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

Time-out for Kwanza Drilling

Statoil has decided to cancel the Stena Carron rig contract after fulfilling the work commitments in the Statoil-operated blocks 38 and 39 in the Kwanza basin offshore Angola.

Maritime Reporter @ 75: The Daily Cartoon

Maritime Reporter & Engineering News was founded by John J. O'Malley (1905-1980) in 1939, and today ranks as the world's largest audited trade publication in the world serving the maritime industry,

Video: Reefer RoRo Ship Design Rebooted

Expanding on the Reefer RoRo Ship design release in September last year, naval architects group Knud E. Hansen A/S has continued the development of the new Reefer RoRo Ship design with version II.

Shipbuilding

Steven Palazzo Visits HII, Newport

Huntington Ingalls Industries today hosted Rep. Steven Palazzo, R-Miss., for a tour of the company's Newport News Shipbuilding division. Palazzo represents the fourth district of Mississippi,

Everett College to Launch New Research Boat

Everett Community College’s Ocean Research College Academy (ORCA) will launch its new research vesel on November 22 with a celebration at 11 a.m. at the Port of Everett.

Video: Reefer RoRo Ship Design Rebooted

Expanding on the Reefer RoRo Ship design release in September last year, naval architects group Knud E. Hansen A/S has continued the development of the new Reefer RoRo Ship design with version II.

Ship Repair & Conversion

Seaspan Shipyard's Prompt Response to Canadian Coast Guard

Seaspan Shipyard’s long-standing relationship with the Canadian Coast Guard was proudly showcased in recent days, with simultaneous repair and maintenance work

Energy Storage System Ordered for LNG Battery Hybrid Ferry

Norwegian hybrid to be the first LNG battery ferry to operate on commercial routes Corvus Energy, Siemens AS and Fjord1 have announced the award of the contract for the Fannefjord LNG hybrid ferry.

N-KOM Recognized for Shipyard Safety, Security

Nakilat-Keppel Offshore & Marine (N-KOM) received the Safety & Security Award at the inaugural edition of The Maritime Standard (TMS) Middle East & Indian Subcontinent Awards,

LNG

HHI to Build FSRU for Höegh LNG

A new Floating Storage and Regasification Unit (FSRU) will be built by the Korean shipbuilding Company Hyundai Heavy Industries (HHI). This FSRU will be the fifth

BG Group's Queensland Curtis LNG to Ship First Cargo

BG Group is set to ship the first cargo of liquefied natural gas from its flagship gas project Queensland Curtis LNG on Dec. 20, a source familiar with the matter told Reuters.

Europe Stockpiling Low Cost, Surplus LNG

Demand from top Asian buyers drops sharply; Asian, European gas price spreads converge. Europe set to becoming dumping ground for LNG. Europe is set to become

News

7 Rescued from Sinking Freighter Near Haiti

Seven crewmembers were rescued after their 100-foot coastal freighter began taking on water and sank approximately 45 miles north off of Cap Haitien, Haiti, Friday.

Gazprom Transgaz Ufa Organizes Arts Festival

Over 200 healthy children and children with disabilities from Bashkortostan as well as the Volga Region participated in the Breaking the Barriers second interregional children’s arts festival,

Time-out for Kwanza Drilling

Statoil has decided to cancel the Stena Carron rig contract after fulfilling the work commitments in the Statoil-operated blocks 38 and 39 in the Kwanza basin offshore Angola.

Offshore Energy

Time-out for Kwanza Drilling

Statoil has decided to cancel the Stena Carron rig contract after fulfilling the work commitments in the Statoil-operated blocks 38 and 39 in the Kwanza basin offshore Angola.

Update: Explosion in the Gulf of Mexico

An explosion occurred aboard a production platform Thursday at West Delta 105, operated by Fieldwood Energy, resulting in one fatality and three injured. The Bureau

Deepwater Semi-Sub COSL Prospector Delivered

COSLProspector, the fourth deep-water semi-submersible drilling rig built by CIMC Raffles for China Oilfield Services Limited (COSL), has been delivered in Yantai, Shandong Province.

 
 
Naval Architecture Offshore Oil Pipelines Pod Propulsion Port Authority Salvage Ship Repair Ship Simulators Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2069 sec (5 req/sec)