Marine Link
Sunday, December 15, 2024

Concrete 'Foundation' Reaches Aberdeen

Maritime Activity Reports, Inc.

February 27, 2019

As the first 6,000 tonne concrete “foundation” for Aberdeen Harbor’s $466m expansion has arrived from Cromarty Firth, the harbor expansion project has reached a new landmark stage.

The 50m long, 15m wide and 16m deep caisson is the first of 22 that will form the foundations for Castlegate and Dunnottar Quays, which will be 540m and 400m long respectively.  

In order to transport the caisson safely, it will travel the 180-nautical mile journey at two nautical miles per hour, escorted by ‘The Strathdee’ towage vessel.

Once the caisson has safely arrived in South Harbor, GPS equipment will be used to position it into its designated location with an accuracy of +/- 20mm.  It will then be filled with water to sink it to the sea bed.  When in place, various fill material will be used to displace the water.  The process from arrival to sinking takes approximately 30 hours.

A total of 22 caissons will form the foundations of Castlegate and Dunnottar Quays, which will be 540 and 400 meters long respectively.

Keith Young, Engineering Director at Aberdeen Harbor Board, said: “The arrival of the first caisson in South Harbor will be significant milestone in the expansion project, and a logistical achievement for us all.  I would like to congratulate and thank everyone who has been involved in the design, manufacture, transport and positioning of these caissons.

“Aberdeen South Harbor is of vital significance for our region and the rest of the country, and we look forward to the remaining caissons arriving as the project progresses.”

The caissons have been manufactured in La Coruna in North-west Spain and travel more than 1,000 miles by sea to the Cromarty Firth for quality checks and inspections.  They are then individually towed to Aberdeen, when required, as construction of South Harbor continues.

In accordance with maritime tradition, each caisson is named after a family member of someone closely involved with the expansion project.  The first caisson to arrive will be named ‘Caisson Brenda’ – named after the Aberdeen Harbor Board’s Chief Executive’s mother.

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week