Advances in Bollard Pull Testing Technology

By Joseph Keefe
Thursday, March 21, 2013
MTNW Tension Link

Many arguments about the capabilities of a tug can be quickly settled when you can conduct a full-ahead power, bollard pull test. “Many captains will argue about horsepower, hull design, rudder angles, and other variables, but the only thing that really matters is bollard pull and a test provides empirical data of pure power,” says Mark Babcock, VP of Machinery for Sause Brothers’ 200 tugs, barges and OSVs. “A well maintained vessel shouldn’t lose bollard pull over time, but with every propulsion related change, engine overhaul, shaft or propeller retrofit, the vessel should be re-tested.”
While the bollard pull test has been around for many decades, recent changes in technique, technology and data-logging allow engineering and operations to fine tune the analysis and provide more accurate information. Providing accurate reports allows pilots, agents and customers to have confidence in towing and tug capabilities at the edge of the performance envelope. While many new tugs are built larger and more powerful than ever before, most of the tugs on rivers and ports have years on their engines and the ability to move their tow when it ultimately matters, should be tested against expectations.

What is Bollard Pull?
Bollard pull is the static force exerted by a tug at zero speed on a fixed line. Almost always, a test involves affixing a line to a shore-based bollard and ramping the RPM’s of the engine to full- throttle, typically in ahead and astern conditions. The vessel is then held at full RPM’s for between 1 and 10 minutes.  Some versions of this test are completed quickly and some, like in Brazil, last for over an hour.

Test Variables
Many variables can influence a bollard pull test reading, including water depth, prop wash, wind, tidal forces or currents, rudder angle, and stretch of the tow line. Finding an ideal site is difficult, so external forces must be figured into the final analysis. Beyond this, A bollard pull test requires a tension sensor which is put in series with the tow line, a local display of the line tension and a process to record that data. Often, an engineer will be present in the engine room to evaluate engine RPM’s and another engineer will stand on the back deck to track the forces on the load cell by noting them on a display and manually tracking the figures by hand. This process can be challenging and inaccurate in rough weather and in river conditions which change quickly. In river situations, the tug may start upriver of the shore-based bollard, bring the tug up to full power and when the vessel is perpendicular to the shore, the engineer must quickly capture the data from the tension sensor.  This short window for readings can make it challenging to capture accurate data.

Advances in Technology
Measurement Technology NW of Seattle has developed a PC-based software solution that allows data capture up to 100 times per second (Hz). The software time-stamps the incoming data so that it is easy to match up with other data in post-event analysis; automating and simplifying data correlation. Recently, MTNW supported Glosten Associates’ work with a tugboat bollard pull test intended to verify the bollard pull of a number of tugs. “The MTNW tension monitoring system and engineer provided the tension data that we required to perform our analysis,” said Ken Lane, Director of Production Services at Glosten. “The MTNW system captured the line tension data with an accurate time stamp which allowed us to easily synchronize the tension sensor data with other important measurements.”
MTNW’s tension monitoring systems include a certified tension link, rugged water proof local display and a laptop PC with data-logging software. The system is plug-and-play for quick set up which allows for more time testing and lower fuel costs. The engineer can now watch the tension locally, but also know that the data-logging software is catching every tension spike for post-test analysis.  “MTNW equipment can accommodate tests as simple as full ahead or astern to more complicated tests which seek to correlate line tension to engine RPMs and other variables. The WinchDAC software prints easy-to-read PDFs of each test.
MTNW’s equipment is available for bollard pull testing and certification for tugboats and can be used as a rental device so that more naval architects, tugboat operations managers, and engineers can perform these services on their own. MTNW’s equipment is certified regularly and MTNW will work with certifying witnesses from DNV, ABS, Lloyds, Bureau Veritas and any other required certifying body.

(As published in the March 2013 edition of Marine News - www.marinelink.com)

 

Maritime Reporter April 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

Goliat FPSO in Norway

The Goliat FPSO was successfully floated off the heavy-lift vessel, Dockwise Vanguard, in the fjord outside Hammerfest, says Eni Norge    The Goliat platform has arrived in Hammerfest,

OSV Technology: Notable Designs & Deliveries

Though the market for Offshore Support Vessels (OSVs) is soft, advances in technology, fit and finish in  the sector is unrivaled in any other maritime niche over the past five years.

Gondan Lays Keef for IMR Oceanographic Vessel

Gondan Shipyard has celebrated at its facilities in Figueras the keel laying ceremony of the new Oceanographic Research Vessel for the Institute of Marine Research (IMR) of Bergen, Norway.

Workboats

Apply Now for the MN 100

The August 2015 edition of Marine News, the leading voice in the North American workboat market, will feature 100 leaders and innovators, including workboat owners and operators,

Boatbuilding in China

While much of the focus on coverage of the Chinese shipbuilding industry is on big shipbuilding, Maritime Reporter switches gears this month to explore activities in select boatbuilding sectors.

Ingram Barge’s Sehrt Elected AWO Chairman

The members of the American Waterways Operators (AWO), the national trade association representing the tugboat, towboat and barge industry, elected a new slate

Marine Materials

HMS Prince of Wales Bridge Sets Sail

The bridge section of the second Queen Elizabeth Class aircraft carrier set sail today from Glasgow on its first sea voyage to Rosyth.   Upper Block 07 is where

Rotork Acquires Masso

Rotork announced it has acquired Masso Ind s.p.a., a manufacturer of shipboard valve remote control systems (VRCS), to enhance its range of flow control products

Naust Marine Wins Huge Winch Order

58 electric winches for two new fishing trawlers   Hradfrystihusid Gunnvor (HG) and Vinnslustodin (VSV) recently awarded Naust Marine contracts to provide a complete

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Naval Architecture Navigation Port Authority Ship Electronics Ship Simulators Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2722 sec (4 req/sec)