Baker Hughes to Supply Tech for Offshore LNG Project in Texas
Baker Hughes has secured a contract to supply gas compression and power generation technology for ST LNG’s proposed 8.4 million tonnes per annum liquefied natural gas export terminal offshore Matagorda in Texas.Under the agreement, Baker Hughes will provide two LM6000PF gas turbine-driven centrifugal compressor trains and three NovaLT16 gas turbine generator packages for the first phase of the project, which is expected to deliver 2.1 MTPA as part of a planned four-phase development.The project, located in U.S.
Novatek's Murmansk LNG Project to Initially Have Two Lines Per Year
Russian natural gas giant Novatek's Murmansk LNG project is expected to have two lines of 6.8 million tonnes per year each, draft project documentation seen by Reuters showed on Monday.Construction of the Murmansk LNG project in Russia's Arctic is scheduled for 2027-2030, the documentation showed.According to the draft project, the annual loading volume is projected to be 3.4 million tonnes in 2028, rising to 6.8 million tonnes in 2029.
Freeport LNG Reaches Milestone
Freeport LNG has reached final commissioning on Train 1 of its liquefaction project on Quintana Island in Freeport, Texas, following months of construction delays.American multinational engineering firm McDermott International along with its partners, Chiyoda International Corporation and Zachry Group, announced that crews have introduced feed gas into Train 1 of the liquefied natural gas export terminal.When fully operational, Train 1 will produce more than 5M metric tons/year of LNG, said a joint press release."We are extremely proud of the Freeport LNG project team for reaching this major milestone at this unique LNG production facility…
Sempra's Cameron LNG Terminal Ships First Cargo
Sempra Energy said on Friday the $10 billion Cameron liquefied natural gas export terminal in Louisiana had shipped its first cargo, making the plant the fourth big LNG export terminal to enter service in the United States.Mitsui & Co Ltd, one of the partners in the Cameron project, chartered the tanker, Marvel Crane, to pick up the commissioning cargo.It was not immediately clear where the vessel was headed.Sempra said commissioning cargos were a critical step in the start-up process. The plant is expected to get federal authorization to enter commercial operations in mid-2019.Natural gas use is growing fast around the world as countries seek to wean their industrial and power sectors off dirtier coal.There are three liquefaction trains at Cameron.
FERC Approves Venture Global LNG Terminal
The Federal Energy Regulatory Commission (FERC) cleared Venture Global Calcasieu Pass LLC’s proposed liquefied natural gas export project in Cameron Parish, Louisiana, marking the first authorization in two years for a new LNG export facility.Venture Global LNG Inc. said it will start construction immediately on its $5 billion Calcasieu Pass liquefied natural gas export terminal in Louisiana. FERC also cleared TransCameron Pipeline LLC’s associated natural gas pipeline."With our FERC order in hand and our project contracted with binding 20-year sale and purchase agreements (SPAs) with Shell, BP, Edison S.p.A., Galp, Repsol and PGNiG…
BP, ExxonMobil, ConocoPhillips 'Quit' Alaska LNG Project
BP, Conoco Phillips, and Exxon Mobil said that the 65-billion dollar megaproject would be too unprofitable for them to move into the next phase of development. The Big 3 oil companies have told state lawmakers that the proposal on the table to pipe, liquefy and export North Slope natural gas is uneconomic and they won't move forward as partners. However, they said they would sell their natural gas to a state-developed project if it comes to fruition, which is more in doubt than ever. A report in WSJ said that Exxon Mobil Corp. has decided not to invest in the next stage of a proposed natural gas export terminal in Alaska and said it would work with its partners to sell its interest in the project to the state government.
U.S. Okays ConocoPhillips Alaska LNG Exports
The U.S. Department of Energy approved ConocoPhillips' application to export about 40 billion cubic feet of natural gas from its Kenai liquefied natural gas export terminal in Alaska over the next two years starting Feb. 19. The Kenai facility was the first LNG export facility in the United States. Most of the gas exports from Kenai have gone to Japan since the plant entered service in 1969. In a few weeks, the fist LNG export terminal in the lower 48 states is expected to enter service at Cheniere Energy Inc's Sabine Pass facility in Louisiana. The federal approval will allow ConocoPhillips to export gas to any country the United States has a free-trade agreement with or any other country with which trade is not prohibited by U.S. law.
Canada Approves Pipeline to Feed Pacific LNG Plant
The Canadian government has approved TransCanada Corp's proposed C$1.7 billion ($1.38 billion) North Montney Mainline natural gas pipeline that would connect natural gas fields in northern British Columbia with a Pacific Coast export terminal. The North Montney line would feed into a second new pipeline, the Prince Rupert Gas Transmission line, that would serve an $11 billion liquefied natural gas export terminal, called the Pacific NorthWest LNG project, proposed by state-owned Malaysian energy company Petronas. The federal natural resources department announced the North Montney approval late on Wednesday. In April, the Canadian regulator…
Petronas Delays Canadian LNG Project
Petronas, Malaysia's state-owned oil and gas company, delayed giving the final investment go-ahead on Wednesday for its $11 billion liquefied natural gas export terminal in British Columbia, citing high costs and other outstanding issues. "Costs associated with the pipeline and LNG facility remain challenging and must be reduced further before a positive FID (final investment decision) can be undertaken," the company said in a statement. Petronas, which had hoped to give the project the green light before yearend, said it will continue to invest in natural gas in British Columbia and will keep working to secure necessary federal approvals and permits for the project. (Reporting by Julie Gordon; Editing by Peter Galloway, Reuters)
BG Group to Delay LNG Terminal on Canada's Pacific Coast
British oil and gas producer BG Group Plc will delay until the next decade a proposed liquefied natural gas export terminal on Canada's Pacific coast, the Wall Street Journal reported, quoting the head of the company's Canadian unit. "We'd always said (construction would begin) as early as 2016, but we now recognize it'll likely be later, with commercial operations likely beginning early in the next decade," BG Canada President Madeline Whitaker said in an interview with the Journal. Kim Blomley, a spokesman for BG Group, said he could not immediately confirm if the project had slipped into the next decade, but he noted comments by interim Executive Chairman Andrew Gould during a post-earnings conference call on Tuesday.
US FERC Approves Sempra LNG Export Project
U.S. regulators on Thursday approved Sempra Energy's bid to build a liquefied natural gas export terminal in Louisiana, opening the door to a significant expansion of the American role in global gas trade. Sempra's Cameron LNG facility was the second gas export project to get the green light to begin construction from the Federal Energy Regulatory Commission and the first since 2012, when FERC permitted Cheniere's Sabine Pass project. With the FERC approval in hand, Cameron will likely soon receive its final permit from the Energy Department allowing the facility to export gas to all countries, which would make it the only project outside of Sabine Pass fully licensed at the federal level.
Kitimat LNG, Apache MOU
Kitimat LNG Inc. announced that it has signed a memorandum of understanding (MOU) with Apache Corporation to supply natural gas to Kitimat LNG's proposed liquefied natural gas export terminal. The MOU sets a framework for Kitimat and Apache to negotiate a definitive agreement to supply 200 million to 300 million cubic feet (MMcf) of natural gas feedstock per day to the terminal, which has a planned capacity of 700 MMcf per day. Apache also obtained an option to purchase an equity stake in the Kitimat LNG terminal. As natural gas supply and reserves continue to increase in North America, Kitimat LNG's terminal will provide producers in Canada such as Apache with secure access to key worldwide markets.