Marine Link
Thursday, March 28, 2024

Shipyards in NE England Buzzing with Activity

Maritime Activity Reports, Inc.

February 26, 2013

The month of January 2013 was again a very busy month for A&P Shipyards in the northeast of England.

On the River Tyne there have been a number of dockings / undocking’s:

  • Longstone (Andrew Weir Shipping) - undocked early January after      an intensive 12 day programme overhauling the stern ramp, vent fans and      sea valves. The ship sailed away on time on 4th January.
  • Pride of York (P&O) - docked on 22nd January where she underwent her annual refit. She sailed on      the 10th February.

The Tyne saw a couple of demobilisation projects for Technip Offshore Wind Limited in January on UR101 and AMT Discoverer. Both projects involved removal of cable carousels and associated equipment. They both successfully completed on time. The same owners have now just stemmed another mobilisation on the Normand Progress. This is an intense 17 day programme which will commence on 8th March. There is a lot of pre-fabrication work to do before the vessel arrives’, which is currently underway. There is also an “A” Frame to put together, again before the vessel arrives. This is also in progress now.

Also stemmed is the MV European Seaway for P&O Ferries. The ship is due on the 17th February for 10 days.
The Tyne also mobilised the Polar Prince for Reef Subsea. This was a major upgrade to the deck system, which included the removal of its “A” Frame where it was extended by 2 metres and then re-installed. Again, another very successful project delivered on time.

In the company's River Tyne fabrification facility there are a number of contracts progressing. The down pipes for the Guala Lula project on behalf of Balltec is about 50% complete and on plan, the centre tower on behalf of Brastec is nearing completion.

At A&P's River Tees facility, January has seen a number of ships dry docked:

  • Union Pluto (Union Transport) - The vessel arrived on the 19th of January for extensive steel renewals to the Cargo Hold & Coaming linings approx. 40 tonnes of steel. During the contract additional steel renewals to Double Bottom tanks & Wing tanks frames. The vessel sailed on 1st Feb 2013.
  • Britannia Beaver (Britannia  Aggregates) - The vessel arrived and entered dry dock No5 on the 22nd December 2012 to undergo repairs to  dredge equipment & carryout steel repair to the hull.
  • Ocean Prince (Atlantic Offshore) – The vessel entered dry dock No5 on the 18th January, Repairs carried out to FiFi pumps, Aux Engines & Engine room Pipework. All work was completed within a 10 day period.
  • Milford Fisher (James Fisher Tankers) - arrived alongside on the 24th Jan to commence the replacement of a main engine crankshaft; the vessel      then entered dry dock on the 02nd Feb for general dry docking &  repairs. Once the docking is complete the crankshaft renewal work scope      will continue at the west jetty.
     

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week