Advances in Bollard Pull Testing Technology

By Joseph Keefe
Thursday, March 21, 2013
MTNW Tension Link

Many arguments about the capabilities of a tug can be quickly settled when you can conduct a full-ahead power, bollard pull test. “Many captains will argue about horsepower, hull design, rudder angles, and other variables, but the only thing that really matters is bollard pull and a test provides empirical data of pure power,” says Mark Babcock, VP of Machinery for Sause Brothers’ 200 tugs, barges and OSVs. “A well maintained vessel shouldn’t lose bollard pull over time, but with every propulsion related change, engine overhaul, shaft or propeller retrofit, the vessel should be re-tested.”
While the bollard pull test has been around for many decades, recent changes in technique, technology and data-logging allow engineering and operations to fine tune the analysis and provide more accurate information. Providing accurate reports allows pilots, agents and customers to have confidence in towing and tug capabilities at the edge of the performance envelope. While many new tugs are built larger and more powerful than ever before, most of the tugs on rivers and ports have years on their engines and the ability to move their tow when it ultimately matters, should be tested against expectations.

What is Bollard Pull?
Bollard pull is the static force exerted by a tug at zero speed on a fixed line. Almost always, a test involves affixing a line to a shore-based bollard and ramping the RPM’s of the engine to full- throttle, typically in ahead and astern conditions. The vessel is then held at full RPM’s for between 1 and 10 minutes.  Some versions of this test are completed quickly and some, like in Brazil, last for over an hour.

Test Variables
Many variables can influence a bollard pull test reading, including water depth, prop wash, wind, tidal forces or currents, rudder angle, and stretch of the tow line. Finding an ideal site is difficult, so external forces must be figured into the final analysis. Beyond this, A bollard pull test requires a tension sensor which is put in series with the tow line, a local display of the line tension and a process to record that data. Often, an engineer will be present in the engine room to evaluate engine RPM’s and another engineer will stand on the back deck to track the forces on the load cell by noting them on a display and manually tracking the figures by hand. This process can be challenging and inaccurate in rough weather and in river conditions which change quickly. In river situations, the tug may start upriver of the shore-based bollard, bring the tug up to full power and when the vessel is perpendicular to the shore, the engineer must quickly capture the data from the tension sensor.  This short window for readings can make it challenging to capture accurate data.

Advances in Technology
Measurement Technology NW of Seattle has developed a PC-based software solution that allows data capture up to 100 times per second (Hz). The software time-stamps the incoming data so that it is easy to match up with other data in post-event analysis; automating and simplifying data correlation. Recently, MTNW supported Glosten Associates’ work with a tugboat bollard pull test intended to verify the bollard pull of a number of tugs. “The MTNW tension monitoring system and engineer provided the tension data that we required to perform our analysis,” said Ken Lane, Director of Production Services at Glosten. “The MTNW system captured the line tension data with an accurate time stamp which allowed us to easily synchronize the tension sensor data with other important measurements.”
MTNW’s tension monitoring systems include a certified tension link, rugged water proof local display and a laptop PC with data-logging software. The system is plug-and-play for quick set up which allows for more time testing and lower fuel costs. The engineer can now watch the tension locally, but also know that the data-logging software is catching every tension spike for post-test analysis.  “MTNW equipment can accommodate tests as simple as full ahead or astern to more complicated tests which seek to correlate line tension to engine RPMs and other variables. The WinchDAC software prints easy-to-read PDFs of each test.
MTNW’s equipment is available for bollard pull testing and certification for tugboats and can be used as a rental device so that more naval architects, tugboat operations managers, and engineers can perform these services on their own. MTNW’s equipment is certified regularly and MTNW will work with certifying witnesses from DNV, ABS, Lloyds, Bureau Veritas and any other required certifying body.

(As published in the March 2013 edition of Marine News - www.marinelink.com)

 

Maritime Reporter January 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

'World's First Hybrid Superyacht'

Developed by Dutch shipbuilders Feadship, the 83.5m Savannah is touted as the world's first hybrid super yacht. Vessel is 30% more fuel efficient than similar sized counterparts, claims the company.

Kongsberg Expands Louisiana Office, Training Facility

Kongsberg Maritime has purchased approximately 5.2 acres for new construction on an 82,980 sq ft office and training facility. Construction on the James Business

Navigational Charts App Debuts at Ocean Business

An independent consultancy and software development company will launch a new web and PC based navigational charting app at Ocean Business 2015.   Norcom Technology

Workboats

New Survey Vessel Ordered for the Port of London

The Port of London Authority (PLA) has ordered a new purpose-built survey catamaran, a CTruk MPC19, due to enter service on the river Thames later this year.   The

Marquette Transportation Reportedly for Sale

Marquette Transportation Company LLC, a U.S. towboat operator, is exploring a sale that could value it at more than $1 billion and has attracted the interest of

Kirby Reports Record Earnings

Kirby Corporation announced record net earnings of $68.1 million, or $1.19 per share, for the fourth quarter 2014 (ended December 31). The results bested 2013’s fourth quarter figures of $64.

Marine Materials

Imabari to Construct Newbuilding Dry Dock

In order to accommodate construction of Ultra-Large newbuilding vessels including recently secured 20,000TEU Mega container ships (about 400m in length and about 59m breadth),

31 ARENA Projects Completed

ARENA has invested $1 billion in more than 230 projects, fellowships and scholarships that are paving the way for a more diverse energy future for Australia.

Safeguarding Maritime Power Connections

KIRK interlocking products provide safe electrical access during cold ironing, ensuring that ship power cables are properly coupled to shore power junction boxes before energizing.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Naval Architecture Pipelines Salvage Ship Electronics Ship Repair Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2829 sec (4 req/sec)