Navy Shipbuilding: U.S. GAO on Getting Things Right

MarineLink.com
Tuesday, November 19, 2013
LCS Sea Trial: Image courtesy of USN

A recent report US Government Audit Office (GAO) report, mandated by the House, discussed amongst other issues:  (1) quality problems in constructing recently delivered ships and Navy actions to improve quality and (2) key practices employed by leading commercial ship buyers and shipbuilders to ensure quality and how these compared with Navy practices. Excerpts from the report follow:

What GAO Found

The Navy has experienced significant quality problems with several ship classes over the past several years. It has focused on reducing the number of serious deficiencies at the time of delivery, and GAO's analysis shows that the number of deficiencies--particularly "starred" deficiencies designated as the most serious for operational or safety reasons--has generally dropped.

Nonetheless, the Navy continues to accept ships with large numbers of open deficiencies. Accepting ships with large numbers of uncorrected deficiencies is a standard practice and GAO found that there are varying interpretations of Navy policy with regard to when the defects should be resolved.

In 2009, the Navy organization that oversees ship construction launched the Back to Basics initiative to improve Navy oversight of ship construction. However, a key output of the initiative promoting consistent and adequate quality requirements in Navy contracts has yet to be implemented.

Although the environment in which leading commercial ship buyers and builders operate differs in many ways from the Navy's, some commercial practices aimed at helping to ensure that ships are delivered with a minimum number of deficiencies may be informative for the Navy.

Throughout the course of commercial shipbuilding projects, significant numbers of quality defects and instances of non-conforming work are identified. However, leading commercial ship buyers and shipbuilders make great efforts to ensure that these issues are resolved prior to delivery. Further, commercial ship buyers establish clear lines of accountability and hold their personnel responsible for ensuring the shipbuilder delivers a quality vessel.

While commercial ship buyers focus on regularly witnessing in-process work through roaming patrols and impromptu inspections, Navy processes at the shipyards place less emphasis on in-process work. Moreover, leading commercial shipbuilders have strong quality management processes that track quality problems to the worker or supervisor level. Navy shipbuilding contractors have historically experienced difficulties in holding production workers and supervisors accountable for their work, but some of the shipyards reported they are making progress on increasing worker accountability.

What GAO Recommends
To improve the construction quality of ships delivered to the Navy, GAO is recommending, among other things, that the Navy clarify policy on when deficiencies should be addressed, provide guidance on contract quality requirements, and assess applicability of certain commercial practices to Navy shipbuilding.

DOD agreed with two recommendations and partially agreed with three, stating for example that current policy is adequate but that the Navy would monitor deficiency trends. GAO believes that the recommendations remain valid as discussed in the report.

For more information, contact Michele Mackin at (202) 512-4841 or mackinm@gao.gov

Maritime Today


The Maritime Industry's original and most viewed E-News Service

Maritime Reporter May 2016 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

Denmark Adopts Digital Ship Certification

As of June 24, 2016, ships flying the Danish flag are being digitally certified, making Denmark one of the first countries to put an end to the 100-year-old tradition

Prince Charles Places Final Section of UK Aircraft Carrier

The second of the largest warships ever built for the U.K. Royal Navy, the Queen Elizabeth Class carrier HMS Prince of Wales, was given the royal seal of approval when HRH The Prince of Wales,

US Navy Accepts Delivery of Future USS Montgomery

The U.S. Navy has accepted delivery of future USS Montgomery (LCS 8) during a ceremony on June 23 at the Austal USA shipyard in Mobile, Ala.   Marking the official

Contracts

ABP orders Two Gottwald cranes

Terex Port Solutions (TPS) has received an order from Associated British Ports (ABP) for two electric Terex Gottwald Model 8 portal harbour cranes in the G HSK 8424 B four-rope grab variant.

POSH Bags Shell FLNG Contract

Singapore’s offshore marine services provider PACC Offshore Services Holdings Ltd. (POSH) has been awarded a contract to support Shell’s Prelude floating liquefied

Baltic Index up for Third Straight Session

The Baltic Exchange's main sea freight index, tracking rates for ships carrying dry bulk commodities, rose on Friday, for a third straight session, on rising demand across all vessel segments.

Shipbuilding

Austal Delivers LCS 8 to US Navy

Austal Limited (Austal) (ASX:ASB) delivered the future USS Montgomery (LCS 8) to the U.S. Navy, during a ceremony held aboard the ship at Austal USA’s shipyard in Mobile, Alabama, USA on 23 June.

Conrad Shipyard Forms LNG Business Unit

Conrad Shipyard has formed a new business unit focused on LNG projects.   Conrad, builder of North America’s first LNG bunker barge scheduled for 2017 delivery,

Prince Charles Places Final Section of UK Aircraft Carrier

The second of the largest warships ever built for the U.K. Royal Navy, the Queen Elizabeth Class carrier HMS Prince of Wales, was given the royal seal of approval when HRH The Prince of Wales,

Navy

Austal Delivers LCS 8 to US Navy

Austal Limited (Austal) (ASX:ASB) delivered the future USS Montgomery (LCS 8) to the U.S. Navy, during a ceremony held aboard the ship at Austal USA’s shipyard in Mobile, Alabama, USA on 23 June.

Prince Charles Places Final Section of UK Aircraft Carrier

The second of the largest warships ever built for the U.K. Royal Navy, the Queen Elizabeth Class carrier HMS Prince of Wales, was given the royal seal of approval when HRH The Prince of Wales,

US Navy Accepts Delivery of Future USS Montgomery

The U.S. Navy has accepted delivery of future USS Montgomery (LCS 8) during a ceremony on June 23 at the Austal USA shipyard in Mobile, Ala.   Marking the official

Government Update

Traffic Separation Schemes off Western Australia

On 1 December 2016 two new Traffic Separation Schemes (TSS) will come into effect off the south-west coast of Western Australia. Australia’s proposal to establish

Austal Delivers LCS 8 to US Navy

Austal Limited (Austal) (ASX:ASB) delivered the future USS Montgomery (LCS 8) to the U.S. Navy, during a ceremony held aboard the ship at Austal USA’s shipyard in Mobile, Alabama, USA on 23 June.

Berthing Policy for Dry Bulk Cargo for Indian Ports Unveiled

Ministry of Shipping has formulated a new Berthing Policy for Dry Bulk Cargo for all Major Ports which will come into effect from 20th August, 2016. The objective

 
 
Maritime Contracts Maritime Security Maritime Standards Naval Architecture Pipelines Port Authority Salvage Ship Electronics Ship Simulators Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1215 sec (8 req/sec)