Marine Link
Thursday, March 28, 2024

World's Largest: Kincardine Floating Wind Farm Fully Operational

Maritime Activity Reports, Inc.

October 19, 2021

Credit: Cobra Group

Credit: Cobra Group

Kincardine floating offshore wind farm, located 15 km off the coast of Aberdeenshire, is now fully operational, Principle Power, a company that designed the 50MW wind farm's semi-submersible foundations, said Tuesday.

The project, the world's largest of the type, consists of five Vestas V164-9.5 MW and one V80-2 MW turbine, each installed on WindFloat semi-submersible platforms designed by Principle Power.  

The Kincardine project was initiated in 2014 by Allan MacAskill and Lord Nicol Stephen, now both directors of Flotation Energy plc. In 2016 Cobra Group became the main investor in Kincardine Offshore Windfarm Ltd. (KOWL)

Cobra Wind, a subsidiary of Cobra Group, has been responsible for delivery of the project, including engineering, construction, installation and commissioning.

Cobra’s Senior Manager, Jose Antonio Fernández, said: "The Kincardine project is not only the world’s largest. It has also been a fantastic foundation for other joint venture projects between Cobra and Flotation Energy. Our Round 4 success with the 480MW Morecambe project, our 7GW of bids into the Scotwind leasing round, and our White Cross 100MW floating project in the South West are all signs of our confidence in Scotland and the UK Floating wind is set for massive growth in the future - and we want to do more.”

With 50MW of installed capacity, this is the largest floating windfarm in the world. The project also uses the highest-capacity wind turbines ever installed on floating platforms.

Kincardine will generate over 200 GWh of green electricity a year, enough renewable electricity to power more than 50.000 Scottish households. Statkraft will purchase all electrical output from the floating wind project with a guaranteed minimum price per MWh until 2029.

Jaime Altolaguirre, KOWL Project Director from Cobra, said: “The completion of Kincardine comes at a pivotal time in determining Scotland’s leadership in the floating offshore sector. Kincardine offshore windfarm has shown that the largest and most advanced wind turbines available can be installed on floating platforms in the challenging North Sea environment. The project proves that floating wind can play a vital role in tackling climate change not only in Scotland and the UK, but also around the world.”

The Kincardine team has also announced the selection of Aberdeen as its operations and maintenance base.

Jaime Altolaguirre said: “Our local team, managed by Cobra, will be responsible for the day-to-day operations of the project. We will be using Scottish-based companies with proven North Sea capabilities, drawing on their experience maintaining offshore semi-submersibles and platforms over the last 50 years. It could not be a better fit.”

Aaron Smith, Chief Commercial Officer, Principle Power, said: "Kincardine is further showing the readiness and commercial potential of floating technology. With eighty percent of the world’s offshore wind resources in deep water areas, floating technologies like the WindFloat open several new geographies to harness the boundless supply of clean energy contained therein.  The UK has led the way in realizing the potential of floating wind and is now recognized globally as a key market for floating wind developments. Kincardine demonstrates the readiness of floating wind to support the government’s net-zero ambitions ahead of the forthcoming lease awards in ScotWind, floating wind leasing rounds managed by Crown Estate Scotland.”

Nils de Baar, President, Vestas Central & Northern Europe, said: "The Kincardine project shows how boundaries of offshore wind technology are constantly being pushed forward. We have once again demonstrated that the world’s most powerful turbines can be installed on floating substructures. We stand ready for the next phase of commercial scale floating offshore wind. With appropriate policy and regulations, floating technology offers the UK an opportunity to expand its global leadership position in offshore wind and build further opportunities for the domestic supply chain. We are proud to be part of the pioneering Kincardine project.”  

 

Kincardine Floating Offshore Wind

·     Developer: Kincardine Offshore Windfarm Ltd. (KOWL). Established in 2014 by Allan MacAskill and Lord Nicol Stephen. Majority owned by the Cobra Group

·     EPC Contractor: Cobra Wind International Limited (CWIL)

·     Turbines: 5 x Vestas V164-9.525 MW turbines and 1 x V80-2 MW

·     Blade tip height: 190 meters

·     Foundation: WindFloat (floating, semi-submersible type)

·     Project Capacity: 50 MW

·     Location: Aberdeen, Scotland

·     Distance from Shore: 15 km

·     Water Depth: 60-80 meters

·     Nominal Voltage: 33 kV

·     Number of homes powered annually: over 50.000

·     Expected life: at least 25 years

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week