Marine Link
Friday, April 19, 2024

Eastern Cuts Steel for Fourth USCG Offshore Patrol Cutter

Maritime Activity Reports, Inc.

October 18, 2022

(Photo: Eastern Shipbuilding Group)

(Photo: Eastern Shipbuilding Group)

Eastern Shipbuilding Group, Inc. (ESG) commenced construction of U.S. Coast Guard Cutter (USCGC) Rush (WMSM-918), the fourth hull of the Heritage Class Offshore Patrol Cutter (OPC) program. The occasion was observed by leaders of the U.S. Coast Guard Project Resident Office at ESG’s Allanton Shipyard where the first steel plates were cut by ESG personnel in the builder’s 103,000-square-foot steel and aluminum processing facility.

“The first four offshore patrol cutters are fully under production for the U.S. Coast Guard thanks to the steadfast commitment of our skilled professionals and partners,” said Joey D’Isernia, President of Eastern Shipbuilding Group. “USCGC Rush is part of a class of ships that boast multi-mission capabilities and the endurance to carry the men and women of the USCG for more than half a century. With more than 45 years of steel shipbuilding experience we promise the highest quality control, and we look forward to delivering the lead vessel of the class next year.”

In addition, Eastern noted that the U.S. Coast Guard modified its contract on May 20 “so installation of the Athena combat weapons system and multi-mode radar system will be completed during the production phase of the OPC. The Athena system, radar and armament of the OPC are provided to the Coast Guard as Navy type-Navy owned government furnished equipment.

“Prior to this modification, installation of both systems was to occur after contract delivery while each cutter was in its homeport. The Navy has completed development, integration and testing of the Athena and radar systems, enabling the Coast Guard to shift to production-phase installation. Performing this work prior to delivery reduces the technical risks associated with post-delivery installation and delivers mission-ready OPCs to the fleet as soon as possible.”

By implementing these modifications now, ESG expects that it will deliver capability years ahead of a post-delivery integration strategy, the company said. This additional scope of work results in a new delivery date in 2023 for the lead cutter Argus which is 75% complete. The second OPC is approximately 50% complete, and the third is 25% complete. The fourth OPC is scheduled for delivery in 2026.

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week